81 Amount at Stake is the _____ .
A. function of planned time/real time project costs.
B. risk identified in successful project completions.
C. (Standard Project Deviation + Expected Costs)/6
D. cost of investment loss + least cost to restore status quo.
E. inherent risk at conception altered by standard project deviations
参考答案
更多 “ 81 Amount at Stake is the _____ .A. function of planned time/real time project costs.B. risk identified in successful project completions.C. (Standard Project Deviation + Expected Costs)/6D. cost of investment loss + least cost to restore status quo.E. inherent risk at conception altered by standard project deviations ” 相关考题
考题
Parametric estimates are based on variables such as:A.Detailed planning and cost restraints.B.Physical characteristics and historical data.C.The WBS and similar projects.D.Project objectives and manpower allocations.E.Precise measurements and multiple inputs.
考题
The type of power most infrequently used by the PM isA . formal authorityB . reward powerC . referent powerD . expert powerE . penalty
考题
Which of the following is equivalent to a lump sum contract:A fixed price contractB price fixing contractC purchase orderD All of the above.E B and C only
考题
168 The salvage value of an asset is:A. The value of the scrap metal if a new asset were taken to a scrap yard.B. The value that an asset has on the books after one year of depreciation.C. The costs that have been sunk into the project to date.D. The expected cash value at the end of an assets useful life.E. A and D only
考题
15 Which of the following is most closely associated with pure risk:A. profit and lossB. personnel turnoverC. insuranceD. market fluctuationsE. A and D only
考题
你是一位项目经理,管理着一个医疗数据库系统项目。公司有专业的编程人员负责设计程序,但是你需要从外部购买硬件。项目中负责合同管理的人员告诉你,需要向承包商提供一份产品描述,这个产品描述也被称作A、工作说明B、合同范围说明C、项目章程D、合同
考题
当项目团队成员既要对职能经理又要对项目经理负责时,团队建设通常十分复杂。这种双重报告关系的有效管理通常是谁的职责A、 涉及到的小组成员B、 项目经理C、 项目业主或发起人D、 职能经理
考题
采用逆推进法的目的在于决定( )A.关键路径B.最早完成日期C.最迟开始日期D.赶工日期