Scope management is:A.a project control function.B.employs change control.C.a work authorization process.D.considers Cost, Quality and Schedule.E.All of the above.
考题
The best way to insure quality conformance is to _____.A . distribute the responsibility to subordinates.B . maintain total control.C . train each worker to implement the work.D . inspect quality into the project.E . None of the above.
考题
In order to achieve long-term quality improvements, management must do the following:A . Motivate the employees with seminars, contests, and institute programs such as "Quality Improvement' day.B . Create a quality control department and give the head of the department ultimate responsibility for quality improvement.C . Implement of a formal quality control program with worker and management involvement.D . Establish financial incentive packages for worker.E . A and D
考题
In the project environment, the individual ultimately responsible for quality control is:A . The line workers who must strive "to do things right the first time" to avoid quality problems.B . the company's quality control manager who must work with the project members to ensure the quality control program is effective.C . The head of the production department who retains ultimate quality control responsibility for all the company's projects.D . The project manager who has ultimate responsibility for the entire project.E . the customer who must ensure that he is receiving a quality product from the vendor.
考题
Of the following, who has the ultimate responsibility for meeting project quality objectives?A . Project EngineerB . Project ManagerC . Functional ManagerD . Quality Assurance ManagerE . Project Owner
考题
Which of the following statements about the cost of quality are true?A . the cost of quality is the expense of nonconformance to requirements and specifications.B . the cost of quality are mostly the direct responsibility of workers who are manufacturing the product.C . quality control programs should be implemented when the cost of quality are deemed affordable by management.D . A and B.E . A and C
考题
● Performing (74) involves monitoring specific project results to determine if they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory results.(74)A. quality planningB. quality assuranceC. quality performanceD. quality control
考题
5 Japanese quality control has improved dramatically in the last 30 years for all of the following reasons except:A. the use of quality circles.B. small, continuous improvements in quality control.C. the use of worker suggestion systems.D. the use of quality control charts.E. focusing quality control efforts on production outputs
考题
16 Which of the following statements about the cost of quality are true?A. the cost of quality is the expense of nonconformance to requirements and specifications.B. the cost of quality are mostly the direct responsibility of workers who are manufacturing the product. C. quality control programs should be implemented when the cost of quality are deemed affordable by management.D. A and B.E. A and C
考题
41 In the project environment, the individual ultimately responsible for quality control is:A. The line workers who must strive "to do things right the first time" to avoid quality problems. B. the company's quality control manager who must work with the project members to ensure the quality control program is effective.C. The head of the production department who retains ultimate quality control responsibility for all the company's projects.D. The project manager who has ultimate responsibility for the entire project.E.the customer who must ensure that he is receiving a quality product from the vendor
考题
99 Scope management is:A. a project control function.B. employs change control.C. a work authorization process.D. considers Cost, Quality and Schedule.E. All of the above
考题
112 Of the following, who has the ultimate responsibility for meeting project quality objectives?A. Project EngineerB. Project ManagerC. Functional ManagerD. Quality Assurance ManagerE. Project Owner
考题
179 In the project environment, the individual ultimately responsible for quality control is:A. The line workers who must strive "to do things right the first time" to avoid quality problems.B. the company's quality control manager who must work with the project members to ensure the quality control program is effective.C. The head of the production department who retains ultimate quality control responsibility for all the company's projects.D. The project manager who has ultimate responsibility for the entire project.E. the customer who must ensure that he is receiving a quality product from the vendor
考题
3 In order to achieve long-term quality improvements, management must do the following:A. Motivate the employees with seminars, contests, and institute programs such as "Quality Improvement' day.B Create a quality control department and give the head of the department ultimate responsibility for quality improvement.C. Implement of a formal quality control program with worker and management involvement.D. Establish financial incentive packages for worker.E. A and D
考题
9 The best way to insure quality conformance is to _____.A. distribute the responsibility to subordinates.B maintain total control.C. train each worker to implement the work.D. inspect quality into the project.E. None of the above
考题
98 Which of the following statements about the cost of quality are true?A. the cost of quality is the expense of nonconformance to requirements and specifications.B. the cost of quality are mostly the direct responsibility of workers who are manufacturing the product.C. quality control programs should be implemented when the cost of quality are deemed affordable by management.D. A and B.E. A and C
考题
● Scope management is:A a project control function.B employs change control.C a work authorization process.D considers Cost, Quality and Schedule.E All of the above.
考题
______is the application of planned,systematic quality activities to ensure that the project will employ all processes needed to meet requirements.A.euality assurance(QA)B.Quality planningC.Quality control(QC)D.Quality costs
考题
Performing( )involves monitoring specific project results to determine ifthey comply with relevant quality standards and identifying ways to eliminate causes ofunsatisfactory results。 A.quality planning B.quality assurance C.quality performance D.quality control
考题
● ()is the application ion of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.()A. Quality assurance (QA) B. Quality planningC. Quality control (QC) D. Quality costs
考题
30. How should European companies do? Which of the following is NOT the answer?A. They must be different from the American companies.B. They must raise the quality of the things they sell.C. They must work harder to sell things.D. They must let the buyer touch or see in person.
考题
Project Quality Management must address the management of the project and the(72)of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.A.performanceB.processC.productD.object
考题
( ) is the application of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.A.Quality assurance(QA)
B.Quality planning
C.Quality control(QC)
D.Quality costs
考题
()is the application of planned,systematic quality activities to ensure thatthe project will employ all processes needed to meet requirements.A.Quality assurance(QA)
B.Quality planning
C.Quality control(QC)
D.Quality costs
考题
( )is not included in Control Quality input documents.A.Project management plan
B.Project documents
C.Quality problems report
D.Work performance data
考题
( )in not inc1uded in Control Quality input documents.A.Project management plan
B.Project documents
C.Quality problems report
D.Work performance data
考题
Project Quality Management must address the management of the project and the() of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.A、performanceB、processC、productD、object