项目执行期间重新委任了一名项目经理,项目已经按照计划执行,但是项目经理发现客户对报告方法相当不满,项目经理应该首先做什么?( )
A.检查沟通系统
B.询问客户的不满和要求,找出解决方案
C.向客户建议修改报告
D.让项目团队制定替代方案
参考答案
更多 “ 项目执行期间重新委任了一名项目经理,项目已经按照计划执行,但是项目经理发现客户对报告方法相当不满,项目经理应该首先做什么?( )A.检查沟通系统B.询问客户的不满和要求,找出解决方案C.向客户建议修改报告D.让项目团队制定替代方案 ” 相关考题
考题
A non-critical path activity is completed in half the time. Then,A.The critical path is also reduced.B.The slack in the path containing this activity will increase.C.The total cost for this activity has decreased.D.Manpower from this activity can be assigned to other activities.E.All of the above.
考题
In communications management, to assimilate through the mind or senses (as in new ideas) is the process ofA UnderstandingB CommunicatingC ReceivingD DecodingE Comprehending
考题
If a project manager communicates a verbal message to a subordinate, and the subordinate leaves without saying a word, the project manager should assume:A the message was understoodB the message was not understoodC the subordinate discarded the informationD the information was not appropriateE None of the above.
考题
107 In project-driven companies, costs are usually billed againest the project based upon:A. The burdened labor rate of the actual employees who performed the work.B. The burdened labor rate of the line organization average salary.C. The burdened labor rate of the company average salary.D. The burdened labor rate of the average salary of the project team members.E. None of the above
考题
● The "rolling wave" or "moving window" concept is used most frequently on projects where:A The baseline is frozen for the duration of the project and no scope changes are permittedB Marketing is unsure of what the customer actually wants and reserves the right to make major scope changesC The low levels of the work breakdown structure are known with certainty for the next three to six months, but the remaining tasks are based upon the results of the first three to six months of workD Networking techniques are not appropriateE All of the above
考题
你是负责这个地区最大的医院的项目经理。研究表明患者在治疗前要等候很久。实际上,在过去的几个月中,有一些患者在等待看医生的中途就放弃了。这些意外已经成为一个公共关系的噩梦。你正带领一个项目团队确定问题发生区域,并且提出解决方法并实施。为了评估影响这个问题的因素,你的团队已经决定使用下面哪种技术?( )A.原因-效果图B.帕雷托分析C.散点图D.控制表