网友您好, 请在下方输入框内输入要搜索的题目:
题目内容
(请给出正确答案)
填空题
____(complete) the project as planned, we have to work two more hours a day.
参考答案
参考解析
解析:
句意:为了按计划完成这个项目,我们每天不得不多工作两个小时。本题考查动词不定式。通过句中的“planned”可知,该项目还没有完成,只是计划过,表示“将要完成”用动词不定式表达。故划线处填To complete。
句意:为了按计划完成这个项目,我们每天不得不多工作两个小时。本题考查动词不定式。通过句中的“planned”可知,该项目还没有完成,只是计划过,表示“将要完成”用动词不定式表达。故划线处填To complete。
更多 “填空题____(complete) the project as planned, we have to work two more hours a day.” 相关考题
考题
During project execution, a line manager informs you that he will not have sufficient resources available next month to support your and two other projects. The best way to handle this problem would be to:A.Ask the line manager to make the decision.B.Ask the line manager to work with senior management to prioritize the work.C.Ask your sponsor to meet with the line manager.D.Ask the line manager to set up a meeting with you and the other project managers to work out the problem yourselves.E.Prepare a purchase order to outsource the work.
考题
● The financial closeout of a project dictates that:A All project funds have been spent.B No charge numbers have been overrun.C No follow-on work from this client is possible.D No further charges can be made against the project.E All of the above.
考题
The(69)Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.A.PlannlngB.ExecutingC.Monitoring and ControllingD.Closing
考题
The( )Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project’s requirements. A.Planning B.Executing C.Monitoring and Controlling D.Close-out
考题
The earned value technique is a commonly used method of performance measurement.It integrates project scope,schedule,and cost measures to help the project management team assess project performance.If a project’s Cost Performance Index(CPI=EV/AC)value less than 1.0,it means that( )。 A.the cost savings for work completed B.the project is ahead of its planned schedule C.the cost overrun for work completed D.1ess work was completed than was planned
考题
●The project budget has been finalized.Additional work has been discovered that was not planned for in the budget or project scope.(74) could provide the fund to cover the newly discovered work item.(74) A. Contingency reserveB. Project profitC. Management reserveD. Special fund
考题
We ( ) on it for many hours but we have not yet reached any conclusion.
A、have had workedB、have been workingC、are workingD、work
考题
We'll have to______ how much food we'll need for the party.
A、work outB、work upC、work inD、work on
考题
We () the project on time without your kind assistance.
A、hadn t had completedB、didn t have completedC、couldn t have completedD、cannot have completed
考题
Project (24) Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.A.IntegrationB.ScopeC.ConfigurationD.Requirement
考题
● You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week period. As of today, you've spent ¥260,000 of your budget to complete work that you originally expected to cost ¥280,000. According to your schedule, you should have spent ¥300,000 by this point. Based on these circumstances, your project could be BEST described as (74) .(74)A.Ahead of scheduleB.Behind scheduleC.On scheduleD.Having not enough information provided
考题
● The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that __(74)__.(74)A.the project is ahead of its planned scheduleB.less work was completed than was plannedC.the cost overrun for work completedD.the cost under-run of performance to date
考题
The earned value technique is a commonlyused method of performance measurement. It integrates project scope, cost, andschedule measures to help the project management team assess projectperformance.If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, itmeans that (74).A.the project is ahead of its planned scheduleB.less work was completed than was plannedC.the cost overrun for work completedD.the cost under-run of performance to date
考题
Project (75).Management:includes the processes required to ensure that the project includes au the word required, and only the work required, to complete the project successfully.A.IntegrationB.ConfigurationC.ScopeD.Requirement
考题
We have planned an exciting publicity _______ 选择
Wehaveplannedanexcitingpublicity_______withouradvertisers.A)struggleB)battleC)campaignD)conflict
考题
( )the project in time, the staff were working at weekends.A. CompetingB. Having completedC. To have completedD. To complete
考题
______ the project in time, the staff were working at weekends.A. Competing B. Having completedC. To have completed D. To complete
考题
The project budget has been finalized.Additional work has been discovered that was not planned for in the budget or project scope. (74) could provide the fund to cover the newly discovered work item.A.Contingency reserve
B.Project profit
C.Management reserve
D.Special fund
考题
The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that ( ) .A.he project is ahead of its planned schedule
B.less work was completed than was planned t
C.the cost overrun for work completed
D.the cost underrun of performance to date
考题
What does A.CPI of 80%mean?( ).A.As of now we expect the total project cost of 80%more than planned
B.When the project is completed,we will have spent 80%more
C.Your project is only progressing at 80%of that planned
D.Your project is only getting 80 cents out of every RMB invested
考题
Estimating schedule activity costs involves developing an approximation of the costs of theresources needed to complete each schedule activity. Cost estimating includes identifying andconsidering various costing alternatives. For example, in most application areas, additional workduring a design phase is widely held to have the potential for reducing the cost of the executionphase and product operations. The cost estimating process considers whether the expectedsavings can offset the cost of the A.project scope statement
B.statement of work
C.project management plan
D.project policy
考题
Project()Management includes the processes required to ensure that theproj ect includes all the work required, and only the work required, to complete the project successfully.A、IntegrationB、ScopeC、ConfigurationD、Requirement
考题
Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.A、IntegrationB、ScopeC、ConfigurationD、Requirement
考题
单选题We had to submit our project without a bibliography, because listing our sources would have took Jose and I another day to complete.A
would have took Jose and IB
would have taken Jose and IC
would have taken Jose and meD
would have took Jose and meE
would be taking Jose and me
考题
单选题The()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.A
PlanningB
ExecutingC
Monitoring and ControllingD
Closing
考题
单选题We are sure that we ______ our second project by the end of the next month.A
will have completedB
had completedC
completedD
were completing
热门标签
最新试卷