考题
AnadministratorhasimplementedthefollowingLPARsonaPower570with32GBmemorywith512MBremainingforallocation:LPAR1memory:min=10GBdes=15GBmax=24GBLPAR2memory:min=10GBdes=15GBmax=24GBTheadministratorreceivesarequesttoadd2GBtoLPAR1.TheonlywaytodothisisbymovingmemoryfromLPAR2toLPAR1.Theadministratorattemptstomovethememory,buttheoperationfails.Theadministratorcanhoweverallocate512MBthatisfreetoLPAR1onthe570.Whatisthemostlikelycauseofthisfailurewhendynamicallymovingmemory?()
考题
A system administrator is creating four LPARs on a Power 550. The Power 550 has 64GB of memoryinstalled and 32GB activated. The system administrator sets the minimum dedicated memory to 8GB in the profile for each LPAR. After activating three LPARs, he is not able to activate the fourth LPAR. What is the likely cause of the problem?()A、The Power 550 is licensed for three LPARs only.B、There is not enough memory to meet the minimum dedicated memory requirement for the fourth LPAR. A faulty memory DIMM is detected in the POWER5 550.C、There is not enough memory to meet the minimum dedicated memory requirement for the fourth LPAR. The HMC reserves some memory toperform logical partition tasks.D、There is not enough memory to meet the minimum dedicated memory requirement for the fourth LPAR. The hypervisor reserves some memory to perform logical partition tasks.
考题
On a Hardware Management Console (HMC) at version 7, an administrator has an LPAR defined with a minimum of 4GB of memory, 6GB desired and a maximum of 16 GB of memory. The administrator wants to go from 5 GB to 8 GB assigned memory for this partition. In order to make the change, what value should the administrator enter into the add processor resources window? ()A、2 B、3 C、4 D、8
考题
Companycom has the following: 8 x 1.65GHz CPUs 16GB Memory 4 LPARs LPAR 1: Test/Dev 1 CPU, 2GB Memory, 1 Fibre Channel HBA, AIX 5.3 LPAR 2: QA 1 CPU, 2GB Memory, 1 Fibre Channel HBA, AIX 5.3 LPAR 3: Prod 3 CPUs, 6GB Memory, 1 Fibre Channel HBA, AIX 5.3 LPAR 4: Web App 3 CPUs, 6GB Memory, 1 Fibre Channel HBA, SUSE Linux Utilization over a 30 day period LPAR 1: Average utilization was 15%, Peak utilization was 100% LPAR 2: Average utilization was 25%, Peak utilization was 100% LPAR 3: Average utilization was 50%, Peak utilization was 90% LPAR 4: Average utilization was 35%, Peak utilization was 100% If the customer has a requirement for all four LPARs moved to a p5 590 and to have dedicated CPU resources. Which of the following would best describe the profile requirements?()A、LPARs 1 and 2, SMT on, min CPU 1.0, max CPU 1.0, desired CPU 1.0 LPARs 3 and 4, SMT on, min CPU 1.0, max CPU 3.0, desired CPU 2.0 B、LPARs 1 and 2, SMT on, min CPU 1.0, max CPU 1.0, desired CPU 1.0 LPARs 3 and 4, SMT on, min CPU 2.0, max CPU 3.0, desired CPU 3.0 C、LPARs 1 and 2, SMT on, min CPU 1.0, max CPU 3.0, desired CPU 3.0 LPARs 3 and 4, SMT on, min CPU 1.0, max CPU 3.0, desired CPU 2.0 D、LPARs 1 and 2, SMT off, min CPU 1.0, max CPU 1.0, desired CPU 1.0 LPARs 3 and 4, SMT off, min CPU 1.0, max CPU 3.0, desired CPU 3.0
考题
An administrator is adding additional memory into a server that registers 1GB of memory in the OS and notices that the system has 2GB of memory physically installed; however, the server only shows 1GB of memory during POST. Which of the following is the MOST likely reason for this?()A、 The OS does not support more than 1GB of memory.B、 The system memory has different manufacture dates.C、 Two of the memory sticks are defective.D、 The server is using memory interleaving.
考题
A system administrator has been instructed to attach storage in their client LPARs, in a Power 770, with fibre channel adapters using N_port ID virtualization (NPIV). Which of the following partitions has the minimum requirements to utilize virtual fibre channel?()A、LPAR-A with 1Gb FC HBA and SAN connectionB、LPAR-B with 2Gb FC HBA and SAN connectionC、LPAR-C with 4Gb FC HBA and SAN connectionD、LPAR-D with 8Gb FC HBA and SAN connection
考题
Company.com has recently added a partition to an existing p5-550 4-way with 8GB RAM. When the newly-created third partition is started, it fails to initialize. The configuration of the partitions is as follows: LPAR Min CPU Des CPU Max CPU P1 0.8 1.4 2.0 P2 0.8 1.4 2.0 P3 1.4 1.6 2.0 Which of the following actions will most likely resolve the problem?()A、Reduce P3 max CPU to 1.8B、Reduce min CPU on P3 to 1.2.C、Recommend the purchase of additional CPU.D、Ensure that partition 3 has a minimum of 4GB of memory.
考题
Which of the following x366 8GB memory configurations will produce the best performance?()A、One memory card with four 2GB DIMMsB、Two memory cards with four 2GB DIMMsC、Two memory cards with eight 1GB DIMMsD、Four memory cards with eight 1GB DIMMs
考题
A customer has purchased an IBM BladeCenter H chassis and needs the following servers: --Two HS21 blade servers each with 8GB memory and 2 drives --Two HS21 blade servers each with 24GB memory and 2 drives --Two LS21 blade servers each with 2GB memory and 2 Hot-Swap SCSI drives How many total server bays will be required for this configuration?()A、6B、8C、10D、12
考题
A p5-570 8-way 32GB system has been proposed to a customer as a new test system with four LPARs. The current applications are certified on AIX 5.2 but not yet on AIX 5.3. The customer wants to understand the advantages and disadvantages of this solution versus a pair of 4-way p5-550s with 16GB each in testing their current applications. Which of the following points should the pSeries technical specialist highlight?()A、The p5-570 would save rack space over a pair of p5-550 servers.B、The p5-570 allows for more CPU and memory resources to be dynamically allocated to any LPAR for performance testing.C、The p5-570 can only be upgraded to 64GB of RAM without replacing memory.D、The p5-570 supports advanced features such as Micro-Partitioning and Virtual I/O allowing more LPARs of the customer’s applications with fewer processors and fewer I/O adapters.
考题
A cluster administrator has been asked to install HACMP on two nodes with the following hardware: -two CPUs, - 1GB RAM, - one 1 36GB drive, -two 10/100/1000 Ethernet adapters, and -GB Fibre Channel adapters dual attached to SAN storage. In order to eliminate single points of failure,the administrator should first add which of the following:() A、 an additional 1GB RAM to each node.B、 Another bootable mirrored disk drive.C、 A 10/100/1000 GB Ethernet adapter to be attached to a redundant switch.D、 Nothing,because this is a viable cluster solution with no single points of failure.
考题
A competitor informed a customer that blades were not suitable to implement robust virtual computing infrastructures due to memory limitations. What is the maximum memory supported by an IBM Intel Blade using what size memory DIMMs? ()A、16GB using 4GB Memory DIMMsB、8GB using 2GB Memory DIMMsC、32GB using 4GB Memory DIMMsD、16GB using 2GB Memory DIMMs
考题
A customer has the following equipment installed in their data center: (1)an IBM BladeCenter H chassis (2)two power supplies (3)six HS22V blades (4)three Nortel 1/10 GB ESMs The retail customer purchased a new HX5 with MAX5. Which of the following must be added to install the HX5 with MAX5?()A、Two additional power suppliesB、Fibre Channel (FC) switches and SAN storageC、A Nortel 1/10 GB ESMD、SSD for the HX5
考题
An administrator has installed 1 VIO Server and 5 client LPARs on a 16-core Power 570 with the following CPU requirements: Virtual Processors Processing Units Min Desired Max Min Desired Max VIOS1 1 2 4 0.1 1.0 2.0 LPAR1 4 4 4 4.0 4.0 4.0 LPAR2 2 5 8 1.0 5.0 6.0 LPAR3 1 3 4 0.1 0.3 1.0 LPAR4 3 6 9 0.5 3.0 6.0 LPAR5 1 3 6 1.0 3.0 .06 If the administrator activates the LPARs in the above order, what will be the result? ()A、 All LPARs will start except LPAR5.B、 All LPARs will start with desired capacity.C、 All LPARs will start but LPAR5 will have its minimum capacity assigned.D、 All LPARs will start but LPAR5 will have less than its desired capacity.
考题
Companycom wants to buy a new p5 570 running AIX 5.3. The applications require 4 processors and 8GB of memory. There is a requirement to have a Virtual IO Server. What is the smallest p5 570 that should be sold to this customer?()A、4 processors 8GB of memoryB、5 processors 8GB of memoryC、4 processors 10GB of memoryD、5 processors 10GB of memory
考题
Companycom has the following: 8 x 1.65GHz CPUs 16GB Memory 4 LPARs LPAR 1: Test/Dev 1 CPU, 2GB Memory, 1 Fibre Channel HBA, AIX 5.3 LPAR 2: QA 1 CPU, 2GB Memory, 1 Fibre Channel HBA, AIX 5.3 LPAR 3: Prod 3 CPUs, 6GB Memory, 1 Fibre Channel HBA, AIX 5.3 LPAR 4: Web App 3 CPUs, 6GB Memory, 1 Fibre Channel HBA, SUSE Linux Utilization over a 30 day period LPAR 1: Average utilization was 15%, Peak utilization was 100% LPAR 2: Average utilization was 25%, Peak utilization was 100% LPAR 3: Average utilization was 50%, Peak utilization was 90% LPAR 4: Average utilization was 35%, Peak utilization was 100% If the customer has a requirement for all four LPARs to be moved to a p5 590 and assigned to a shared pool. Which of the following would best describe the profile requirements?()A、LPARs 1 and 2, capped, SMT on, Weights between 25-30, min CPU 0.1, max CPU 1.0 LPARs 3 and 4, uncapped, SMT on, Weights between 100-130, min CPU 2.7, max CPU 3.0B、LPARs 1 and 2, capped, SMT on, Weights between 100-130, min CPU 0.1, max CPU 1.0 LPARs 3 and 4, uncapped, SMT on, Weights between 25-30, min CPU 2.7, max CPU 3.0 C、LPARs 1 and 2, uncapped, SMT on, Weights between 25-30, min CPU 0.1, max CPU 1.0 LPARs 3 and 4, capped, SMT on, Weights between 100-130, min CPU 2.7, max CPU 3.0D、LPARs 1 and 2, uncapped, SMT off, Weights between 25-30, min CPU 0.1, max CPU 1.0 LPARs 3 and 4, capped, SMT on, Weights between 100-130, min CPU 2.7, max CPU 3.0
考题
You enabled Automatic Shared Memory Management. The initialization parameters are set as shown below: SGA_TARGET = 10GB SGA_MAX_SIZE = 14GB STREAMS_POOL_SIZE = 1GB SHARED_POOL_SIZE = 3GB Which two statements are correct in this scenario? ()A、 A total of 14 GB memory will be allocated to the automatically tuned memory componentsB、 Reducing the value for SGA_TARGET to 9 GB will automatically decrease the memory allocated to shared pool from 3 GB to 2 GBC、 The value for SGA_TARGET can be increased up to a maximum of 14 GBD、 A maximum of 3 GB can be allocated to shared poolE、 Increasing the value for SGA_TARGET to 12 GB will automatically increase the memory allocated to autotuned parametersF、 Increasing the value for SGA_TARGET will automatically increase the memory allocated for STREAMS_POOL_SIZE
考题
You enabled Automatic Shared Memory Management. The initialization parameters are set as shown below: SGA_TARGET= 10GB SGA_MAX_SIZE = 14GB STREAMS_POOL_SIZE = 1GB SHARED_POOL_SIZE = 3GB Which two statements are correct in this scenario? ()A、 A maximum of 3 GB can be allocated to shared poolB、 The value for SGA_TARGET can be increased up to a maximum of 15 GBC、 A total of 14 GB memory will be allocated to the automatically tuned memory components.D、 Increasing the value for SGA_TARGET will automatically increase the memory allocated for STREAMS_POOL_SIZEE、 Increasing the value for SGA_TARGET to 12 GB will automatically increase the memory allocated to autotuned parametersF、 Reducing the value for SGA_TARGET to 9 GB will automatically decrease the memory allocated to shared pool from 3 GB to 2 GB
考题
Your computer runs Microsoft Windows XP Professional. The computer has the following hardware configuration: 512 MB of RAM 1-GHz processor 60-GB hard disk 15 GB of free space 64-MB video adapter. You perform a clean install of Microsoft Windows Vista. You need to ensure that Microsoft Windows Aero Experience is supported. What should you do?()A、Upgrade the memory to 1 GB of RAM.B、Upgrade the hard disk to 120 GB with 40 GB of free space.C、Install a video adapter that has 128 MB of RAM, support for Microsoft DirectX 9, and Microsoft Pixel Shader 2.0.D、Install a video adapter that has 128 MB of RAM, support for Microsoft Scalable Link Interface (SLI) and Microsoft Pixel Shader 2.0.
考题
单选题A system administrator has been instructed to attach storage in their client LPARs, in a Power 770, with fibre channel adapters using N_port ID virtualization (NPIV). Which of the following partitions has the minimum requirements to utilize virtual fibre channel?()A
LPAR-A with 1Gb FC HBA and SAN connectionB
LPAR-B with 2Gb FC HBA and SAN connectionC
LPAR-C with 4Gb FC HBA and SAN connectionD
LPAR-D with 8Gb FC HBA and SAN connection
考题
单选题An administrator has implemented the following LPARs on a Power 570 with 32 GB memory with 512 MB remaining for allocation: LPAR 1 memory : min = 10 GB des = 15 GB max = 24 GB LPAR 2memory : min = 10 GB des = 15 GB max = 24 GB The administrator receives a request to add 2 GB to LPAR 1. The only way to do this is by moving memory from LPAR 2 to LPAR 1. The administrator attempts to move the memory, but the operation fails. The administrator can however allocate 512 MB that is free to LPAR 1 on the 570. What is the most likely cause of this failure when dynamically moving memory?()A
Maxperm% is set too low on LPAR 2B
Insufficient paging space on LPAR 1C
Service IBM.DRM is unavailable on LPAR 1D
Insufficient pinnable memory frames available on LPAR 2
考题
单选题A competitor informed a customer that blades were not suitable to implement robust virtual computing infrastructures due to memory limitations. What is the maximum memory supported by an IBM Intel Blade using what size memory DIMMs? ()A
16GB using 4GB Memory DIMMsB
8GB using 2GB Memory DIMMsC
32GB using 4GB Memory DIMMsD
16GB using 2GB Memory DIMMs
考题
单选题On a Hardware Management Console (HMC) at version 7, an administrator has an LPAR defined with a minimum of 4GB of memory, 6GB desired and a maximum of 16 GB of memory. The administrator wants to go from 5 GB to 8 GB assigned memory for this partition. In order to make the change, what value should the administrator enter into the add processor resources window? ()A
2 B
3 C
4 D
8
考题
单选题Companycom has the following: 8 x 1.65GHz CPUs 16GB Memory 4 LPARs LPAR 1: Test/Dev 1 CPU, 2GB Memory, 1 Fibre Channel HBA, AIX 5.3 LPAR 2: QA 1 CPU, 2GB Memory, 1 Fibre Channel HBA, AIX 5.3 LPAR 3: Prod 3 CPUs, 6GB Memory, 1 Fibre Channel HBA, AIX 5.3 LPAR 4: Web App 3 CPUs, 6GB Memory, 1 Fibre Channel HBA, SUSE Linux Utilization over a 30 day period LPAR 1: Average utilization was 15%, Peak utilization was 100% LPAR 2: Average utilization was 25%, Peak utilization was 100% LPAR 3: Average utilization was 50%, Peak utilization was 90% LPAR 4: Average utilization was 35%, Peak utilization was 100% If the customer has a requirement for all four LPARs to be moved to a p5 590 and assigned to a shared pool. Which of the following would best describe the profile requirements?()A
LPARs 1 and 2, capped, SMT on, Weights between 25-30, min CPU 0.1, max CPU 1.0 LPARs 3 and 4, uncapped, SMT on, Weights between 100-130, min CPU 2.7, max CPU 3.0B
LPARs 1 and 2, capped, SMT on, Weights between 100-130, min CPU 0.1, max CPU 1.0 LPARs 3 and 4, uncapped, SMT on, Weights between 25-30, min CPU 2.7, max CPU 3.0 C
LPARs 1 and 2, uncapped, SMT on, Weights between 25-30, min CPU 0.1, max CPU 1.0 LPARs 3 and 4, capped, SMT on, Weights between 100-130, min CPU 2.7, max CPU 3.0D
LPARs 1 and 2, uncapped, SMT off, Weights between 25-30, min CPU 0.1, max CPU 1.0 LPARs 3 and 4, capped, SMT on, Weights between 100-130, min CPU 2.7, max CPU 3.0
考题
单选题An administrator is adding additional memory into a server that registers 1GB of memory in the OS and notices that the system has 2GB of memory physically installed; however, the server only shows 1GB of memory during POST. Which of the following is the MOST likely reason for this?()A
The OS does not support more than 1GB of memory.B
The system memory has different manufacture dates.C
Two of the memory sticks are defective.D
The server is using memory interleaving.
考题
单选题Companycom has the following: 8 x 1.65GHz CPUs 16GB Memory 4 LPARs LPAR 1: Test/Dev 1 CPU, 2GB Memory, 1 Fibre Channel HBA, AIX 5.3 LPAR 2: QA 1 CPU, 2GB Memory, 1 Fibre Channel HBA, AIX 5.3 LPAR 3: Prod 3 CPUs, 6GB Memory, 1 Fibre Channel HBA, AIX 5.3 LPAR 4: Web App 3 CPUs, 6GB Memory, 1 Fibre Channel HBA, SUSE Linux Utilization over a 30 day period LPAR 1: Average utilization was 15%, Peak utilization was 100% LPAR 2: Average utilization was 25%, Peak utilization was 100% LPAR 3: Average utilization was 50%, Peak utilization was 90% LPAR 4: Average utilization was 35%, Peak utilization was 100% If the customer has a requirement for all four LPARs moved to a p5 590 and to have dedicated CPU resources. Which of the following would best describe the profile requirements?()A
LPARs 1 and 2, SMT on, min CPU 1.0, max CPU 1.0, desired CPU 1.0 LPARs 3 and 4, SMT on, min CPU 1.0, max CPU 3.0, desired CPU 2.0 B
LPARs 1 and 2, SMT on, min CPU 1.0, max CPU 1.0, desired CPU 1.0 LPARs 3 and 4, SMT on, min CPU 2.0, max CPU 3.0, desired CPU 3.0 C
LPARs 1 and 2, SMT on, min CPU 1.0, max CPU 3.0, desired CPU 3.0 LPARs 3 and 4, SMT on, min CPU 1.0, max CPU 3.0, desired CPU 2.0 D
LPARs 1 and 2, SMT off, min CPU 1.0, max CPU 1.0, desired CPU 1.0 LPARs 3 and 4, SMT off, min CPU 1.0, max CPU 3.0, desired CPU 3.0
考题
单选题Companycom wants to buy a new p5 570 running AIX 5.3. The applications require 4 processors and 8GB of memory. There is a requirement to have a Virtual IO Server. What is the smallest p5 570 that should be sold to this customer?()A
4 processors 8GB of memoryB
5 processors 8GB of memoryC
4 processors 10GB of memoryD
5 processors 10GB of memory