“Cost of quality”is a project management concept that includes cost of( 73)

A.exceedings requirements

B.Changes to the requirements

C.Ensuring conformance to requirements

D.The quality control requirements


参考答案

更多 “ “Cost of quality”is a project management concept that includes cost of( 73)A.exceedings requirementsB.Changes to the requirementsC.Ensuring conformance to requirementsD.The quality control requirements ” 相关考题
考题 Project tradeoffs are usually made by comparing _____ and constraints.ATime, cost, and qualityBTime, risk, and qualityCRisk, quality, and manpower availabilityDCost, quality, and technical performanceECost, quality, and risk

考题 What is the relative priority of project Cost, Schedule and Quality?A . 1)Cost - 2)Schedule - 3)QualityB . 1)Quality - 2)Schedule - 3)CostC . 1)Quality - 2)Cost - 3)ScheduleD . 1)Schedule - 2)Quality - 3)CostE . All are of equal priority

考题 130 What is the relative priority of project Cost, Schedule and Quality?A. 1)Cost - 2)Schedule - 3)QualityB. 1)Quality - 2)Schedule - 3)CostC. 1)Quality - 2)Cost - 3)ScheduleD. 1)Schedule - 2)Quality - 3)CostE. All are of equal priority

考题 12 What is the relative priority of project Cost, Schedule and Quality?A. 1)Cost - 2)Schedule - 3)QualityB. 1)Quality - 2)Schedule - 3)CostC. 1)Quality - 2)Cost - 3)ScheduleD. 1)Schedule - 2)Quality - 3)CostE. All are of equal priority

考题 3 Project tradeoffs are usually made by comparing _____ and constraints.A. Time, cost, and qualityB. Time, risk, and qualityC. Risk, quality, and manpower availabilityD. Cost, quality, and technical performanceE. Cost, quality, and risk

考题 85 Project tradeoffs are usually made by comparing _____ and constraints.A. Time, cost, and qualityB. Time, risk, and qualityC. Risk, quality, and manpower availabilityD. Cost, quality, and technical performanceE. Cost, quality, and risk

考题 ● Project tradeoffs are usually made by comparing _____ and constraints.A Time, cost, and qualityB Time, risk, and qualityC Risk, quality, and manpower availabilityD Cost, quality, and technical performanceE Cost, quality, and risk

考题 ● Project()is an uncertain event or condition that ,if it occurs ,has a positive or a negative effect on at least one project objective ,such as time ,cost ,scope or quality()A. risk B. problem C. result D. data

考题 Project()is an uncertain event or condition that,if it occurs,has a positiveor a negative effect on at least one project objective,such as time,cost,scope, or quality.A.risk B.problem C.result D.data

考题 Project( )is an uncertain event or condition that,if it occurs,has a positive or a negative effect on at least one project objective,such as time,cost,scope,or quality.A.risk B.problem C.result D.data