In the project management context,() includes characteristics of unification, consolidation, articulation, and integrative actions that are crucial to project completion, successfully meeting customer and other stakeholder requirements, and managing expectations.
A

Integration

B

Scope

C

Configuration

D

Requirement


参考答案

参考解析
解析: 暂无解析
更多 “单选题In the project management context,() includes characteristics of unification, consolidation, articulation, and integrative actions that are crucial to project completion, successfully meeting customer and other stakeholder requirements, and managing expectations.A IntegrationB ScopeC ConfigurationD Requirement” 相关考题
考题 In the project management context()includes characteristics of unification,consolidation, articulation, and integrative actions that are crucial to project completion,successfully meeting customer and other stakeholder requirements, and managing expectations.A.integrationB.scopeC.processD.charter

考题 ● Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other. (74) is following the process- Estimate Activity Durations.(74)A.Develop ScheduleB.Estimate Activity ResourcesC.Define ActivitiesD.Sequence Activities

考题 ● In the project management context, (68) includes characteristics of unification, consolidation, articulation, and integrative actions that are crucial to project completion, successfully meeting customer and other stakeholder requirements, and managing expectations.A.integrationB.scopeC.processD.charter

考题 ● Project (69) Management includes the processes required to ensure thatthe project includes all the work required, and only the work required, tocomplete the project successfully.tA.IntegrationB.ScopeC.ConfigurationD.Requiremen

考题 Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other.______is following the process-Estimate Activity Durations.A.Develop ScheduleB.Estimate Activity ResourcesC.Define ActivitiesD.Sequence Activities

考题 ● The Develop Project Management Plan Process includes the actions necessary to define, prepare, integrate, and coordinate all constituent plans into a (75)(75)A. Project Scope StatementB. Project Management PlanC. ForecastsD. Project Charter

考题 The Develop Project Management Plan Process includes the actions necessary to define,prepare,integrate,and coordinate all constituent plans into a(75). A.Project Scope Statement B.Project Management Plan C.Forecasts D.Project Charter

考题 Project Quality Management must address the management of the project and the ()of the project.While Project Quality Management applies to all projects, regardless of the nature of their product,product quality measures and techniques are specific to the particular type of product produced by the project.()A.performance B.process C.product D.object

考题 Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups.()process does not belong to Project Integration Management.A.Developing project charterB.Developing project management planC.Analyzing project risksD.Monitoring and controlling project

考题 Project (24) Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.A.IntegrationB.ScopeC.ConfigurationD.Requirement

考题 “Cost of quality”is a project management concept that includes cost of( 73)A.exceedings requirementsB.Changes to the requirementsC.Ensuring conformance to requirementsD.The quality control requirements

考题 The Develop Project Management Plan Process includes the actions necessary to define, prepare, integrate, and coordinate all constituent plans into a (75).A.Project Scope StatementB.Project Management PlanC.ForecastsD.Project Charter

考题 The scope management plan is how the team will prepare the()a document that includes descriptions of create the WBS, verify completion of the project deliverables, and control requests for changes to the project scope.A.project charterB.project scope goalC.project budgetD.project scope statement

考题 The schedule management plan is a component of the project management plan The schedule management plan may be formal or informal, highly detailed or broadly framed, based upon the()of the project, and includes appropriate control thresholds.A.goalsB.valuesC.needsD.Level

考题 The Develop Project Management Plan Process includes the actions necessary to define, prepare,integrate, and coordinate all constituent plans into a ( )A. Project Scope Statement B.Project Management Plan C.Forecasts D.Project Charter

考题 ()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.A:Create scopE B:Project stakeholder management C:Project scope management D:Project cost management

考题 The schedule management plan is a component of the project management plan The schedule management plan maybe formal or informal,highly detailed or broadly framed,based up on the( )of the project,and includes appropriate control thresholds. A.goals B.values C.needs D.Level

考题 The scope management plan is how the team will prepare the( )a document that includes descriptions of create the WBS,verify completion of the project deliverables,and control requests for changes to the project scope. A.project charter B.project scope goal C.project budget D.project scope statement

考题 ()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.A. Create scopE B. Project stakeholder management C. Project scope management D. Project cost management

考题 ( ) is primarily concerned with defining and controlling what is and is not included in the project. A.Project Time Management B.Project Cost Management C.Project Scope Management D.Project Communications Management

考题 The inputs of developing project management plan do not include()A、project charterB、stakeholder management strategyC、project scope statementD、outputs from planning processes

考题 A characteristic of operating system is()。A、 resource  management B、 memory management C、 error recovery D、 all the above

考题 Project()Management includes the processes required to ensure that theproj ect includes all the work required, and only the work required, to complete the project successfully.A、IntegrationB、ScopeC、ConfigurationD、Requirement

考题 Project Quality Management must address the management of the project and the()ofthe project. While Project Quality Management applies to all projects,regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.A、performanceB、processC、productD、object

考题 Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.A、IntegrationB、ScopeC、ConfigurationD、Requirement

考题 You create a Visual Studio 2010 solution that includes a WCF service project and an ASP.NET project. The service includes a method named GetPeople that takes no arguments and returns an array of Person objects. The ASP.NET application uses a proxy class to access the service. You use the Add Service Reference wizard to generate the class. After you create the proxy, you move the service endpoint to a different port. You need to configure the client to use the new service address. In addition, you must change the implementation so that calls to the client proxy will return a List instead of an array. Which two actions should you perform?()A、In the context menu for the service reference in the ASP.NET project, select the Configure Service Reference commSystem.Collections.Generic.ListB、In the context menu for the service reference in the ASP.NET project, select the Update Service Reference commaC、Change the service interface and implementation to return a ListD、Edit the address property of the endpoint element in the web.config file to use the new service address

考题 单选题In the context of GMPLS,LMP stands for().A Loop Management ProtocolB Label Management ProtocolC Load Management ProtocolD Link Management ProtocolE None of above

考题 单选题Project Quality Management must address the management of the project and the() of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.A performanceB processC productD object