()describes, in detail, the project’s deliverables and the work required to create those deliverables.
A
Product scope description
B
Project objectives
C
Stakeholder Analysis
D
The project scope statement
参考答案
参考解析
解析:
参考答案:D
更多 “单选题()describes, in detail, the project’s deliverables and the work required to create those deliverables.A Product scope descriptionB Project objectivesC Stakeholder AnalysisD The project scope statement” 相关考题
考题
Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()
A.independentresourceB.individualworkloadC.workmilestoneD.workpackage
考题
The()describes, in detail, the project's deliverables and the work required to create those deliverables.
A.project scope statementB.project requirementC.project charterD.product specification
考题
Define Activities is the process of identifying the specific actions to be performed to produce the (71).A.project elementsB.work draftsC.work packageD.project deliverables
考题
● Define Activities is the process of identifying the specific actions tobe performed to produce the (71).(71)A. project elementsB. work draftsC. work packageD. project deliverables
考题
●(74) describes, in detail, the project' s deliverables and the work required to create those deliverables.(74) A. Product scope descriptionB. Project objectivesC. Product specificationD. The project scope statement
考题
● Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the (75) level.(75)A.independent resourceB.individual work loadC.work milestoneD.work package
考题
______describes,in detail,the project's deliverables and the work required to create those deliverables.A.Product scope descriptionB.Project objectivesC.Stakeholder AnalysisD.The project scope statement
考题
The( )is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables.
A、project scope statementB、work packageC、WBSD、project scope plan
考题
● A project management technique that is currently in widespread use is the (71) . The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives. There are some special activities called (72) , which are events that signify the accomplishment or completion of major deliverables during the project. Most system development methodologies also provide (73) , whose purpose is to contain the various pieces of relevant information – feasibility assessments, schedules, needs analysis, and so forth – in a single place so that they can be presented to project clients and other related parties. Several types of important network diagrams are used in project management. (74) was developed to make clear the interdependence between project tasks before those tasks are scheduled. (75) offers the advantage of clearly showing overlapping tasks.
考题
Operations( )is a document that describes in detail the processes。A.PaperB.BookC.MenuD.Manual
考题
In project management , a (1) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource (2) ,budget and duration, linked by dependencies and scheduled events.A.scheduleB.activityC.planD.contractor@@@SXB@@@A.findingB.balanceC.allocationD.distribution
考题
The scope management plan is how the team will prepare the()a document that includes descriptions of create the WBS, verify completion of the project deliverables, and control requests for changes to the project scope.A.project charterB.project scope goalC.project budgetD.project scope statement
考题
The ()describes, in detail, the project’s deliverables and the work required to create those deliverables.A.project scope statement
B.project requirement
C.project charter
D.product specification
考题
()describees,indetail,the project's deliverables and the work required to create those deliverables.
A.Product scope description
B.Project objectives
C.Produce specification
D.The project scope statement
考题
In project management, a ( ) is a listing of a project’s milestones ,activities, and deliverables, usually with intended start and finish dates。A.schedule
B.activity
C.Plan
D.contractor
考题
( ) describes,in detail,the project’s deliverables and the work required to create those deliverables. A.Product scope description
B.Project objectives
C.Stakeholder Analysis
D.The project scope statement
考题
The()is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables.A.Project scope statement
B.Work package
C.WBS
D.Project scope plan
考题
The scope management plan is how the team will prepare the( )a document that includes descriptions of create the WBS,verify completion of the project deliverables,and control requests for changes to the project scope. A.project charter
B.project scope goal
C.project budget
D.project scope statement
考题
Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the ( ) level.A.independent resource
B.individual work load
C.work milestone
D.work package
考题
In project management, a ( )is a list of a project’s milestones, activities, and deliverables, usually with intended start and finish date. Those items are often estimated in terms of resource allocation, budget and duration, linked by dependencies and scheduled events. A、scheduleB、WBSC、SOWD、charter
考题
()describes, in detail, the project’s deliverables and the work required to create those deliverables.A、Product scope descriptionB、Project objectivesC、Stakeholder AnalysisD、The project scope statement
考题
The () describes, in detail, the project's deliverables and the work required to create those deliverables.A、project scope statementB、project requirementC、project charterD、product specification
考题
单选题In project management , a (73) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource (74) ,budget and duration, linked by dependencies and scheduled events.A
scheduleB
activityC
planD
contractor
考题
单选题The()describes, in detail, the project's deliverables and the work required to create those deliverables.A
project scope statementB
project requirementC
project charterD
product specification
考题
单选题()describes, in detail, the project’s deliverables and the work required to create those deliverables.A
Product scope descriptionB
Project objectivesC
Stakeholder AnalysisD
The project scope statement
考题
单选题The project()is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements,thresholds, and acceptance criteria.A
work performance informationB
scope statementC
changerequestsD
process analysis
考题
单选题The creation ofa work breakdown structure (WBS) is the process of()the major project deliverables.A
subdividingB
assessingC
planningD
integrating
考题
单选题Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()A
independentresourceB
individualworkloadC
workmilestoneD
workpackage