()is the process of obtaining the stakeholders’ formal acceptance of the completed project scope.Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.
- A、Project acceptance
- B、Scope verification
- C、Scope definition
- D、WBS Creation
参考答案
更多 “ ()is the process of obtaining the stakeholders’ formal acceptance of the completed project scope.Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.A、Project acceptanceB、Scope verificationC、Scope definitionD、WBS Creation” 相关考题
考题
● The project (73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.(73)A. work performance informationB. scope statementC. change requestsD. process analysis
考题
●(74) describes, in detail, the project' s deliverables and the work required to create those deliverables.(74) A. Product scope descriptionB. Project objectivesC. Product specificationD. The project scope statement
考题
is the process of obtaining the stakeholdrs'formal acceptance of the completed project scope. Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.A.WBS CreationB.Scope definitionC.Project acceptanceD.Scope verification
考题
The project()is a key input to quality planning since it documents major project deliverables,the project objectives that serve to define important stakeholder requirements,thresholds,and acceptance criteriaA.work performance informationB.scope statementC.change requestsD.process analysis
考题
is the process of obtaining the stakeholders' formal acceptance of the completed project scope. Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.A.Project acceptanceB.Scope verificationC.Scope definitionD.WBS Creation
考题
______describes,in detail,the project's deliverables and the work required to create those deliverables.A.Product scope descriptionB.Project objectivesC.Stakeholder AnalysisD.The project scope statement
考题
The project(73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.A.work performance informationB.scope statementC.change requestsD.process analysis
考题
()is the process of formalizing acceptance of the completed project deliverables. The key benefit of this process is that it brings objectivity to the acceptance process and increases the probability of final product, service,or result acceptance by validating each deliverable。A、Validate scopeB、Define scopeC、Control scopeD、Collect requirement
考题
The( )is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables.
A、project scope statementB、work packageC、WBSD、project scope plan
考题
is the process of obtaining the stakeholdrs' formal acceptance of the completed project Scope. Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.A.Project acceptanceB.Scope verificationC.Scope definitionD.WBS Creation
考题
Validate Scope is the process of formalizing acceptance of completed().A.project deliverablesB.WBSC.activitiesD.milestones
考题
The scope management plan is how the team will prepare the()a document that includes descriptions of create the WBS, verify completion of the project deliverables, and control requests for changes to the project scope.A.project charterB.project scope goalC.project budgetD.project scope statement
考题
()describees,indetail,the project's deliverables and the work required to create those deliverables.
A.Product scope description
B.Project objectives
C.Produce specification
D.The project scope statement
考题
()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.A:Create scopE
B:Project stakeholder management
C:Project scope management
D:Project cost management
考题
() is the process of obtaining the stakeholders\' formal acceptance of thecompleted project scope. Verifying the scope includes reviewing deliverables and work results toensure that all were completed satisfactorily. A.Project acceptance
B.Scope verification
C.Scope definition
D.WBS Creation
考题
The()is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables.A.Project scope statement
B.Work package
C.WBS
D.Project scope plan
考题
The scope management plan is how the team will prepare the( )a document that includes descriptions of create the WBS,verify completion of the project deliverables,and control requests for changes to the project scope. A.project charter
B.project scope goal
C.project budget
D.project scope statement
考题
()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.A. Create scopE
B. Project stakeholder management
C. Project scope management
D. Project cost management
考题
()is the process of obtaining the stakeholders’ formal acceptance of the completed project scopE. Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.A、Project acceptanceB、Scope verificationC、Scope definitionD、WBS Creation
考题
The project()is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements,thresholds, and acceptance criteria.A、work performance informationB、scope statementC、changerequestsD、process analysis
考题
()describes, in detail, the project’s deliverables and the work required to create those deliverables.A、Product scope descriptionB、Project objectivesC、Stakeholder AnalysisD、The project scope statement
考题
() is the process of obtaining the stakeholders' formal acceptance of the completed project scope .verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.A、projectacceptanceB、scopeverificationC、scopedefinitionD、WBS Creation
考题
The () describes, in detail, the project's deliverables and the work required to create those deliverables.A、project scope statementB、project requirementC、project charterD、product specification
考题
单选题() is the process of obtaining the stakeholders' formal acceptance of the completed project scope .verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.A
projectacceptanceB
scopeverificationC
scopedefinitionD
WBS Creation
考题
单选题()describes, in detail, the project’s deliverables and the work required to create those deliverables.A
Product scope descriptionB
Project objectivesC
Stakeholder AnalysisD
The project scope statement
考题
单选题()is the process of obtaining the stakeholders’ formal acceptance of the completed project scopE. Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.A
Project acceptanceB
Scope verificationC
Scope definitionD
WBS Creation
考题
单选题()is the process of obtaining the stakeholders’ formal acceptance of the completed project scope.Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.A
Project acceptanceB
Scope verificationC
Scope definitionD
WBS Creation