Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.
- A、Integration
- B、Scope
- C、Configuration
- D、Requirement
参考答案
更多 “ Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.A、IntegrationB、ScopeC、ConfigurationD、Requirement” 相关考题
考题
In the project management context()includes characteristics of unification,consolidation, articulation, and integrative actions that are crucial to project completion,successfully meeting customer and other stakeholder requirements, and managing expectations.A.integrationB.scopeC.processD.charter
考题
The()describes, in detail, the project's deliverables and the work required to create those deliverables.
A.project scope statementB.project requirementC.project charterD.product specification
考题
In the project management context,() includes characteristics of unification, consolidation, articulation, and integrative actions that are crucial to project completion, successfully meeting customer and other stakeholder requirements, and managing expectations.A.IntegrationB.ScopeC.ConfigurationD.Requirement
考题
● Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other. (74) is following the process- Estimate Activity Durations.(74)A.Develop ScheduleB.Estimate Activity ResourcesC.Define ActivitiesD.Sequence Activities
考题
● Project (69) Management includes the processes required to ensure thatthe project includes all the work required, and only the work required, tocomplete the project successfully.tA.IntegrationB.ScopeC.ConfigurationD.Requiremen
考题
Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other.______is following the process-Estimate Activity Durations.A.Develop ScheduleB.Estimate Activity ResourcesC.Define ActivitiesD.Sequence Activities
考题
Project()Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval,and ultimate disposition of project information.() A.Integration B.Time C.Planning D.Communication
考题
A project management technique that is currently in widespread use is the (73). The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives.A.Structure ChartB.Organizational StructureC.Work Breakdown StructureD.Functional decomposition diagram
考题
The( )is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables.
A、project scope statementB、work packageC、WBSD、project scope plan
考题
Project (75).Management:includes the processes required to ensure that the project includes au the word required, and only the work required, to complete the project successfully.A.IntegrationB.ConfigurationC.ScopeD.Requirement
考题
In the project management context,(68)includes characteristics of unification, consolidation, articulation, and integrative actions that are crucial to project completion, successfully meeting customer and other stakeholder requirements, and managing expectations.A.integrationB.scopeC.processD.charter
考题
Project(69)Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.A.IntegrationB.ScopeC.ConfigurationD.Requirement
考题
Project(74)Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.A.IntegrationB.TimeC.PlanningD.Communication
考题
The ()describes, in detail, the project’s deliverables and the work required to create those deliverables.A.project scope statement
B.project requirement
C.project charter
D.product specification
考题
A project management technique that is currently in widespread use is the ( ) . The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives.A.Functional decomposition diagram
B.Work Breakdown Structure
C.Structure Chart
D.Organizational Structure
考题
()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.A:Create scopE
B:Project stakeholder management
C:Project scope management
D:Project cost management
考题
Project Integration Management includes the processes and activities to identify,define,combine,unify,and coordinate the various processes and project management activities within the Project Management Process Groups.( )process does not belong to Project Integration Management.A.Developing project charter
B.Developing project management plan
C.Analyzing project risks
D.Monitoring and controlling project
考题
The()is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables.A.Project scope statement
B.Work package
C.WBS
D.Project scope plan
考题
()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.A. Create scopE
B. Project stakeholder management
C. Project scope management
D. Project cost management
考题
()describes, in detail, the project’s deliverables and the work required to create those deliverables.A、Product scope descriptionB、Project objectivesC、Stakeholder AnalysisD、The project scope statement
考题
The () describes, in detail, the project's deliverables and the work required to create those deliverables.A、project scope statementB、project requirementC、project charterD、product specification
考题
Project() Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.A、IntegrationB、TimeC、PlanningD、Communication
考题
Project()Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage,retrieval, and ultimate disposition ofproject information.A、IntegrationB、TimeC、PlanningD、Communication
考题
Project()Management includes the processes required to ensure that theproj ect includes all the work required, and only the work required, to complete the project successfully.A、IntegrationB、ScopeC、ConfigurationD、Requirement
考题
单选题Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.A
IntegrationB
ScopeC
ConfigurationD
Requirement
考题
单选题Project()Management includes the processes required to ensure that theproj ect includes all the work required, and only the work required, to complete the project successfully.A
IntegrationB
ScopeC
ConfigurationD
Requirement
考题
单选题Project() Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.A
IntegrationB
TimeC
PlanningD
Communication