May be involved in the qualitative analysis of project risks().
A.Establish probability and influence matrix
B.Decision tree analysis
C.Sensitivity analysis
D.Modeling and simulation
B.Decision tree analysis
C.Sensitivity analysis
D.Modeling and simulation
参考答案
参考解析
解析:解析:翻译:在进行项目风险定性分析时,可能会涉及到( )。
A.建立概率及影响矩阵B.决策树分析
C.敏感性分析D.建模和模拟
实施定性风险分析的工具与技术包括:风险概率和影响评估、概率和影响矩阵、风险数据质量评估、风险分类、风险紧迫性评估、专家判断。
A.建立概率及影响矩阵B.决策树分析
C.敏感性分析D.建模和模拟
实施定性风险分析的工具与技术包括:风险概率和影响评估、概率和影响矩阵、风险数据质量评估、风险分类、风险紧迫性评估、专家判断。
更多 “May be involved in the qualitative analysis of project risks(). A.Establish probability and influence matrix B.Decision tree analysis C.Sensitivity analysis D.Modeling and simulation” 相关考题
考题
● The (75) process analyzes the effect of risk events and assigns a numerical rating to those risks.A.Risk IdentificationB.Quantitative Risk AnalysisC.Qualitative Risk Analysis.Risk Monitoring and Control
考题
There are strategies typically deal with threats or risk that may have negative impacts on project objectives if they occur, some other strategies are suggested to deal with risks with potentially positive impacts. ()is a risk response strategy that may be adopted for either threats or opportunities.A.shareB.MitigateC.TransferD.Acceptance
考题
●(71)assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame. and risk tolerance of the project constraints of cost, schedule, scope, and quality.(71)A. Quantitative Risk AnalysisB. Qualitative Risk AnalysisC. Enterprise Environmental FactorsD. Risk Management Plan
考题
● Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).(73)A.executive IT managerB.project mangerC.change control boardD.project sponsor
考题
are individuals and organizations that are actively involved in the project,or whose interests may be affected as a result of project execution or project completion.A.Project managerB.Project team memberC.SponsorD.Proiect stakeholders
考题
are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion; they may also exert influence over the project and its results.A.ControlsB.BaselinesC.Project stakeholdersD.Project managers
考题
● There are strategies typically deal with threats or risks that may have negative impacts on project objectives if they occur. Some other strategies are suggested to deal with risks with potentially positive impacts. (74) is a risk response strategy that may be adopted for either threats or opportunities.(74) A. ShareB. MitigateC. TransferD. Acceptance
考题
______assesses the priority of identified ri sks using their probability of occurring,the corresponding impact on project objectives if the risks do occur,as well as other factors such as the time frame. and risk tolerance of the project constraints of cost,schedule,scope,and quality.A.Quantitative Risk AnalysisB.Qualitative Risk AnalysisC.Enterprise Environmental FactorsD.Risk Management Plan
考题
Risk management allows the project manager and the project team not to(71). A.eliminate most risks during the planning phase of the project B.identify project risks C.identify impacts of various risks D.plan suitable responses
考题
The( )process ascertains which risks have the potential of affecting the project and documenting the risks’characteristics. A.Risk Identification B.Quantitative Risk Analysis C.Qualitative Risk Analysis D.Risk Monitoring and Control
考题
The()process analyzes the effect of risk events and assigns a numerical rating to those risks.()A.Risk Identification B.Quantitative Risk AnalysisC.Qualitative Risk Analysis D.Risk Monitoring and Control
考题
The______process ascertains which risks have the potential Of affecting the proect and documenting the risks' characteristics.A.Risk IdentificationB.Quantitative Risk AnalysisC.Qualitative Risk AnalysisD.Risk Monitoring and Control
考题
资料:For the development of Crunchy Nut (a product),K company has used various methods of primary data collection. Primary market data may involve qualitative research or quantitative research. Qualitative data is connected more about opinions, feelings and attitudes. Quantitative data is in numerical form and is usually gathered from a large sample of respondents.
Qualitative research establishes a conversation with consumers. It prompts consumer reaction to, for example, a new product idea and helps researchers understand what they think of it, how it makes them feel, why they find it interesting or not.
Qualitative research may be obtained through focus groups, where a moderator captures feedback from a group of six or seven consumers to the ideas shown to them. Those ideas may take the format of drawings or having new food prototypes to taste. Quantitative research may use questionnaires administered to large numbers of respondents. This allows statistical analysis. It may involve the use of scales, so numbers get associated with a particular meaning-for example, on an evaluation scale of 1 to 7, where 1 means very poor and 7 means excellent. Crucially those numbers need to be interpreted to enable the business to understand the consumers' overall response.
What is the passage about?A.The development of Crunchy Nut.
B.K Company's production line.
C.Qualitative data collection.
D.Two approaches to data collection.
考题
Changes may be requested by any stakeholder involved with the project,but changes can be authorized only by ( ) . A.executive IT manager
B.project manger
C.change control board
D.project sponsor
考题
Changes may be requested by any stakeholder involved with the project,but changes can be authorized only by ( ) .A.executive IT manager
B.project manger
C.change control board
D.project sponsor
考题
() are individuals and organizations that are actively involved in the project, orwhose interests may be affected as a result of project execution or project completion; they mayalso exert influence over the project and its results. A.Controls
B.Baselines
C.Project stakeholders
D.Project managers
考题
The ( ) process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics. A.Risk Identification
B.Quantitative Risk Analysis
C.Qualitative Risk Analysis
D.Risk Monitoring anD.Control
考题
( ) Assesses the priority of identified risks using their probability of occurring,the corresponding impact on project objectives if the risks do occur,as well as other factors such as the time frame and risk tolerance of the project constraints of cost,schedule,scope,and quality. A.Quantitative Risk Analysis
B.Qualitative Risk Analysis
C.Enterprise Environmental Factors
D.Risk Management Plan
考题
() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.A、Project managersB、Project team membersC、SponsorsD、Project stakeholders
考题
The ()process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics.A、RiskldentificationB、Quantitative Risk AnalysisC、Qualitative Risk AnalysisD、Risk Monitoring and Control
考题
()assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame and risk tolerance of the project constraints of cost, schedule, scope, and quality.A、Quantitative Risk AnalysisB、Qualitative Risk AnalysisC、Enterprise Environmental FactorsD、Risk Management Plan
考题
Which of the following techniques is used for tracking the project risks?()A、Probability-Impact matrixB、Pareto chartC、R-ChartD、PERT (Program Evaluation and Review Technique) analysis
考题
单选题() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.A
Project managersB
Project team membersC
SponsorsD
Project stakeholders
考题
单选题() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion; they may also exert influence over the project and its results.A
controlsB
baselinesC
projectstakeholdersD
projectmanagers
考题
单选题Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by()A
executive IT managerB
projectmangerC
change control boardD
projectsponsor
热门标签
最新试卷