在以下可用于风险识别的历史信息中,最不可靠的是:
A、项目档案
B、商业数据库
C、项目小组知识
D、经验数据库
参考答案
更多 “ 在以下可用于风险识别的历史信息中,最不可靠的是:A、项目档案B、商业数据库C、项目小组知识D、经验数据库 ” 相关考题
考题
There are two major types of reserves used on projects. The _____ is for (usually major) scope changes that were not considered as part of the original plan, whereas the _____ is to compensate for minor changes in estimating, escalation factors.A . Management reserve, unplanned allowance fund.B . Management reserve, contingency.C . Contingency fund, management reserve.D . Unplanned allowance fund, budgetary reserve.E . Unplanned reserve, planned reserve.
考题
163 A deficiency in characteristics that render the quality of the material/service unacceptable is usually referred to as:A. defectiveB. defectC. non-conformanceD. poor workmanshipE. lack of fitness for use
考题
105 Conflict management requires problem-solving. Which of the following is often referred to as a problem-solving technique and used extensively in conflict resolution?A. ConfrontationB. CompromiseC. SmoothingD. ForcingE. Withdrawal
考题
77 We assign human and non-human resources in the _____ phase of the budget.A. conceptualB. planningC. developmentD. implementationE. close-out
考题
85 Project tradeoffs are usually made by comparing _____ and constraints.A. Time, cost, and qualityB. Time, risk, and qualityC. Risk, quality, and manpower availabilityD. Cost, quality, and technical performanceE. Cost, quality, and risk
考题
由于缺乏雇员培训和适当的产品控制,缺陷在产品中存在导致重做,它花费了$250,000。生产线的员工应负多少成本损失的责任?a. $75,000b. $37,500c. $145,000d. $150,000
考题
核心计划过程有明确的依赖关系,在大多数项目中要以同样的顺序必须完成。下列哪一项符合核心计划过程的正确顺序:.a. 范围规划--范围定义--活动排序--活动工期估计b. 范围定义--范围规划--活动定义--活动排序--活动工期估计c. 范围规划--范围定义--活动排序--活动定义--活动工期估计d. 活动工期估计--范围规划--范围定义--活动定义--活动排序
考题
完工成本预测计算不包括:( )A.EAC=AC=(BAC-EV)B.EAC=BAC-CVC.EAC=AC=(BAC/CPI)D.A或B