EF=()。
- A、ES+工期估计
- B、LS+工期估计
- C、LS―ES
- D、LF―LS
参考答案
更多 “EF=()。A、ES+工期估计B、LS+工期估计C、LS―ESD、LF―LS” 相关考题
考题
The range of time allowed for an activity to be completed in is the _____.A.Planned time (Duration).B.Float time (LS - ES, or LF - EF).C.Critical time (when ES = LS, or EF = LF).D.Scheduled time (LF - ES).E.Event.
考题
153 The range of time allowed for an activity to be completed in is the _____.A. Planned time (Duration).B. Float time (LS - ES, or LF - EF).C. Critical time (when ES = LS, or EF = LF).D. Scheduled time (LF - ES).E. Event
考题
35 The range of time allowed for an activity to be completed in is the _____.A. Planned time (Duration).B. Float time (LS - ES, or LF - EF).C. Critical time (when ES = LS, or EF = LF).D. Scheduled time (LF - ES).E. Event.
考题
● The range of time allowed for an activity to be completed in is the _____.A Planned time (Duration).B Float time (LS - ES, or LF - EF).C Critical time (when ES = LS, or EF = LF).D Scheduled time (LF - ES).E Event.
考题
阅读下列说明,回答问题1至问题3,将解答填入的对应栏内。[说明]下图为某项目主要工作的单代号网络图。工期以工作日为单位。请在图中填写各活动的最早开始时间(ES)、最早结束时间(EF)、最晚开始时间 (LS)、最晚结束时间(LF),从第0天开始计算。
考题
按工程进度绘制的资金使用计划S曲线必然包括在“香蕉图”内,该“香蕉图”是由工程网络计划中全部工作分别按( )绘制的两条S曲线组成。A:最早开始时间(ES)开始和最早完成时间(EF)完成
B:最早开始时间(ES)开始和最迟开始时间(LS)开始
C:最迟开始时间(LS)开始和最早完成时间(EF)完成
D:最迟开始时间(LS)开始和最迟完成时间(LF)完成
考题
已知某工程的网络计划中相关资料如下表所示。
问题:1.根据上表绘制网络计划图。2.计算总工期,以及网络图中各工作的六个时间参数(ES、EF、LS、LF、TF、FF)。3.写出关键线路(工作表示或节点表示)。
考题
在已知全部工作的( )时,可以按工程进度绘制资金使用计划S 曲线。A.最早开始时间(ES)开始和最早完成时间(EF)完成
B.最早开始时间(ES)开始和最迟开始时间(LS)开始
C.最迟开始时间(LS)开始和最早完成时间(EF)完成
D.最迟开始时间(LS)开始和最迟完成时间(LF)完成
考题
下列关于最早时间和最晚时间的计算公式正确的是()。 ①ES=EF+活动持续时间②EF=ES+活动持续时间③LS=LF-活动持续时间④LF=LS-活动持续时间A、①③B、①④C、②③D、②④
考题
使用反推法,如果任务F的工期减少到12天,对于任务F最迟开始和最迟完成的日期是多少?()A、LS=15,LF=20B、LS=16,LF=21C、LS=17,LF=22D、LS=14,LF=19
考题
单选题下列关于最早时间和最晚时间的计算公式正确的是()。 ①ES=EF+活动持续时间②EF=ES+活动持续时间③LS=LF-活动持续时间④LF=LS-活动持续时间A
①③B
①④C
②③D
②④
考题
单选题在利用网络图进行计算时,ef=es+工期估计表示()。A
最早开始时间B
最迟结束时间C
总时差D
最迟开始时间