网友您好, 请在下方输入框内输入要搜索的题目:

题目内容 (请给出正确答案)
A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should ( )

A.assign change tasks to project members
B.call a meeting of the configuration control board
C.change the scope baseline
D. postpone the modification until a separate enhancement project is fundedafter this project is completed according to the original baseline

参考答案

参考解析
解析:项目经理认为调整项目范围可以给客户提供增值的服务,项目经理应该怎么做。
选项A是安排任务变更到项目成员,选项B是召集变更控制委员会会议,选项C是变更项目基线,选项D是按照原先的基线,在确定完成一项改进项目会得到客户的相应资金前,暂缓修改。
由于是在原内容基础上增加增值服务内容,超出原先范围,应先确定客户认可和增加新资金。因此应选择D。
更多 “ A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should ( ) A.assign change tasks to project members B.call a meeting of the configuration control board C.change the scope baseline D. postpone the modification until a separate enhancement project is fundedafter this project is completed according to the original baseline ” 相关考题
考题 The scope of a project can be expected to change if:A.The project manager must provide cost estimates without having a design conceptB.Oversimplification (underestimating) of the nature of the work occursC.The project manager is assigned after the project is defined, and the cost and schedule are approvedD.A clear objective is not providedE.All of the above are possible based upon the situation

考题 The scope baseline/project charter is prepared by the:AProject managerBProject manager and project officeCProject manager, project office and functional teamDProject manager, project office, functional team and project sponsorEProject manager, project sponsor and customer/user

考题 Management reserves are normally defined as a % of the total budget. As a project progresses, the project manager wants the $ value of management reserve to _____, whereas the customer wants the management reserve to _____.A . Increase, increase.B . Increase, decrease.C . Decrease, decrease.D . Decrease, increase.E . Remain the same, return to customer.

考题 A project manager believes that the best way to manage is to form. a good, harmonious working relationship with the team, and high performance will follow. The project manager could be defined as a _____ manager.A . 1,9B . 9,1C . 1,1D . 9,9E . 5,5

考题 Team members want to work for a project manager that can provide them with career path planning. In which organizational form. is career path planning difficult for project employees?A . MatrixB . Pure projectC . Project coordinatorD . Project expediterE . Classical/traditional

考题 In a matrix organizational form, MBO may be difficult to implement:A . If the functional employees are supervised closely by the line manager rather than the project managerB . Unless the project manager has an input into the employee's performance reviewC . Unless the project and line managers agree on the ultimate objectiveD . Unless the project and line managers agree to the duration of the taskE . None of the above are correct answers

考题 A common way by which executives provide the project manager with written authority is through:A . A common job description for all project managersB . An appointment letterC . A project charterD . All of the aboveE . B and C only

考题 If a project manager communicates a verbal message to a subordinate, and the subordinate leaves without saying a word, the project manager should assume:A the message was understoodB the message was not understoodC the subordinate discarded the informationD the information was not appropriateE None of the above.

考题 The way a project manager sends and receives information depends upon:A How others relate to the project managerB The project manager's level in the organizational hierarchyC the size and nature of the projectD the project manager's salary and ageE the number of projects going on at one time in the company

考题 66 A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:A. Change the scope baselineB. Prepare a variance reportC. Call a meeting of the configuration control boardD. Change the project's objectivesE. Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

考题 123 The scope baseline/project charter is prepared by the:A. Project managerB. Project manager and project officeC. Project manager, project office and functional teamD. Project manager, project office, functional team and project sponsorE. Project manager, project sponsor and customer/user

考题 41 The scope of a project can be expected to change if:A. The project manager must provide cost estimates without having a design concept B. Oversimplification (underestimating) of the nature of the work occursC. The project manager is assigned after the project is defined, and the cost and schedule are approvedD. A clear objective is not providedE. All of the above are possible based upon the situation

考题 123 The scope of a project can be expected to change if:A. The project manager must provide cost estimates without having a design concept B. Oversimplification (underestimating) of the nature of the work occursC. The project manager is assigned after the project is defined, and the cost and schedule are approved D. A clear objective is not providedE. All of the above are possible based upon the situation

考题 ● The scope of a project can be expected to change if:A The project manager must provide cost estimates without having a design conceptB Oversimplification (underestimating) of the nature of the work occursC The project manager is assigned after the project is defined, and the cost and schedule are approvedD A clear objective is not providedE All of the above are possible based upon the situation

考题 ● The scope baseline/project charter is prepared by the:A Project managerB Project manager and project officeC Project manager, project office and functional teamD Project manager, project office, functional team and project sponsorE Project manager, project sponsor and customer/user

考题 ● A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:A Change the scope baselineB Prepare a variance reportC Call a meeting of the configuration control boardD Change the project's objectivesE Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

考题 ● A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should(75).(75)A.assign change tasks to project membersB.call a meeting of the configuration control boardC.change the scope baselineD.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

考题 ● Project manager believes that modifying the project scope may provide added value for the customer. The project manager should (73) .(73) A. change the scope baselineB. contact the customer to determine if the change adds valueC. call a meeting of the change control boardD. change the project' s objectives

考题 A project manager believes that modifying the scope of the project may provide added value service for the customer.The project manager should______.A.assign change tasks to project membersB.call a meeting of the configuration control boardC.change the scope baselineD.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

考题 The perform. Integrated Change Contorl process is the ultimate responsibility of the(①).Although changes may be initiated verbally,they should be recorded in writtern form. and entered into the (②)system.①A.resource managerB.division managerC.functional managerD.project manager②.A.quality managementB.configuration managementC.project managerD.scope management

考题 Project manager believes that modifying the project scope may provide added value for the customer . The project manager should (73).A.change the scope baselineB.contact the customer to determine if the change adds valueC.call a meeting of the change control boardD.change the project’s objectives

考题 Project manager believes that modifying the project scop may provide added value for the customer.The project manager should( ) A.change the scope baseline B.contact the customer to determine if the change adds value C.call A.meeting of the change control board D.change the project's objectives

考题 Project manager believes that modifying the project scope may provide added value for the customer. The project manager should ( ) .A.change the scope baseline B.contact the customer to determine if the change adds value C.call A.meeting of the change control board D.change the project’s objectives

考题 Changes may be requested by any stakeholder involved with the project,but changes can be authorized only by ( ) . A.executive IT manager B.project manger C.change control board D.project sponsor

考题 A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should ( ) . A.assign change tasks to project members B.call A.meeting of the configuration control board C.change the scope baseline D.postpone the modification until A.separate enhancement project is fundeD.after this project is completeD.according to the original baseline

考题 The project manager is developing a project schedule. The project manager negotiated with all the execution organizations, and the task times are as short as possible. After manipulating the schedule, the project completion date is still beyond the date requested by the business owners of the project. The project manager believes that the content agreed on for the project is appropriate, and concludes that this schedule should be taken to the business owners and renegotiated. Which one of the following tools will help the project manager justify the revised schedule?()A、Data flow modelB、The project critical pathC、Resource loading chartD、WBS (Work Breakdown Structure)

考题 What is the role of the line manager in a project plan?()A、Provide resources to a projectB、Request requirements changesC、Resolve team conflictsD、Control the project budget