109 The project manager that allows and supports group discussions and decision making is called a(n) _____ manager.

A. autocratic

B. consultant autocratic

C. consensus

D. shareholder

E. None of the above


参考答案

更多 “ 109 The project manager that allows and supports group discussions and decision making is called a(n) _____ manager.A. autocraticB. consultant autocraticC. consensusD. shareholderE. None of the above ” 相关考题
考题 Assigning resources in an attempt to find the shortest project schedule consistent with fixed resource limits is called resource _____.A.Allocation.B.PartitioningC.LevelingD.Quantification.E.None of above.

考题 The following types of costs are relevant to making a financial decision except:A . opportunity costsB . direct costsC . sunk costD . unavoidable costsE . None of the above

考题 Delegation mayA . defer the decision on type of approach to be used.B . be interpreted as passive and uncaringC . tend to emphasize the task over the people involved.D . be frequently utilized by a project manager.E . All of the above.

考题 In a matrix organizational form, MBO may be difficult to implement:A . If the functional employees are supervised closely by the line manager rather than the project managerB . Unless the project manager has an input into the employee's performance reviewC . Unless the project and line managers agree on the ultimate objectiveD . Unless the project and line managers agree to the duration of the taskE . None of the above are correct answers

考题 Universal characteristics of effective project managers include such skills as communication, decision-making, planning, ability to identify problems and:A . Performing feasibility studiesB . Proposal preparationC . being close to the customerD . MaturityE . None of the above are universal characteristics

考题 When a majority of team members must agree before a decision is reached _____.A some team members may become alienatedB future group effectiveness may become damaged.C the PM may lose credibilityD the project manager will most likely have to utilize a conflict resolution techniqueE All of the above.

考题 If a project manager communicates a verbal message to a subordinate, and the subordinate leaves without saying a word, the project manager should assume:A the message was understoodB the message was not understoodC the subordinate discarded the informationD the information was not appropriateE None of the above.

考题 The project manager that allows and supports group discussions and decision making is called a(n) _____ manager.A autocraticB consultant autocraticC consensusD shareholderE None of the above.

考题 A recurring communication pattern within the project organization or company is called a:A free-form. matrixB structured matrixC networkD rigid channelE None of the above.

考题 When subordinates know pertinent information that is not known by the project manager, the result is:A BlindspotB FacadeC region of influenceD Communication power baseE None of the above

考题 A line manager possesses information which the project team needs, but withholds the information. The results in a(n):A BlindspotB FacadeC region of influenceD Communication power baseE None of the above

考题 By using Project Risk Management techniques, project managers can develop strategies that do all but which of the following:A Significantly reduce project risksB eliminate project risksC provide a rational basis for better decision makingD identify risks, their impact(s), and any appropriate responsesE None of the above.

考题 164 A line manager possesses information which the project team needs, but withholds the information. The results in a(n):A. BlindspotB. FacadeC. region of influenceD. Communication power baseE. None of the above

考题 174 When subordinates know pertinent information that is not known by the project manager, the result is:A. BlindspotB. FacadeC. region of influenceD. Communication power baseE. None of the above

考题 178 Assigning resources in an attempt to find the shortest project schedule consistent with fixed resource limits is called resource _____.A. Allocation.B. PartitioningC. LevelingD. Quantification.E. None of above.

考题 59 By using Project Risk Management techniques, project managers can develop strategies that do all but which of the following:A. Significantly reduce project risksB. eliminate project risksC. provide a rational basis for better decision makingD. identify risks, their impact(s), and any appropriate responsesE. None of the above

考题 80 A recurring communication pattern within the project organization or company is called a:A. free-form. matrixB. structured matrixC. networkD. rigid channelE. None of the above

考题 136 Universal characteristics of effective project managers include such skills as communication, decision-making, planning, ability to identify problems and:A. Performing feasibility studiesB. Proposal preparationC. being close to the customerD. MaturityE. None of the above are universal characteristics

考题 174 In a matrix organizational form, MBO may be difficult to implement:A. If the functional employees are supervised closely by the line manager rather than the project managerB. Unless the project manager has an input into the employee's performance review C. Unless the project and line managers agree on the ultimate objectiveD. Unless the project and line managers agree to the duration of the taskE. None of the above are correct answers

考题 15 If a project manager communicates a verbal message to a subordinate, and the subordinate leaves without saying a word, the project manager should assume:A. the message was understoodB the message was not understoodC. the subordinate discarded the informationD. the information was not appropriateE. None of the above

考题 102 The following types of costs are relevant to making a financial decision except:A. opportunity costsB. direct costsC. sunk costD. unavoidable costsE. None of the above

考题 97 If a project manager communicates a verbal message to a subordinate, and the subordinate leaves without saying a word, the project manager should assume:A. the message was understoodB. the message was not understoodC. the subordinate discarded the informationD. the information was not appropriateE. None of the above.

考题 191 The project manager that allows and supports group discussions and decision making is called a(n) _____ manager.A. autocraticB. consultant autocraticC. consensusD. shareholderE. None of the above

考题 22 When a majority of team members must agree before a decision is reached _____.A. some team members may become alienatedB. future group effectiveness may become damaged.C. the PM may lose credibilityD. the project manager will most likely have to utilize a conflict resolution techniqueE. All of the above

考题 81 A project manager believes that the best way to manage is to form. a good, harmonious working relationship with the team, and high performance will follow. The project manager could be defined as a _____ manager.A. 1,9B. 9,1C. 1,1D. 9,9E. 5,5

考题 104 When a majority of team members must agree before a decision is reached _____.A. some team members may become alienatedB. future group effectiveness may become damaged.C. the PM may lose credibilityD. the project manager will most likely have to utilize a conflict resolution techniqueE. All of the above.

考题 20 Using the scenario in the special window, the project manager appears to be a _____ manager.A. 1, 9B. 9, 1C. 1, 1D. 9, 9E. 5, 5