网友您好, 请在下方输入框内输入要搜索的题目:
题目内容
(请给出正确答案)
152 Which of the following can affect network durations?
A. Skills of the resource pool
B. Calendar dates
C. Constraints
D. All of the above
E. A and B only
参考答案
更多 “ 152 Which of the following can affect network durations?A. Skills of the resource poolB. Calendar datesC. ConstraintsD. All of the aboveE. A and B only ” 相关考题
考题
We assign human and non-human resources in the _____ phase of the budget.A . conceptualB . planningC . developmentD . implementationE . close-out
考题
The project manager has, as a prime responsibility, to assure proper integration of activities. In which organizational form. does the project manager probably have the easiest time in integrating work?A . MatrixB . ClassicalC . ExpediterD . CoordinatorE . Pure project
考题
Universal characteristics of effective project managers include such skills as communication, decision-making, planning, ability to identify problems and:A . Performing feasibility studiesB . Proposal preparationC . being close to the customerD . MaturityE . None of the above are universal characteristics
考题
194 An advertiser who uses a movie or sports star to endorse a product is trying to use power.A. ExpertB. LegitimateC. RewardD. InfluentialE. Referent
考题
156 At least _____of the cost of quality are the direct responsibility of management.A. 25%B. 85%C. 50%D. 100%E. 33%
考题
166 The capacity to get an individual or group to perform. a given task is described as:A. AuthorityB. PowerC. InfluenceD. LeadershipE. Motivation
考题
16 Which of the statements regarding benefit-cost analysis in the Special window are true?A. 1 and 2B. 2 and 3C. 1 and 3D. 1, 2 and 3E. None of the above
考题
● A completion of a local government study resides on your critical path. This would most likely be referred to as:A Soft logicB Hard logicC An external dependencyD A mandatory dependencyE A lost cause
考题
风险管理的什么过程会对项目的计划产生影响?A、 风险识别B、 风险的定性分析C、 风险的应对规划D、 风险监控