Cost and schedule data are usually integrated because:
A.optimized project cash flow can affect financial requirements
B.they provide MIS with an integrated system to produce reports
C.they control escalation allowances
D.they account for omissions in the definitive estimate
E.they predict future performance
参考答案
更多 “ Cost and schedule data are usually integrated because:A.optimized project cash flow can affect financial requirementsB.they provide MIS with an integrated system to produce reportsC.they control escalation allowancesD.they account for omissions in the definitive estimateE.they predict future performance ” 相关考题
考题
What is the relative priority of project Cost, Schedule and Quality?A . 1)Cost - 2)Schedule - 3)QualityB . 1)Quality - 2)Schedule - 3)CostC . 1)Quality - 2)Cost - 3)ScheduleD . 1)Schedule - 2)Quality - 3)CostE . All are of equal priority
考题
130 What is the relative priority of project Cost, Schedule and Quality?A. 1)Cost - 2)Schedule - 3)QualityB. 1)Quality - 2)Schedule - 3)CostC. 1)Quality - 2)Cost - 3)ScheduleD. 1)Schedule - 2)Quality - 3)CostE. All are of equal priority
考题
12 What is the relative priority of project Cost, Schedule and Quality?A. 1)Cost - 2)Schedule - 3)QualityB. 1)Quality - 2)Schedule - 3)CostC. 1)Quality - 2)Cost - 3)ScheduleD. 1)Schedule - 2)Quality - 3)CostE. All are of equal priority
考题
57 Which of the following are types of status reports?A. document, variance, trend and exceptionB. cost, trend, schedule and acquisitionC. cost, schedule, technical performanceD. analysis, cost, performance and scheduleE. All of the above.
考题
● Project(71)is an uncertain event or condition that, if it occurs, has a positive or a negative effect on at least one project objective, such as time, cost, scope, or quality.(71)A.riskB.problemC.resultD.data
考题
Project ______is an uncertain event or condition that,if it occurs,has a positive or a negative effect on at least one project objective,such as time,cost,scope,or quality.A.riskB.problemC.resultD.data
考题
● Project()is an uncertain event or condition that ,if it occurs ,has a positive or a negative effect on at least one project objective ,such as time ,cost ,scope or quality()A. risk B. problem C. result D. data
考题
Project(71)is an uncertain event or condition that,if it occurs,has a positive or a negative effect on at least one project objective,such as time,cost,scope,or quality.A.riskB.problemC.resultD.data
考题
Project()is an uncertain event or condition that,if it occurs,has a positiveor a negative effect on at least one project objective,such as time,cost,scope, or quality.A.risk
B.problem
C.result
D.data
考题
Project( )is an uncertain event or condition that,if it occurs,has a positive or a negative effect on at least one project objective,such as time,cost,scope,or quality.A.risk
B.problem
C.result
D.data