网友您好, 请在下方输入框内输入要搜索的题目:

题目内容 (请给出正确答案)

Expectancy theory as applied to project management implies that:

A The team will work the hardest on those goals that are clearly explained by the project manager

B The more rewards that the project manager provides, the better the performance of the team

C Team members will work hardest for those project goals that also bring satisfaction to personal goals

D Employees will work hardest for those project goals which are accompanied by high levels of authority for the individual team members

E None of the above


参考答案

更多 “ Expectancy theory as applied to project management implies that:A The team will work the hardest on those goals that are clearly explained by the project managerB The more rewards that the project manager provides, the better the performance of the teamC Team members will work hardest for those project goals that also bring satisfaction to personal goalsD Employees will work hardest for those project goals which are accompanied by high levels of authority for the individual team membersE None of the above ” 相关考题
考题 The scope baseline/project charter is prepared by the:AProject managerBProject manager and project officeCProject manager, project office and functional teamDProject manager, project office, functional team and project sponsorEProject manager, project sponsor and customer/user

考题 Scheduling systems such as PERT, ADM, and PDM are project management tools to be used by:A.The project manager and project office personnel.B.The project team and functional managers.C.The project sponsor.D.All of the above.E.A and B only.

考题 Team members want to work for a project manager that can provide them with career path planning. In which organizational form. is career path planning difficult for project employees?A . MatrixB . Pure projectC . Project coordinatorD . Project expediterE . Classical/traditional

考题 Ouchi's Theory Z relates more to _____ whereas Theory X / Theory Y relates to _____ .A . Project managers; team membersB . Company management philosophy in treating employees; the average workerC . Project sponsors; project managersD . The functional team; project sponsorsE . Recruitment policy; wage and salary administration

考题 In a matrix organizational form, MBO may be difficult to implement:A . If the functional employees are supervised closely by the line manager rather than the project managerB . Unless the project manager has an input into the employee's performance reviewC . Unless the project and line managers agree on the ultimate objectiveD . Unless the project and line managers agree to the duration of the taskE . None of the above are correct answers

考题 156 Expectancy theory as applied to project management implies that:A. The team will work the hardest on those goals that are clearly explained by the project managerB. The more rewards that the project manager provides, the better the performance of the teamC. Team members will work hardest for those project goals that also bring satisfaction to personal goalsD. Employees will work hardest for those project goals which are accompanied by high levels of authority for the individual team members E. None of the above

考题 189 Ouchi's Theory Z relates more to _____ whereas Theory X / Theory Y relates to _____ .A. Project managers; team membersB. Company management philosophy in treating employees; the average workerC. Project sponsors; project managersD. The functional team; project sponsorsE. Recruitment policy; wage and salary administration

考题 123 The scope baseline/project charter is prepared by the:A. Project managerB. Project manager and project officeC. Project manager, project office and functional teamD. Project manager, project office, functional team and project sponsorE. Project manager, project sponsor and customer/user

考题 ● The scope baseline/project charter is prepared by the:A Project managerB Project manager and project officeC Project manager, project office and functional teamD Project manager, project office, functional team and project sponsorE Project manager, project sponsor and customer/user

考题 ● Scheduling systems such as PERT, ADM, and PDM are project management tools to be used by:A The project manager and project office personnel.B The project team and functional managers.C The project sponsor.D All of the above.E A and B only.

考题 ●To ensure the project team provides the functionality the customerexpects in a new piece of software, the project manager ask the customer forsign-off on the design criteria. These documents are(75).(75) A. technical specificationsB. performance specificationsC. product descriptionsD. quality assurance

考题 are individuals and organizations that are actively involved in the project,or whose interests may be affected as a result of project execution or project completion.A.Project managerB.Project team memberC.SponsorD.Proiect stakeholders

考题 The(70)provides the project manager with the authority to apply organizational resources to project activities.A.project management planB.contractC.project human resource planD.project charter

考题 Risk management allows the project manager and the project team not to(71). A.eliminate most risks during the planning phase of the project B.identify project risks C.identify impacts of various risks D.plan suitable responses

考题 The( )provides the project manager with the authority to apply organizational resources to project activities。 A.project management plan B.project charter C.project human resource plan D.project stakeholders

考题 The( )provides the project manager with the authority to apply organizational resources to project activities。A.project management planB.project charterC.project human resource planD.project stakeholders

考题 The earned value technique is a commonly used method of performance measurement.It integrates project scope,schedule,and cost measures to help the project management team assess project performance.If a project’s Cost Performance Index(CPI=EV/AC)value less than 1.0,it means that( )。 A.the cost savings for work completed B.the project is ahead of its planned schedule C.the cost overrun for work completed D.1ess work was completed than was planned

考题 The earned value technique is a commonlyused method of performance measurement. It integrates project scope, cost, andschedule measures to help the project management team assess projectperformance.If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, itmeans that (74).A.the project is ahead of its planned scheduleB.less work was completed than was plannedC.the cost overrun for work completedD.the cost under-run of performance to date

考题 The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performancIf a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that __(74)__.A.the project is ahead of its planned scheduleB.less work was completed than was plannedC.the cost overrun for work completedD.the cost under-run of performance to date

考题 The (73) provides the project manager with the authority to apply organizational resources to project activities.A.project management planB.project charterC.project human resource planD.project stakeholders

考题 The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than1.0, it means that_().A.the project is a head of its planned schedule B.less work was completed than was planned C.the cost overrun for work completed D.the cost under-run of performance to date

考题 In project management and systems engineering,( )is a deliverable-oriented breakdown of a project into smaller components.It is a key project deliverable that organizes the team's work into manageable sections.A.RBS B.PBS C.GBS D.WBS

考题 Earned value management(EVM)integrates the scope baseline with the()baseline,along with schedule baseline,to form the performance,which helps the project management team assess and measure project performance and progress.A.qulity B.risk C.change D.cost

考题 The()provides the project manager with the authority to apply organizational resources to project activities.A、project management planB、contractC、project human resource planD、project charter

考题 The()provides the project manager with the authority to apply organizational resources to project activities.A、project management planB、contractC、project human resource planD、projectcharter

考题 单选题The()provides the project manager with the authority to apply organizational resources to project activities.A project management planB contractC project human resource planD projectcharter

考题 单选题The()provides the project manager with the authority to apply organizational resources to project activities.A project management planB contractC project human resource planD project charter