Using the figure in the Special window, Activity "L" has an early start time of _____ weeks and an early finish time of _____ weeks.
A . 11, 13
B . 12, 14
C . 13, 15
D . 14, 16
E . 15, 17
参考答案
更多 “ Using the figure in the Special window, Activity "L" has an early start time of _____ weeks and an early finish time of _____ weeks.A . 11, 13B . 12, 14C . 13, 15D . 14, 16E . 15, 17 ” 相关考题
考题
Free float is the amount of time that an activity may be delayed with out affecting the _____.A.Early start of the succeeding activities.B.Late start of the succeeding activities.C.Project finish.D.Cost of the project.E.None of the above.
考题
Using the figure in the Special window, The slacktime in Activity "G" is _____ weeks.A . 2B . 3C . 4D . 5E . 7
考题
Using the figure in the Special window, Activity "D" has a latest start time of _____ weeks and a latest finish time of _____ weeks.A . 2, 10B . 4, 12C . 6, 14D . 7, 15E . 9, 17
考题
Using the figure in the Special window, The Critical path is _____ weeks.A . 21B . 22C . 23D . 24E . 25
考题
Using the data shown in the Special window, Activities P, Q, and T are critical path activities. In order to shorten the time duration of the project, which activity should be "crashed" first?A . PB . QC . RD . SE . T
考题
Using the figure in the Special window, By how many weeks can activity "F" slip without extending the end date of the project?A . 0B . 1C . 2D . 3E . 4
考题
An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?A.Total float for the activity is 9 days.B.The early finish date ofthe activity is the end ofthe day on the 14th.C.The late finish date is the 25th.D.The activity can be completed in 2 days ifthe resources devoted to it are doubled.
考题
111 Using the figure in the Special window, By how many weeks can activity "F" slip without extending the end date of the project?A. 0B. 1C. 2D. 3E. 4
考题
114 Using the figure in the Special window, The Critical path is _____ weeks.A. 21B. 22C. 23D. 24E. 25
考题
117 Using the figure in the Special window, Activity "L" has an early start time of _____ weeks and an early finish time of _____ weeks.A. 11, 13B. 12, 14C. 13, 15D. 14, 16E. 15, 17
考题
119 Using the figure in the Special window, Activity "D" has a latest start time of _____ weeks and a latest finish time of _____ weeks.A. 2, 10B. 4, 12C. 6, 14D. 7, 15E. 9, 17
考题
120 Using the figure in the Special window, The slacktime in Activity "G" is _____ weeks.A. 2B. 3C. 4D. 5E. 7
考题
● Free float is the amount of time that an activity may be delayed with out affecting the _____.A Early start of the succeeding activities.B Late start of the succeeding activities.C Project finish.D Cost of the project.E None of the above.
考题
单选题An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?A
Total float for the activity is 9 days.B
The early finish date ofthe activity is the end ofthe day on the 14th.C
The late finish date is the 25th.D
The activity can be completed in 2 days ifthe resources devoted to it are doubled.