60 Assigning resources in an attempt to find the shortest project schedule consistent with fixed resource limits is called resource _____.
A. Allocation.
B. Partitioning
C. Leveling
D. Quantification.
E. None of above.
参考答案
更多 “ 60 Assigning resources in an attempt to find the shortest project schedule consistent with fixed resource limits is called resource _____.A. Allocation.B. PartitioningC. LevelingD. Quantification.E. None of above. ” 相关考题
考题
The project scope/charter baseline includes:A.Summary of background conditions defining the project.B.Organization, authority and responsibility relationships.C.Functions to be performed.D.Resource requirement schedule including time estimates.E.All of the above.
考题
Resource leveling _____.A.Allocates resources to activities to find shortest schedule within fixed resource limits.B.Smoothes out resource requirements by rescheduling activities within their float time.C.Smooths out resource requirements by substituting activities with unassigned resources.D.Attempts to reduce resource requirements within a constraint on project durationE.B or D
考题
Assigning resources in an attempt to find the shortest project schedule consistent with fixed resource limits is called resource _____.A.Allocation.B.PartitioningC.LevelingD.Quantification.E.None of above.
考题
Smoothing out resource requirements from period to period is called resource _____.A.Allocation.B.PartitioningC.Leveling.D.QuantificationE.None of above.
考题
A life cycle project manager tends to have the following characteristics:A . balanced trainingB . stronger administrative skills than technical skillsC . stronger technical skills than administrative skillsD . stronger human resource skillsE . None of the above.
考题
172 Smoothing out resource requirements from period to period is called resource _____.A. Allocation.B. PartitioningC. Leveling.D. QuantificationE. None of above
考题
178 Assigning resources in an attempt to find the shortest project schedule consistent with fixed resource limits is called resource _____.A. Allocation.B. PartitioningC. LevelingD. Quantification.E. None of above.
考题
171 Resource leveling _____.A. Allocates resources to activities to find shortest schedule within fixed resource limits.B. Smoothes out resource requirements by rescheduling activities within their float time.C. Smooths out resource requirements by substituting activities with unassigned resources.D. Attempts to reduce resource requirements within a constraint on project durationE. B or D
考题
● The project scope/charter baseline includes:A Summary of background conditions defining the project.B Organization, authority and responsibility relationships.C Functions to be performed.D Resource requirement schedule including time estimates.E All of the above.
考题
● Resource leveling _____.A Allocates resources to activities to find shortest schedule within fixed resource limits.B Smoothes out resource requirements by rescheduling activities within their float time.C Smooths out resource requirements by substituting activities with unassigned resources.D Attempts to reduce resource requirements within a constraint on project durationE B or D
考题
● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.(71)A.activity duration estimating, schedule developing, activity resource estimatingB . activity resource estimating, activity duration estimating, schedule developmentC.schedule developing, activity resource estimating, activity duration estimatingD.activity resource estimating, schedule developing, activity duration estimating
考题
● Many useful tools and techniques are used in developing schedule. (72) is a schedule network analysis technique that modifies the project schedule to account for limited resource.(72)A.PERTB.Resource levellingC.Schedule compressionD.Critical chain method
考题
For which two situations would you use functionality provided by the Resource Manager?()
A. setting idle timeout limits on resource plansB. saving storage space by using compressed backup setsC. creating jobs that will run automatically at a scheduled timeD. assigning priorities to jobs to manage access to system resourcesE. creating alerts to perform notification when tablespaces are low on available space resources
考题
For which two situations would you use functionality provided by the Resource Manager? ()(Choose two.)
A. setting idle timeout limits on resource plansB. saving storage space by using compressed backup setsC. creating jobs that will run automatically at a scheduled timeD. assigning priorities to jobs to manage access to system resourcesE. creating alerts to perform notification when tablespaces are low on available space resources
考题
● Your project is behind schedule due to conflict between team members. Having resolved the conflict, to get the project back on schedule, you should consider __(74)__.(74)A.crashing the scheduleB.performing resource levelingC.conducting reverse resource allocation schedulingD.utilizing the critical chair resources
考题
Your project is behind schedule due to conflict between team members. Having resolved the conflict, to get the project back on schedule, you should consider __(74)__.A.crashing the scheduleB.performing resource levelingC.conducting reverse resource allocation schedulingD.utilizing the critical chair resources
考题
Many useful tools techniques are used in developing schedule. ( )s a schedule network analysis technique that modifies the project schedule to account for limited resource.A.PERT B.Resource levelling C.Schedule compression D.Critical chain method
考题
??Many useful tools and techniques are used in developing schedule.( 73) is a schedulenetwork analysis technique that modifies the project schedule to account for limited resource??A.PERTB. Resource levellingC.Schedule compressionD.Critical chain method
考题
Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( ) , and schedule control by order. A.activity duration estimating, schedule developing, activity resource estimating
B.activity resource estimating, activity duration estimating, schedule development
C.schedule developing, activity resource estimating, activity duration estimating
D.activity resource estimating, schedule developing, activity duration estimating
考题
Many useful tools and techniques are used in developing schedule. ( ) is a schedule network analysis technique that modifies the project schedule to account for limited resource.A.PERT
B.Resource levelling
C.Schedule compression
D.Critical chain methoD.
考题
Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( ) , and schedule control by order. A.activity duration estimating, schedule developing, activity resource estimating
B.activity resource estimating, activity duration estimating, schedule development
C.schedule developing, activity resource estimating, activity duration estimating
D.activity resource estimating, schedule developing, activity duration estimating
考题
Your project is behind schedule due to conflict between team members. Having resolved the conflict,to get the project back on schedule,you should consider ( ) . A.crashing the schedule
B.performing resource leveling
C.conducting reverse resource allocation scheduling
D.utilizing the critical chair resources
考题
Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.A、activity duration estimating, schedule developing, activity resource estimatingB、activity resource estimating, activity duration estimating, schedule developmentC、schedule developing, activity resource estimating, activity duration estimatingD、activity resource estimating, schedule developing, activity duration estimating
考题
Your project is behind schedule due to conflict between team members . Havingresolved the conflict, to get the project back on schedule , you should consider ().A、crashing the scheduleB、performing resource levelingC、conducting reverse resource allocation schedulingD、utilizing the critical chain resources
考题
For which two situations would you use functionality provided by the Resource Manager? ()(Choose two.)A、setting idle timeout limits on resource plansB、saving storage space by using compressed backup setsC、creating jobs that will run automatically at a scheduled timeD、assigning priorities to jobs to manage access to system resourcesE、creating alerts to perform notification when tablespaces are low on available space resources
考题
For which two situations would you use functionality provided by the Resource Manager?()A、setting idle timeout limits on resource plansB、saving storage space by using compressed backup setsC、creating jobs that will run automatically at a scheduled timeD、assigning priorities to jobs to manage access to system resourcesE、creating alerts to perform notification when tablespaces are low on available space resources
考题
单选题Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.A
activity duration estimating, schedule developing, activity resource estimatingB
activity resource estimating, activity duration estimating, schedule developmentC
schedule developing, activity resource estimating, activity duration estimatingD
activity resource estimating, schedule developing, activity duration estimating