网友您好, 请在下方输入框内输入要搜索的题目:
题目内容
(请给出正确答案)
单选题
ETP hopes to finish this project in_____.
A
2016
B
2017
C
2018
D
2019
参考答案
参考解析
解析:
更多 “单选题ETP hopes to finish this project in_____.A 2016B 2017C 2018D 2019” 相关考题
考题
Which of the following is indicative of negative float?A.The late start date is earlier than the early start date.B.The critical path supports the imposed end date.C.The early finish date is equal to the late finish date.D.When leads are employed in the schedule.E.The project is sinking.
考题
Free float is the amount of time that an activity may be delayed with out affecting the _____.A.Early start of the succeeding activities.B.Late start of the succeeding activities.C.Project finish.D.Cost of the project.E.None of the above.
考题
● Which of the following is indicative of negative float?A The late start date is earlier than the early start date.B The critical path supports the imposed end date.C The early finish date is equal to the late finish date.D When leads are employed in the schedule.E The project is sinking.
考题
● The most frequently used construct in Precedent Diagramming Method is:A Start to Start.B Finish to Finish.C Start to Finish.D Finish to Start.E Dummy activity.
考题
● Free float is the amount of time that an activity may be delayed with out affecting the _____.A Early start of the succeeding activities.B Late start of the succeeding activities.C Project finish.D Cost of the project.E None of the above.
考题
Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to(75) progress.A.analyzeB.trackC.levelD.extend
考题
●Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to (75) progress.(75)A. analyzeB. trackC. levelD. extend
考题
--- What' s the matter with Della?--- Well, her parents wouldn't allow her to go to the party, but she still __. A. hopes toB. hopes soC. hopes notD. hopes for
考题
-Are the Project Managers linking up OK? -They seem to be, yes._________ .
A One of them hopes to quit now ;B There's been a good atmosphere at the first management meetings ;C They don't seem to know each other
考题
I______ all my work before I________.A、finish, leaveB、finishes, leavesC、will finish, will leaveD、will finish, leave
考题
A()is a type of bar chart that illustrates a project schedule. It illustrates the start and finish dates of the terminal elements and summary elements of a project.A.gantt chartB.project histogramC.milestone chartD.project flowchart
考题
A__(74)__is a type of bar chart that illustrates a project schedulA.It illustrates the start and finish dates of the terminal elements and summary elements of a project.B.Gantt chartC.project histogramD.milestone chartE.project flowchart
考题
Establishing a project management timetable involves listing milestones,activities,and()with intended start and finish dates,of which the scheduling of employees may be an elementA.relationshipsB.resourcesC.stakeholdersD.deliverables
考题
In project management , a (1) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource (2) ,budget and duration, linked by dependencies and scheduled events.A.scheduleB.activityC.planD.contractor@@@SXB@@@A.findingB.balanceC.allocationD.distribution
考题
Establishing a project ( ) involves listing milestones, activities, and deliverables with intended start and finish dates, of which the scheduling of employees may be an element.A.cost management planB.risk management planC.scope management planD.management schedule
考题
Establishing a project ( ) involves listen milestones, activities, and deliverables with intendstart and finish dates^of which the scheduling of employees may be an element.A.cost management planB.risk managementC.scope management planD.management schedule
考题
--- What' s the matter with Della?--- Well, her parents wouldn't allow her to go to the party, but she still __A. hopes to B. hopes so C. hopes not D. hopes for
考题
Establishing a project(74)involves listen mile stones,activities,and deliverables with intend start and finish dates of which the scheduling of employees may be an element.A.cost management plan
B.risk management
C.scope management plan
D.management schedule
考题
( ) is a type of bar chart that illustrates a project schedule. It illustrates the start and finish dates of the terminal elements and summary elements of a project. A.gantt chart
B.project histogram
C.milestone chart
D.project flowchart
考题
Developing the project schedule is often an
iterative process. It determines the planned start and finish dates for project
activities and milestones. Schedule development can require the review and
revision of duration estimates and resource estimates to create an approved
project schedule that can serve as a baseline to ( ) progress. A.analyze
B.track
C.level
D.extenD.
考题
()is a type of bar chart that illustrates a project schedule. It illustrates the start and finish dates of the terminal elements and summary elements of a project.A、gantt chartB、project histogramC、milestone chartD、project flowchart
考题
单选题Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to()progress.A
analyzeB
trackC
levelD
extend
考题
单选题— ______ I know by what time you want the project to be done?—By the day after tomorrow. ______ you finish it on time?A
May; CanB
Must ; NeedC
Could ; MustD
Need ; Would
考题
单选题Mr. Agent, do you know()?A
when can the stevedores finish loadingB
when will the stevedores finish loadingC
when the stevedores can finish loadingD
when the stevedores finish loading can
热门标签
最新试卷