● The scope baseline/project charter is prepared by the:

A Project manager

B Project manager and project office

C Project manager, project office and functional team

D Project manager, project office, functional team and project sponsor

E Project manager, project sponsor and customer/user


参考答案

更多 “ ● The scope baseline/project charter is prepared by the:A Project managerB Project manager and project officeC Project manager, project office and functional teamD Project manager, project office, functional team and project sponsorE Project manager, project sponsor and customer/user ” 相关考题
考题 The identification, definition, and selection of the project objectives as well as the best approach to achieving the project objectives are indentified in the _____ phase of the project but first documented in the project _____.A.Conceptual, charter/baseline.B.Conceptual, master schedule.C.Development, charter/baseline.D.Development, master schedule.E.Development, masterplan.

考题 130 The identification, definition, and selection of the project objectives as well as the best approach to achieving the project objectives are indentified in the _____ phase of the project but first documented in the project _____.A. Conceptual, charter/baseline.B. Conceptual, master schedule.C. Development, charter/baseline.D. Development, master schedule.E. Development, masterplan

考题 12 The identification, definition, and selection of the project objectives as well as the best approach to achieving the project objectives are indentified in the _____ phase of the project but first documented in the project _____.A. Conceptual, charter/baseline.B. Conceptual, master schedule.C. Development, charter/baseline.D. Development, master schedule.E. Development, masterplan

考题 ● Middle (functional) managers have the greatest influence in the direction of the project in which type of organizational structure?A Project.B Strong matrix.C Weak matrix.D Project coordinator.E Project expeditor.

考题 ● The identification, definition, and selection of the project objectives as well as the best approach to achieving the project objectives are indentified in the _____ phase of the project but first documented in the project _____.A Conceptual, charter/baseline.B Conceptual, master schedule.C Development, charter/baseline.D Development, master schedule.E Development, masterplan.

考题 ● Project(71)is an uncertain event or condition that, if it occurs, has a positive or a negative effect on at least one project objective, such as time, cost, scope, or quality.(71)A.riskB.problemC.resultD.data

考题 Project ______is an uncertain event or condition that,if it occurs,has a positive or a negative effect on at least one project objective,such as time,cost,scope,or quality.A.riskB.problemC.resultD.data

考题 Project(71)is an uncertain event or condition that,if it occurs,has a positive or a negative effect on at least one project objective,such as time,cost,scope,or quality.A.riskB.problemC.resultD.data

考题 Project()is an uncertain event or condition that,if it occurs,has a positiveor a negative effect on at least one project objective,such as time,cost,scope, or quality.A.risk B.problem C.result D.data