Scheduling systems such as PERT, ADM, and PDM are project management tools to be used by:
A.The project manager and project office personnel.
B.The project team and functional managers.
C.The project sponsor.
D.All of the above.
E.A and B only.
参考答案
更多 “ Scheduling systems such as PERT, ADM, and PDM are project management tools to be used by:A.The project manager and project office personnel.B.The project team and functional managers.C.The project sponsor.D.All of the above.E.A and B only. ” 相关考题
考题
三种主要的图示法(diagramming methods)是()
A.AOA,PERT和CPMB.PERT,CPM和GERTC.前导图法、箭线图法、条件网络图法D.AON,AOA和PDM
考题
Project (75).Management:includes the processes required to ensure that the project includes au the word required, and only the work required, to complete the project successfully.A.IntegrationB.ConfigurationC.ScopeD.Requirement
考题
AcustomerhasasystemwithanumberofLPARs,oneofwhichisrunningasupportedversionofLinux.WhichCLIcommandcananadministratorusetodisplaytheCPUandmemoryresourceallocationoftheLinuxpartition?()
A.cat/proc/usr/lparchkB.cat/proc/ppc64/lparcfgC./var/adm/tools/res_listD./var/adm/tools/lparalloc
考题
下列对网络图描述正确的是()A.PDM图能够表示多种活动逻辑关系,而ADM图不能B.ADM图中的虚活动消耗资源和时间C.PDM图中可能有多个开始和多个结束D.ADM图用单节点表示活动本身
考题
在对原理图进行电气规则检查前,可以()打开规则设置界面。A.design-Document OptionsB.Project-Project OptionsC.Tools-Schematic PreferencesD.Project-Configuration Manager
考题
在原理图界面将鼠标光标设置为large cursor 90应选择()。A.Project-Project Options..B.Project-Project Templates...C.Tools-Schematic Preferencs...D.Design-Document Options...