A customer is installing an HMC-managed Power 720 with two partitions, one for Production the other for Testing. They plan to use the Testing partition only occasionally and want to minimize hardware. Which of the following meets these requirements?()
A
Create a system profile for each partition. Assign all needed resources as 'required'.
B
Define all system resources as 'desired' on the Testing partition. Activate only as needed.
C
Create two shared processor pools. Assign the minimal I/O resources required for each partition to the shared pools.
D
Create both partitions with minimal 'required' resources, and optional resources as 'desired'. Activate each partition as necessary.
参考答案
参考解析
解析:
暂无解析
更多 “单选题A customer is installing an HMC-managed Power 720 with two partitions, one for Production the other for Testing. They plan to use the Testing partition only occasionally and want to minimize hardware. Which of the following meets these requirements?()A Create a system profile for each partition. Assign all needed resources as 'required'.B Define all system resources as 'desired' on the Testing partition. Activate only as needed.C Create two shared processor pools. Assign the minimal I/O resources required for each partition to the shared pools.D Create both partitions with minimal 'required' resources, and optional resources as 'desired'. Activate each partition as necessary.” 相关考题
考题
A customer has provided the pSeries technical specialist with details of an HACMP solution that they would like validated. The solution is for two POWER4+ p630 servers directly attached to a FAStT600 storage server as the shared storage. Each system has the following: ? 2 integrated network ports ? 2 fibre channel adapter cards ? 1 power supply and redundant cooling ? HACMP v5.1 In addition to a second power supply, what further requirements, if any, are needed to validate this solution and ensure no single point of failure? ()A、One fibre channel switchB、Two fibre channel switchesC、Two Ethernet cardsD、Nothing
考题
A customer has ordered a rack, a p650, two p630s, and two p615s. During a conversation on installation planning, the pSeries technical specialist recognizes that the customer expects the rack to arrive as one unit. However, the specialist knows that the p650 will be racked, but the other systems will arrive separately. In fact, the other systems are CSU (Customer Set Up). Why should the specialist immediately inform the customer that additional racking is the customer’s responsibility?()A、Because additional systems would require more power receptaclesB、Because the customer may need to do additional facilities planningC、Because the customer needs additional funding to cover the servicesD、Because postponing the eventual discussion will likely lead to customer dissatisfaction
考题
A customer has a p650 on order and plans to put it in a current OEM rack. They are concerned that the p650 power supply may demand more current than the OEM PDU can provide. Which planning guide specification would provide the necessary requirements?()A、VoltageB、FrequencyC、Power Source Loading (max)D、Power Source Loading (typical)
考题
A customer needs a solution that provides a total of eight processors (four active and four inactive), 16GB of memory, Advanced POWER Virtualization, and the ability to grow. Which of the followingsystems should the pSeries technical specialist propose?()A、p650B、p5-570C、Two p630sD、p5-570 Express
考题
Which feature of the IBM p5 servers enables customers to be confident that data within two distinct partitions on the server will be isolated?()A、POWER HypervisorB、Virtual LANC、POWER5 processorD、Redundant Power and Cooling
考题
A customer is very concerned about maintaining a competitive advantage through the use of state-of-the-art technology. Assuming all solutions meet the customer’s technical requirements, which solution should the IBM team propose to maximize customer satisfaction?()A、p690 with Dynamic LPARB、Grid of SP switch-attached p5-550sC、p690 with Advanced POWER VirtualizationD、p5-570 with Advanced POWER Virtualization
考题
A p5 570 customer is currently running AIX 5.3. The customer now wants to add Virtual Ethernet to two of the LPARs. This will enable the application tier can communicate to the database tier without using an external Ethernet card. What is the best way to accomplish this task?()A、Create a VIO serverB、Modify the LPAR profiles to add a Virtual Ethernet adapterC、Buy the Advanced Power Virtualization feature and enter a authorization code at the HMCD、Buy the Advanced Power Virtualization feature and enter a authorization code at the service processor menu
考题
A customer is planning to buy a two enclosure Power 770, and will implement 4 LPARs with the following requirements:Each LPAR must have a private, dedicated connection to the network.The adapter for this network connection must be hot-swappable.The customer wants to minimize the number of I/O slots used. Which of the following fulfills the customer requirements?()A、Two dual-port PCIe adaptersB、A four-port PCIe Ethernet adapterC、Four separate PCIe Ethernet adaptersD、Two embedded Integrated Virtual Ethernet adapters (IVE)
考题
有关IBM Power 720服务器,下面的哪些说法是合理的()A、Power 720可以使用Power6处理器B、Power 720是IBM System p 服务器一款超低端产品,可配置4核、6核、8核CPUC、Power 720采用power7芯片,支持3.3GHz,3.55GHz主频D、Power 720支持AIX,LINUX,Windows操作系统
考题
A customer has a requirement for a single AIX LPAR to be highly available. The customer only has enough funding to purchase a single system. Which would be the most critical option to mitigate AIX availability?()A、Dual power supplies.B、Twice the amount of disk.C、Two dual-port LHEA adapters.D、Two dual-port fibre channel adapters.
考题
A customer is installing an HMC-managed Power 720 with two partitions, one for Production the other for Testing. They plan to use the Testing partition only occasionally and want to minimize hardware. Which of the following meets these requirements?()A、Create a system profile for each partition. Assign all needed resources as 'required'.B、Define all system resources as 'desired' on the Testing partition. Activate only as needed.C、Create two shared processor pools. Assign the minimal I/O resources required for each partition to the shared pools.D、Create both partitions with minimal 'required' resources, and optional resources as 'desired'. Activate each partition as necessary.
考题
A customer has a new Power 720 with PowerVM Standard Edition. They plan to migrate their single-partition POWER5 550 to the new Power 720. How can the customer migrate from the POWER5 550 to the Power 720 with minimal effort and down time?()A、Perform Live Partition Mobility between the two systems.B、Move the boot disks from the old system to the new system.C、Use Tivoli Storage Manager to back up the POWER5 550 and restore on the Power 720.D、Upgrade AIX to the latest level on the POWER5 550 and clone using the mksysb command.
考题
A customer requires two 12X loops on their new POWER7 system. What is the smallest system that will support two loops?()A、Power 710B、Power 720C、Power 730D、Power 740
考题
A customer needs a system supporting four partitions, each with the following requirements: ? 0.6 1.65GHz processors ? 2GB memory ? AIX 5.2 They also need the ability to grow the system in the future. Which pSeries system would be positioned best to meet this customer’s requirements?()A、p5-550 with the Advanced POWER Virtualization feature and AIX 5.2B、p5-550 with the POWER5 processor technology and AIX 5.2C、p5-570 with the Advanced POWER Virtualization feature and AIX 5.3D、p5-570 with the POWER5 processor technology and AIX 5.2
考题
A space-constrained customer is currently running AIX 5.2 on a number of p650 servers and a pair of new p5-550 servers. They have four identical new applications each requiring a minimum of seven processors and 96GB of memory. Which solution would best meet the customer’s requirements?()A、Two p670 serversB、Four p650 serversC、Two p5-570 serversD、Four p5-550 servers
考题
A retail customer is looking at ways to reduce power requirements. They are considering deploying two hundred IBM HS22 blades running Red Hat Linux in the IBM BladeCenter E chassis. The customer has already chosen Intel L5640 CPUs to reduce power. Which on-board storage option allows the customer to reduce power consumption of each blade?()A、One 50 GB SATA 1.8 inch SSDB、Two 73GB 10K SAS HDD SFFC、Two 31 GB SATA 2.5 inch SSDD、Two 50GB SATA 1.8 inch SSD
考题
A customer runs an application on a supported 8-way x445. The customer needs to monitor operations and wants to be alerted when problems arise. Which TWO of the following can be configured in IBM Director Base Pack to monitor the customer’s operations?()A、Fan operationB、Bottleneck analysisC、Power supply operationsD、Planned versus unplanned outagesE、Application predictive failure analysis
考题
A customer has the following equipment installed in their data center: (1)an IBM BladeCenter H chassis (2)two power supplies (3)six HS22V blades (4)three Nortel 1/10 GB ESMs The retail customer purchased a new HX5 with MAX5. Which of the following must be added to install the HX5 with MAX5?()A、Two additional power suppliesB、Fibre Channel (FC) switches and SAN storageC、A Nortel 1/10 GB ESMD、SSD for the HX5
考题
A customer is adding a new p5 machine to their environment. The machine will host several DB2 partitions running AIX 5.2. They currently have two SAN directors and an IBM ESS. The SAN design allows for concurrent maintenance. What is required on each partition to attach to the SAN?()A、A minimum of two HBAs; the customer will need to download SDDB、A minimum of four HBAs; the customer will need to download SDDC、A minimum of two HBAs; the customer will need to configure MPIOD、A minimum of four HBAs; the customer will need to configure MPIO
考题
An IT director needs to deploy 3 partitions, each using dedicated internal boot disk. Which system will support the customer requirement using the least amount of rack space?()A、Power 770 serversB、Power 750 serversC、Power 755 serversD、Power 720 servers
考题
单选题A customer is interested in using two Power 550 servers to implement a new two node cluster. The cluster willbe using SAN attached disk for shared storage and will be attached to one IP network. Which of the followingadapter configurations will meet the customer requirements while reducing single points of failure?()A
AB
BC
CD
D
考题
单选题A customer wants to install a pSeries system into an OEM rack. What critical information is provided in the Site and Hardware Planning Information manual?()A
System dimensions and weight, system power and cooling requirements, and list of supported OEM racksB
System dimensions and weight, list of supported OEM racks, and requirements for installing IBM systems into OEM racksC
System performance specs, system power and cooling requirements, and requirements for installing IBM systems into OEM racksD
System dimensions and weight, system power and cooling requirements, and requirements for installingIBM systems into OEM racks
考题
单选题有关IBM Power 720服务器,下面的哪些说法是合理的()A
Power 720可以使用Power6处理器B
Power 720是IBM System p 服务器一款超低端产品,可配置4核、6核、8核CPUC
Power 720采用power7芯片,支持3.3GHz,3.55GHz主频D
Power 720支持AIX,LINUX,Windows操作系统
考题
单选题A small IT department is deploying Power 720 servers exploiting virtualization technologies. Each Power 720 will have two partitions, one with 6 cores and one with 2 cores, and both partitions having 32GB of memory each. Live Partition Mobility is being considered at some point in the future. What is the minimum AIX Edition required to support the customer?()A
AIX Basic EditionB
AIX Express EditionC
AIX Standard EditionD
AIX Enterprise Edition
考题
单选题A retail customer is looking at ways to reduce power requirements. They are considering deploying two hundred IBM HS22 blades running Red Hat Linux in the IBM BladeCenter E chassis. The customer has already chosen Intel L5640 CPUs to reduce power. Which on-board storage option allows the customer to reduce power consumption of each blade?()A
One 50 GB SATA 1.8 inch SSDB
Two 73GB 10K SAS HDD SFFC
Two 31 GB SATA 2.5 inch SSDD
Two 50GB SATA 1.8 inch SSD
考题
单选题A new p5 customer has just installed a partitioned p5-550 alongside some older POWER4 servers. The pSeries technical specialist has received a call to say that the existing HMC (7315) cannot connect to the new server. How can the specialist help the customer?()A
Explain to the customer that they need an additional HMC for the POWER5 system.B
Obtain a PO from the customer to purchase additional serial connections to the HMC.C
Obtain a PO from the customer to purchase additional Ethernet connections to the HMC.D
Explain to the customer that they need a firmware update on the HMC to support both POWER4 and POWER5.
考题
单选题A customer requires two 12X loops on their new POWER7 system. What is the smallest system that will support two loops?()A
Power 710B
Power 720C
Power 730D
Power 740
考题
单选题A customer is very concerned about maintaining a competitive advantage through the use of state-of-the-art technology. Assuming all solutions meet the customer’s technical requirements, which solution should the IBM team propose to maximize customer satisfaction?()A
p690 with Dynamic LPARB
Grid of SP switch-attached p5-550sC
p690 with Advanced POWER VirtualizationD
p5-570 with Advanced POWER Virtualization