Which of the following actions is an example of risk response:
A adjust project parameters (scope, time, quality ...)
B reduce the probability of potential project risk events
C reduce the consequences of potential project risk events
D wait until a problem actually happens, then deal with it in the most effective and efficient manner.
E A, B and C only
参考答案
更多 “ Which of the following actions is an example of risk response:A adjust project parameters (scope, time, quality ...)B reduce the probability of potential project risk eventsC reduce the consequences of potential project risk eventsD wait until a problem actually happens, then deal with it in the most effective and efficient manner.E A, B and C only ” 相关考题
考题
Using the problem stated in the Special window, Calculate the deviation of duration for the task, using the PERT concept of standard deviation of task duration.A . 0.5B . 1C . 1.8D . 2.2E . 2.8
考题
134 On November 1, $1000 worth of work on task A was supposed to have been done (BCWS); however, the BCWP was $850. Calculate the schedule variance:A. ($100)B. $100C. ($150)D. $150 E. 85%
考题
108 Using the situation stated in the Special window, the labor rate cost variance is:A. $66,927B. $68,329C. $386D. -$0.22E. $18.36
考题
86 Standard "Shewhart" control charts assume that the distribution of sample means is:A. uniform.B. normalC. discreteD. symmetricalE. B and D only
考题
24 The project charter is prepared in which scope management process?A. InitiationB. Scope planningC. Scope DefinitionD. Scope change controlE. Scope verification
考题
进度控制的一个重要部分是:A、 决定是否需要对进度计划偏差采取纠错行动B、 定义需要生产项目可交付成果所需的活动C、 评估范围定义是否足以支持进度计划D、 保证项目团队士气高昂,小组成员能够发挥最大潜能。
热门标签
最新试卷