单选题
A charterer is unable to complete the loading of a vessel during the lay days specified in the charter party. Under these circumstances,the().
A
vessel operator can collect demurrage
B
ship is authorized extra time to discharge the cargo
C
charterer must pay dispatch money
D
effective period of the charter is extended
参考答案
参考解析
解析:
暂无解析
更多 “单选题A charterer is unable to complete the loading of a vessel during the lay days specified in the charter party. Under these circumstances,the().A vessel operator can collect demurrageB ship is authorized extra time to discharge the cargoC charterer must pay dispatch moneyD effective period of the charter is extended” 相关考题
考题
On a voyage charter party when the vessel is in port the charter will specify a definite period of time for loading or discharging of cargo by the Charterer.This time is called ________ .A.DemurrageB.DispatchC.Days of readinessD.Laydays
考题
On a voyage charter,when a vessel is ready to load cargo,the Master should render to the charterer a ______.A.Notice of ReadinessB.Master Certificate of ServiceC.Shipmasters DeclarationD.Vessel Utilization and Performance Report
考题
A charterer is unable to complete the loading of a vessel during the lay days specified in the charter party. Under these circumstances,the ______.A.vessel operator can collect demurrageB.ship is authorized extra time to discharge the cargoC.charterer must pay dispatch moneyD.effective period of the charter is extended
考题
The final inspection responsibility for seeing that a tank barge is provided with the required equipment and fittings in good and serviceable condition prior to loading cargo rests with the ______.A.terminal operatorB.owner of the bargeC.tankerman or person in charge of loadingD.charterer through the Master of the towing vessel
考题
Delivery of a vessel to a charterer is called ______.A.charteringB.dispatchingC.fixingD.tendering
考题
The Captain enters into the Salvage Contract as the representative of ______.A.the owner of vesselB.the owner of vessel and her cargoC.the owner of vessel,her cargo and freightD.the owner of vessel,her cargo,freight and Charterer
考题
The charterer has completed loading the vessel in 3 days instead of the 5 days agreed to in the charter party.As a result of this,the ______.A.Shipowner may charge for two laydaysB.Charterer may receive dispatch moneyC.Stevedore may collect demurrageD.Consignee may be required to pay a ceaser fee
考题
When loading a container vessel,the operation is basically that of vertical loading.The important factors to be considered when loading containers are port of discharge,______.A.Available dunnage,and chockingB.Crushability,and inherent viceC.Sweat,and weightD.Weight,and refrigeration
考题
While off-loading from an offshore supply vessel with the crane,the wind increases in strength and changes direction significantly,you should ______.A.Expedite off-loadingB.Stop off-loading,but keep the offshore supply vessel in the present locationC.Continue off-loading with no changesD.Move the offshore supply vessel to the downwind side
考题
翻译:shore tallyman to be employed by the vessel at the expenses to the vessel ,both at loading and discharging port
考题
翻译:Under a voyage charterthe time for loading and discharge and the way of calculationthereofas well as the rate of the demurrage that would incur after the expiration of thelaytime and the rate of dispatch money to be paid as a result of the compeltion of loading ordischarge ahead of schedule,shall be fixed by the shipowner and the charterer upon mutualagreement
考题
The Bareboat Chartering means that the vessel is put at the disposal of the Charterer for a certain period employment without any crew.
考题
单选题By the time charter,a Shipowner agrees to place his vessel at the disposal of a Charterer for ().A
a periodB
a tripC
a voyageD
a journey
考题
单选题A breach of the()undertaking of seaworthiness at the port of loading entitles the Charterer to refuse to load.A
suppliedB
compliedC
providedD
implied
考题
单选题A vessel which through some exceptional circumstance is unable to maneuver as required by these Rules and is therefore unable to keep out of the way of another vessel is called().A
a vessel restricted in her ability to maneuverB
a vessel not under commandC
a vessel engaged in fishingD
a vessel constrained by her draught
考题
问答题翻译:Under a voyage charterthe time for loading and discharge and the way of calculationthereofas well as the rate of the demurrage that would incur after the expiration of thelaytime and the rate of dispatch money to be paid as a result of the compeltion of loading ordischarge ahead of schedule,shall be fixed by the shipowner and the charterer upon mutualagreement
考题
单选题When loading a container vessel,the operation is basically that of vertical loading. The important factors to be considered when loading containers are port of discharge,().A
available dunnage,and chockingB
crushability,and inherent viceC
sweat,and weightD
weight,and refrigeration
考题
单选题It is not the Charterer’s duty that().A
he must procure a cargo and bring it alongside the vesselB
he must load a full and complete cargoC
he must load in the time stipulatedD
he must have the vessel tightly secured to the quay where the loading is to take place
考题
问答题翻译:shore tallyman to be employed by the vessel at the expenses to the vessel ,both at loading and discharging port
考题
单选题The certificate of loading required by each vessel carrying grain in bulk is issued by the().A
owner or charterer of the vesselB
American Bureau of ShippingC
shipper of the cargoD
National Cargo Bureau
考题
单选题()loading has not been completed,the Charterer is entitled to delay the vessel’s sailing until the expiration of lay time.A
As long soB
So longC
As longD
So long as
考题
单选题A continuous sounding of a fog-signal apparatus indicates().A
the vessel is in distressB
the vessel has completed loading dangerous cargoC
it is safe to passD
the vessel is anchored
考题
单选题Should it appear that war or blockade would prevent the vessel from safely reaching the port of destination and / or discharging the goods thereat,the Carrier().A
is entitled to discharge the goods at the port of loading or any other safe and convenient place and terminate the contract of carriageB
is not entitled to terminate the contract of carriageC
is not entitled to claim against the shipper or charterer any damage that he will suffer with the cargo on boardD
is entitled to claim freight with the cargo on board
考题
单选题Delivery of a vessel to a charterer is called().A
charteringB
dispatchingC
fixingD
tendering
考题
单选题If the Charterer sends a vessel to an unsafe port,and she is damaged as a result,he will have to indemnify the().A
ReceiverB
Cargo ownerC
ShipownerD
Merchant
考题
单选题The Charterer is entitled to the benefit of the excepted perils during the transit of the goods from storing place to the actual place of loading,provided such transit substantially ()part of the operation of loading.A
has the form of aB
formsC
is in the form of aD
is to form a
考题
单选题The loading of the ship must be done in accordance with().A
the ship’s instructionsB
the terminal’s instructionsC
the port captain’s instructionsD
the charterer’s instructions