The stages within the development phase of the software life cycle are ( 71 ).
A.design, analysis, implementation, and testing
B.analysis, design, implementation, and testing
C.analysis, design, testing, and implementation
D.design, analysis, testing, and implementation
参考答案
更多 “ The stages within the development phase of the software life cycle are ( 71 ).A.design, analysis, implementation, and testingB.analysis, design, implementation, and testingC.analysis, design, testing, and implementationD.design, analysis, testing, and implementation ” 相关考题
考题
The project stakeholders should be actively involved with the _____ phase(s) of the life cycle.A.ConceptualB.Development.C.ExecutionD.FinishE.All of the above.
考题
Network schedules are prepared during the _____ phase and updated during the _____ phase.A.Conceptual, execution.B.Development, implementation.C.Development, close-out.D.Implementation, close-out.E.Planning, finishing.
考题
67 The project stakeholders should be actively involved with the _____ phase(s) of the life cycle. A. ConceptualB. Development.C. ExecutionD. FinishE. All of the above
考题
148 Network schedules are prepared during the _____ phase and updated during the _____ phase. A. Conceptual, execution.B. Development, implementation.C. Development, close-out.D. Implementation, close-out.E. Planning, finishing
考题
30 Network schedules are prepared during the _____ phase and updated during the _____ phase. A. Conceptual, execution.B. Development, implementation.C. Development, close-out.D. Implementation, close-out.E. Planning, finishing
考题
149 The project stakeholders should be actively involved with the _____ phase(s) of the life cycle. A. ConceptualB. Development.C. ExecutionD. FinishE. All of the above
考题
● Software (71) refers to that the software to meet the specification must be produced.(71)A. testB. supportC. developmentD. process
考题
Software engineering is the study and an application of engineering to the design,development,and(71)of software.A.maintenance
B.service
C.running
D.deployment
考题
()在西门子802D系统中指的是平面铣削循环。A.CYCLE71B.CYCLE73C.CYCLE95D.CYCLE81