Each box is an activity;the number it contains is the duration of the activity in days.The duration of the critical path is.

A.16 days
B.14 days
C.19 days
D.20 days

参考答案

参考解析
解析:题意:每一个方块代表一个活动,其中的数字是互动持续时间(天为单位),求关键路径的时间。

关键路径就是看每一个并行过程最大值的路径。如图,应该是:3→6→7→1→2,共19天。
更多 “Each box is an activity;the number it contains is the duration of the activity in days.The duration of the critical path is. A.16 days B.14 days C.19 days D.20 days” 相关考题
考题 Which of the following impacts the critical path?A.Changing the task duration.B.Reduce the free float of an activity.C.Executing a backward passD.A or BE.None of the above.

考题 The range of time allowed for an activity to be completed in is the _____.A.Planned time (Duration).B.Float time (LS - ES, or LF - EF).C.Critical time (when ES = LS, or EF = LF).D.Scheduled time (LF - ES).E.Event.

考题 A non-critical path activity is completed in half the time. Then,A.The critical path is also reduced.B.The slack in the path containing this activity will increase.C.The total cost for this activity has decreased.D.Manpower from this activity can be assigned to other activities.E.All of the above.

考题 Once the logic of a network is laid out, the project manager will conduct a forward pass and backward pass through the network. This will provide information on the _____ and identification of the _____ .A.Slack for each activity, critical path.B.Slack for each activity, high risk activities.C.Manpower shortages, high risk activities.D.High risk activities, non-critical paths.E.Manpower availability, contingency plans.

考题 Activities with zero time duration are referred to as:A.Critical path activites.B.Noncritical path activities.C.Slack time activities.D.DummiesE.None of above.

考题 Using the data shown in the Special window, Activities P, Q, and T are critical path activities. In order to shorten the time duration of the project, which activity should be "crashed" first?A . PB . QC . RD . SE . T

考题 The schedule risk is the _____ .A the accumulated "expected' durations which maintain project completion.B Critical Path adjusted by "high-risk" activity float.C highest risk path that maintains quality.D Critical Path when calculated with "most likely" duration.E highest risk path that contributes the most risk toward the project completion.

考题 112 The schedule risk is the _____ .A. the accumulated "expected' durations which maintain project completion.B. Critical Path adjusted by "high-risk" activity float.C. highest risk path that maintains quality.D. Critical Path when calculated with "most likely" duration.E. highest risk path that contributes the most risk toward the project completion

考题 153 The range of time allowed for an activity to be completed in is the _____.A. Planned time (Duration).B. Float time (LS - ES, or LF - EF).C. Critical time (when ES = LS, or EF = LF).D. Scheduled time (LF - ES).E. Event

考题 Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order. A.activity duration estimating, schedule developing, activity resource estimatingB.activity resource estimating, activity duration estimating, schedule developmentC.schedule developing, activity resource estimating, activity duration estimatingD.activity resource estimating, schedule developing, activity duration estimating

考题 112 Using the data shown in the Special window, Activities P, Q, and T are critical path activities. In order to shorten the time duration of the project, which activity should be "crashed" first?A. PB. QC. RD. SE. T

考题 35 The range of time allowed for an activity to be completed in is the _____.A. Planned time (Duration).B. Float time (LS - ES, or LF - EF).C. Critical time (when ES = LS, or EF = LF).D. Scheduled time (LF - ES).E. Event.

考题 ● Which of the following impacts the critical path?A Changing the task duration.B Reduce the free float of an activity.C Executing a backward passD A or BE None of the above.

考题 ● The range of time allowed for an activity to be completed in is the _____.A Planned time (Duration).B Float time (LS - ES, or LF - EF).C Critical time (when ES = LS, or EF = LF).D Scheduled time (LF - ES).E Event.

考题 ● A non-critical path activity is completed in half the time. Then,A The critical path is also reduced.B The slack in the path containing this activity will increase.C The total cost for this activity has decreased.D Manpower from this activity can be assigned to other activities.E All of the above.

考题 ● On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and (70) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.A.time estimatingB.cost estimatingC.project planningD.schedule development

考题 ● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.(71)A.activity duration estimating, schedule developing, activity resource estimatingB . activity resource estimating, activity duration estimating, schedule developmentC.schedule developing, activity resource estimating, activity duration estimatingD.activity resource estimating, schedule developing, activity duration estimating

考题 Each box is an activity; the number it contains is the duration of the activity in days. The duration of the critical path is(75)A.16daysB.14daysC.19daysD.20days

考题 ● Each box is an activity; the number it contains is the duration of the activity in days. The duration of the critical path is (75) .(75)A.16 daysB.14 daysC.19 daysD.20 days

考题 On some projects,especially ones of smaller scope,activity sequencing,activity resource estimating.Activity duration estimating,and (71) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.A.project planningB.time estimatingC.cost estimatingD.schedule development

考题 ( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project.A.ParametricB.AnalogousC.Three-pointD.Expert judgment

考题 ()is a technique for estimating the duration or cost of activity or a projecy using historical data orm a similar activity or project.A.Analogous estimating B.Parametric estimating C.Three-Point estmating D.Bottom-Up estimating

考题 Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( ) , and schedule control by order. A.activity duration estimating, schedule developing, activity resource estimating B.activity resource estimating, activity duration estimating, schedule development C.schedule developing, activity resource estimating, activity duration estimating D.activity resource estimating, schedule developing, activity duration estimating

考题 ( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project. A.Parametric B.Analogous C.Three-point D.Expert judgment

考题 Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.A、activity duration estimating, schedule developing, activity resource estimatingB、activity resource estimating, activity duration estimating, schedule developmentC、schedule developing, activity resource estimating, activity duration estimatingD、activity resource estimating, schedule developing, activity duration estimating

考题 单选题On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and()are so tightly linkedthat they are viewed as a single process that can be performed by a person over a relatively short period of time.A time estimatingB cost estimatingC project planningD schedule development

考题 单选题Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.A activity duration estimating, schedule developing, activity resource estimatingB activity resource estimating, activity duration estimating, schedule developmentC schedule developing, activity resource estimating, activity duration estimatingD activity resource estimating, schedule developing, activity duration estimating