If the organizational spending plan has allocated $100,000 for a project, and the high level budget estimate for that project is $200,000; which of the following is accurate?()

  • A、The high level budget estimates are inaccurate
  • B、The organizational spending plan is inaccurate
  • C、The budget is not aligned with the spending plan of the organization
  • D、The detailed bottom up budget will need to be adjusted

参考答案

更多 “If the organizational spending plan has allocated $100,000 for a project, and the high level budget estimate for that project is $200,000; which of the following is accurate?()A、The high level budget estimates are inaccurateB、The organizational spending plan is inaccurateC、The budget is not aligned with the spending plan of the organizationD、The detailed bottom up budget will need to be adjusted” 相关考题
考题 Filling vacant positions by recruiting within the organizationA . Is exempt from equal employment opportunity lawsB . Is less expensive than recruiting externallyC . Can help provide new and innovative ideas to the organizationD . Is more time consuming than recruiting externallyE . A and B

考题 157 Filling vacant positions by recruiting within the organizationA. Is exempt from equal employment opportunity lawsB. Is less expensive than recruiting externallyC. Can help provide new and innovative ideas to the organizationD. Is more time consuming than recruiting externallyE. A and B