网友您好, 请在下方输入框内输入要搜索的题目:

题目内容 (请给出正确答案)
单选题
Team member listing, scheduled tasks, and risk identification are part of the:()
A

project plan.

B

project charter.

C

communication plan.

D

WBS (Work Breakdown Structure).


参考答案

参考解析
解析: 暂无解析
更多 “单选题Team member listing, scheduled tasks, and risk identification are part of the:()A project plan.B project charter.C communication plan.D WBS (Work Breakdown Structure).” 相关考题
考题 A work breakdown structure:A . assures all work is identified.B . subdivides the project into manageable segments.C . provides the project sponsor with a time-phase task summary.D . both A and B.E . All of the above.

考题 When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at theA.taskB.level of effortC.sub-taskD.projectE.work package

考题 A Work Breakdown Structure:A.assures all work is identifiedB.subdivides the project into manageable segmentsC.provides the project sponsor with a time-phase task summaryD.both A and BE.All of the above.

考题 The Work Breakdown Structure (WBS) is the basis for communicating:A.Project scope, cost control, schedule, qualityB.Project objectives, dependencies, plan, cost controlC.Project scope, schedule, staffing, cost controlD.Project scope, quality, schedule, dependenciesE.Project budget, schedule, risk factors, work assignments.

考题 The starting point in the development of a top-down PERT/CPM chart is the _____ .A.Project specification tree.B.Customer's deliverable list.C.Customer's milestone dates.D.Work breakdown structure.E.Listing of customer team meeting dates.

考题 The primary source document for establishing the content of the Project Status Report is:A The project charterB The Project PlanC The ASTM Project Document GuideD The summary work breakdown structure

考题 Giving a part of project work to a contractor is an example of:A risk mitigationB risk assignmentC risk delegationD risk deflectionE risk assumption

考题 It is useful to conduct project risk assessment according to the project'sA charterB statement of workC Work Breakdown structureD networkE budget

考题 111 It is useful to conduct project risk assessment according to the project'sA. charterB. statement of workC. Work Breakdown structureD. networkE. budget

考题 63 When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at theA. taskB. level of effortC. sub-taskD. projectE. work package

考题 94 The primary source document for establishing the content of the Project Status Report is:A. The project charterB. The Project PlanC. The ASTM Project Document GuideD. The summary work breakdown structure

考题 ● When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at theA taskB level of effortC sub-taskD projectE work package

考题 ● A Work Breakdown Structure:A assures all work is identifiedB subdivides the project into manageable segmentsC provides the project sponsor with a time-phase task summaryD both A and BE All of the above.

考题 ● The Work Breakdown Structure (WBS) is the basis for communicating:A Project scope, cost control, schedule, qualityB Project objectives, dependencies, plan, cost controlC Project scope, schedule, staffing, cost controlD Project scope, quality, schedule, dependenciesE Project budget, schedule, risk factors, work assignments.

考题 ● The starting point in the development of a top-down PERT/CPM chart is the _____ .A Project specification tree.B Customer's deliverable list.C Customer's milestone dates.D Work breakdown structure.E Listing of customer team meeting dates.

考题 A project management technique that is currently in widespread use is the(71) . The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives. There are some special activities called(72) , which are events that signify the accomplishment or completion of major deliverables during the project. Most system development methodologies also provide(73), whose purpose is to contain the various pieces of relevant information-feasibility assessments, schedules, needs analysis, and so forth-in a single place so that they can be presented to project clients and other related parties. Several types of important network diagrams are used in project management.(74) was developed to make clear the interdependence between project tasks before those tasks are scheduled.(75) offers the advantage of clearly showing overlapping tasks.A.Structure ChartB.Organizational StructureC.Work Breakdown StructureD.Functional decomposition diagram

考题 ● A work breakdown structure (WBS) is a tool used to define and group a project's discrete work elements in a way that helps organize and define the total work scope of the project. A WBS is most useful for(72) .(72)A.identifying individual tasks for a projectB.scheduling the start of tasksC.scheduling the end of tasksD.determining potential delays

考题 A schedule is commonly used in project planning and project portfolio management.(73) on a schedule may be closely related to the work breakdown structure(WBS)terminal elements.the statement of work.or a contract data requirements listA.EssencesB.ElementsC.PurposesD. Issues

考题 The work breakdown structure (WBS) has been widely used in management for software development project, ( ) is generally NOT validated through the WBS.A.Schedule and costB.Organization structuringC.Management coordinationD.Quality of work

考题 The creation of a work breakdown structure (WBS) is the process of______the major project deliverables.A.subdividingB.assessingC.planningD.integrating

考题 A project management technique that is currently in widespread use is the ( ) . The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives.A.Functional decomposition diagram B.Work Breakdown Structure C.Structure Chart D.Organizational Structure

考题 A schedule is commonly used in project planning and project portfolio management.( ) on a schedule may be closely related to the work breakdown structure (WBS)terminal elements, the statement of work, or a contract data requirements list. A.Essences B.Elements C.Purposes D.Issues

考题 In project management and systems engineering,( )is a deliverable-oriented breakdown of a project into smaller components.It is a key project deliverable that organizes the team's work into manageable sections.A.RBS B.PBS C.GBS D.WBS

考题 The creation of a work breakdown structure(WBS)is the process of ( ) the major project deliverables. A.subdividing B.assessing C.planning D.integrating

考题 The project manager is developing a project schedule. The project manager negotiated with all the execution organizations, and the task times are as short as possible. After manipulating the schedule, the project completion date is still beyond the date requested by the business owners of the project. The project manager believes that the content agreed on for the project is appropriate, and concludes that this schedule should be taken to the business owners and renegotiated. Which one of the following tools will help the project manager justify the revised schedule?()A、Data flow modelB、The project critical pathC、Resource loading chartD、WBS (Work Breakdown Structure)

考题 Team member listing, scheduled tasks, and risk identification are part of the:()A、project plan.B、project charter.C、communication plan.D、WBS (Work Breakdown Structure).

考题 单选题The creation ofa work breakdown structure (WBS) is the process of()the major project deliverables.A subdividingB assessingC planningD integrating