In project time management processes,( )involves identifying and documenting the relationships between project activities.

A.activity definition

B.activity sequencing

C.schedule control

D.Schedule development


参考答案

更多 “ In project time management processes,( )involves identifying and documenting the relationships between project activities.A.activity definitionB.activity sequencingC.schedule controlD.Schedule development ” 相关考题
考题 The reason that cost management is so difficult in project management is that:A . Projects by definition and nature are non-recurring events and are therefore difficult to predict.B . There are no tools for identifying project tasks.C . Project managers do not care about tracking costs, as only schedules are important to all project managers.D . A and B onlyE . B and C only

考题 ● Project Quality Management processes include all the activities of the (71) that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.(71)A. projectB. project management teamC. performing organizationD. customer

考题 ● Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other. (74) is following the process- Estimate Activity Durations.(74)A.Develop ScheduleB.Estimate Activity ResourcesC.Define ActivitiesD.Sequence Activities

考题 ● Project (69) Management includes the processes required to ensure thatthe project includes all the work required, and only the work required, tocomplete the project successfully.tA.IntegrationB.ScopeC.ConfigurationD.Requiremen

考题 ● The inputs of developing project management plan do not include (72).(72)A. project charterB. stakeholder management strategyC. project scope statementD. outputs from planning processes

考题 Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other.______is following the process-Estimate Activity Durations.A.Develop ScheduleB.Estimate Activity ResourcesC.Define ActivitiesD.Sequence Activities

考题 The inputs of developing project management plan do not include (72) .A.project charterB.stakeholder management strategyC.project scope statementD.outputs from planning processes

考题 The inputs of developing project management plan do not include(72). A.project charter B.stakeholder management strategy C.project scope statement D.outputs from planning processes

考题 Project()Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval,and ultimate disposition of project information.() A.Integration B.Time C.Planning D.Communication

考题 Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups.()process does not belong to Project Integration Management.A.Developing project charterB.Developing project management planC.Analyzing project risksD.Monitoring and controlling project

考题 Project Quality Management processes include all the activities of the (75) that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.A.performing organizationB.project management teamC.projectD.customer

考题 Project (24) Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.A.IntegrationB.ScopeC.ConfigurationD.Requirement

考题 ● Which of the following Project Scope Management processes involves subdividing the major project deliverables into smaller, more manageable components? (74)(74)A. Scope PlanningB. Scope VerificationC. Scope Change ControlD. Scope Definition

考题 In project time management, activity definition is the process of identifying and documenting the specific action to be performed to produce the project deliverables. ()are not output of activity definition.A.Activity listB.Work Breakdown StructuresC.Activity AttributesD.Milestone Lists

考题 In project time management,activity definition is the process of identifying and documenting the specification to be performed to produce the project deliverables.( )are not output of activity definition.A.Activity list B.Work Break down Structures C.Activity Attributes D.Mile stone Lists

考题 The inputs of developing project management plan do not include()A.project charter B.stakeholder management strategy C.project scope statement D.outputs from planning processes

考题 ()is the process of identifying individual project risks as well as source of overall project risk,and documenting their characteristics.A.identify risks B.monitor risks C.implement risks responses D.plan risk management

考题 Which of the following Project Scope Management processes involves subdividing the major projectdeliverablesinto smaller, more manageable components)()A.Scope Planning B.Scope Verification C.Scope Change Control D.Scope Definition

考题 Configuration management is focused on the specification of both the deliverables and the processes;while( )is focused on identifying,documenting,and approving or rejecting changes to the project documents,deliverables,or baselines.A.cost management B.change management C.configuration management D.capacity management

考题 The inputs of developing project management plan do not include (). A.project charter B.stakeholder management strategy C.project scope statement D.outputs from planning processes

考题 ( ) is the process of documenting. Analyzing,tracing,prioritizing and agreeing on requirements and then controlling change and communicating to relevant stakeholders. It is a continuous process throughout a project. A.Integrated management B.Configuration management C.Scope management D.Requirements management

考题 ( ) is primarily concerned with defining and controlling what is and is not included in the project. A.Project Time Management B.Project Cost Management C.Project Scope Management D.Project Communications Management

考题 The inputs of developing project management plan do not include()A、project charterB、stakeholder management strategyC、project scope statementD、outputs from planning processes

考题 Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.A、IntegrationB、ScopeC、ConfigurationD、Requirement

考题 单选题Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.A ProjectB project management teamC performingorganizationD customer

考题 单选题Performing()involves monitoring specific project results to determine if they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory results.A qualityplanningB qualityassuranceC qualityperformanceD quality control

考题 单选题The inputs of developing project management plan do not include()A project charterB stakeholder management strategyC project scope statementD outputs from planning processes