() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion; they may also exert influence over the project and its results.
A
controls
B
baselines
C
projectstakeholders
D
projectmanagers
参考答案
参考解析
解析:
该题的关键词为"individuals and organizations、 be affected、 exertinfluence",其语句结构为" (主语)are(谓语)individuals and organizations",含义为"什么是个人或组织",选项A和B容易排除,选项D虽然也受项目影响,也可以施加影响,但其不表示为组织形式,因而 也可以排除。实际上,这句话正是project stakeholders(项目干系人)的定义,所以选择C。
更多 “单选题() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion; they may also exert influence over the project and its results.A controlsB baselinesC projectstakeholdersD projectmanagers” 相关考题
考题
The project life-cycle can be described as:A.project concept, project planning, project execution, and project close-out.B.project planning, work authorization, and project reporting.C.project planning, project control, project definition, WBS development, and project termination.D.project concept, project execution, and project reporting.E.All of the above.
考题
A negative cost variance and positive schedule variance means:A The project is under budget and ahead of scheduleB The project is over budget and behind scheduleC The project is over budget and ahead of scheduleD The project will be overrun but ahead of schedule at completion
考题
96 A negative cost variance and positive schedule variance means:A. The project is under budget and ahead of scheduleB. The project is over budget and behind scheduleC. The project is over budget and ahead of scheduleD. The project will be overrun but ahead of schedule at completion
考题
● A project life cycle is a collection of generally sequential project (73)whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic (74)for managing the project, regardless of the specific work involved.(73)A. phasesB. processesC. segmentsD. pieces(74)A. planB. fractionC. mainD. framework
考题
● Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).(73)A.executive IT managerB.project mangerC.change control boardD.project sponsor
考题
● The project life-cycle can be described as(72).(72)A.project concept, project planning, project execution, and project close-outB.project planning, work authorization, and project reportingC.project planning, project control, project definition, WBS development, and project terminationD.project concept, project execution, and project reporting
考题
are individuals and organizations that are actively involved in the project,or whose interests may be affected as a result of project execution or project completion.A.Project managerB.Project team memberC.SponsorD.Proiect stakeholders
考题
are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion; they may also exert influence over the project and its results.A.ControlsB.BaselinesC.Project stakeholdersD.Project managers
考题
A project life cycle is a collection of generally sequential project (73) whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic (74) for managing the project, regardless of the specific work involved.A.phasesB.processesC.segmentsD.pieces
考题
根据材料回答3~4题: A project life cycle is a collection of generally sequential project(73)whose name and number are determined by the control needs of the organization or organizations involved in the project.The life cycle provides the basic(74)for managing the project,regardless ofthe specific work involve D. A.phases B.processes C.segments D.pieces
考题
are individuals and organizations that are actively involved in the project, or whose interests may be affected as aresult of project execution or project completion, they may also exert influence over the project and its results.A.ControlsB.BaselinesC.Project stakeholdersD.Project managers
考题
A project life cycle is a collection of generally sequential project ()whose name and number are determined by the control needs of the organization or organizations involved in the project.
The life cycle provides the basic for managing the project, regardless of the specific work involved.A.phases
B.processes
C.segments
D. pieces
考题
A project life cycle is a collection of generally sequential project whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic () for managing the project, regardless of the specific work involved.A. plan
B. fraction
C. main
D.framework
考题
The project life-cycle can be described as().A.project concept, project planning, project execution, and project close-out
B.project planning, work authorization, and project reporting
C.project planning, project control, project definition, WBS development, and project termination
D.project concept, project execution, and project reporting
考题
May be involved in the qualitative analysis of project risks(). A.Establish probability and influence matrix
B.Decision tree analysis
C.Sensitivity analysis
D.Modeling and simulation
考题
During the implementation of the project,the user's environment(business environment,organizational structure,etc.)may change,and the demand for the project may also change.For the changing needs of the project scope,()is the person with real approval power.A.user
B.project manager
C.CCB
D.Project investor
考题
Changes may be requested by any stakeholder involved with the project,but changes can be authorized only by ( ) . A.executive IT manager
B.project manger
C.change control board
D.project sponsor
考题
Changes may be requested by any stakeholder involved with the project,but changes can be authorized only by ( ) .A.executive IT manager
B.project manger
C.change control board
D.project sponsor
考题
() are individuals and organizations that are actively involved in the project, orwhose interests may be affected as a result of project execution or project completion; they mayalso exert influence over the project and its results. A.Controls
B.Baselines
C.Project stakeholders
D.Project managers
考题
A project life cycle is a collection of generally sequential project ()whose name and number are determined by the control needs of the organization or organizations involved in the project. A.phases
B.processes
C.segments
D.pieces
考题
() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.A、Project managersB、Project team membersC、SponsorsD、Project stakeholders
考题
() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion; they may also exert influence over the project and its results.A、controlsB、baselinesC、projectstakeholdersD、projectmanagers
考题
A project life cycle is a collection of generally sequential project()(1) whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic ()(2) for managing the project, regardless of the specific work involved.
空白(2)处应选择()A、planB、fractionC、mainD、framework
考题
The project manager is developing a project schedule. The project manager negotiated with all the execution organizations, and the task times are as short as possible. After manipulating the schedule, the project completion date is still beyond the date requested by the business owners of the project. The project manager believes that the content agreed on for the project is appropriate, and concludes that this schedule should be taken to the business owners and renegotiated. Which one of the following tools will help the project manager justify the revised schedule?()A、Data flow modelB、The project critical pathC、Resource loading chartD、WBS (Work Breakdown Structure)
考题
单选题() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.A
Project managersB
Project team membersC
SponsorsD
Project stakeholders
考题
单选题A project life cycle is a collection of generally sequential project()(1) whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic ()(2) for managing the project, regardless of the specific work involved.
空白(1)处应选择()A
phasesB
processesC
segmentsD
pieces
考题
单选题The project manager is developing a project schedule. The project manager negotiated with all the execution organizations, and the task times are as short as possible. After manipulating the schedule, the project completion date is still beyond the date requested by the business owners of the project. The project manager believes that the content agreed on for the project is appropriate, and concludes that this schedule should be taken to the business owners and renegotiated. Which one of the following tools will help the project manager justify the revised schedule?()A
Data flow modelB
The project critical pathC
Resource loading chartD
WBS (Work Breakdown Structure)