网友您好, 请在下方输入框内输入要搜索的题目:
题目内容
(请给出正确答案)
( ) is the application of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.
A.Quality assurance(QA)
B.Quality planning
C.Quality control(QC)
D.Quality costs
B.Quality planning
C.Quality control(QC)
D.Quality costs
参考答案
参考解析
解析:质量计划是质量管理的一部分,致力于制定质量目标,并规定必要的运行过程和相关资源以实现项目质量目标。
质量控制就是项目团队的管理人员采取有效措施,监督项目的具体实施结果,判断它们是否符合项目有关的质量标准,并消除产生不良结果原因的途径。
质量成本是指为满足质量要求所付出的主要成本。
质量保证是通过对质量计划的系统实施,确保项目需要的相关过程达到预期要求的质量活动。选项A是质量保证(QA),选项B是质量计划,选项C是质量控制(QC),选项D是质量成本。因此应选择A。
质量控制就是项目团队的管理人员采取有效措施,监督项目的具体实施结果,判断它们是否符合项目有关的质量标准,并消除产生不良结果原因的途径。
质量成本是指为满足质量要求所付出的主要成本。
质量保证是通过对质量计划的系统实施,确保项目需要的相关过程达到预期要求的质量活动。选项A是质量保证(QA),选项B是质量计划,选项C是质量控制(QC),选项D是质量成本。因此应选择A。
更多 “( ) is the application of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.A.Quality assurance(QA) B.Quality planning C.Quality control(QC) D.Quality costs ” 相关考题
考题
In the project environment, the individual ultimately responsible for quality control is:A . The line workers who must strive "to do things right the first time" to avoid quality problems.B . the company's quality control manager who must work with the project members to ensure the quality control program is effective.C . The head of the production department who retains ultimate quality control responsibility for all the company's projects.D . The project manager who has ultimate responsibility for the entire project.E . the customer who must ensure that he is receiving a quality product from the vendor.
考题
● Project Quality Management processes include all the activities of the (71) that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.(71)A. projectB. project management teamC. performing organizationD. customer
考题
41 In the project environment, the individual ultimately responsible for quality control is:A. The line workers who must strive "to do things right the first time" to avoid quality problems. B. the company's quality control manager who must work with the project members to ensure the quality control program is effective.C. The head of the production department who retains ultimate quality control responsibility for all the company's projects.D. The project manager who has ultimate responsibility for the entire project.E.the customer who must ensure that he is receiving a quality product from the vendor
考题
Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.A.BenchmarkingB.Quality metricC.Quality checklistD.Brainstornung
考题
Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.A.ProjectB.project management teamC.performingorganizationD.customer
考题
● (73)is the application of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.(73)A. Quality assurance (QA)B. Quality planningC. Quality control (QC)D. Quality costs
考题
● Project (69) Management includes the processes required to ensure thatthe project includes all the work required, and only the work required, tocomplete the project successfully.tA.IntegrationB.ScopeC.ConfigurationD.Requiremen
考题
●Quality planning tools are often used to help plan effective quality management activities.(71) is one of such tools, which involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance.(71)A. BenchmarkingB. Quality metricC. Quality checklistD. Brainstorming
考题
______is the application of planned,systematic quality activities to ensure that the project will employ all processes needed to meet requirements.A.euality assurance(QA)B.Quality planningC.Quality control(QC)D.Quality costs
考题
Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups.()process does not belong to Project Integration Management.A.Developing project charterB.Developing project management planC.Analyzing project risksD.Monitoring and controlling project
考题
● ()is the application ion of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.()A. Quality assurance (QA) B. Quality planningC. Quality control (QC) D. Quality costs
考题
Project Quality Management processes include all the activities of the (75) that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.A.performing organizationB.project management teamC.projectD.customer
考题
● Plan Quality is the process of identifying quality requirements and standards for the project and product, and documenting how the project will demonstrate compliance.(75) is a method that analyze all the costs incurred over the life of the product by investment in preventing nonconformance to requirements, appraising the product or service for conformance to requirement, and failing to meet requirements.(75)A.Cost-Benefit analysisB.Control chartsC.Quality function deploymentD.Cost of quality analysis
考题
Project (24) Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.A.IntegrationB.ScopeC.ConfigurationD.Requirement
考题
Plan Quality is the process of identifying quality requirements and standards for the project and product and documenting how the project will demonstrate compliance ______ is a method that analyze all the costs incurred over the life of the product by investment in preventing nonconformance to requirements, appraising the product or service for conformance to requirement and failing to meet requirements.A.Cost-Benefit analysisB.Control chartsC.Quality function deploymentD.Cost of quality analysis
考题
()is the application of planned,systematic quality activities to ensure thatthe project will employ all processes needed to meet requirements.A.Quality assurance(QA)
B.Quality planning
C.Quality control(QC)
D.Quality costs
考题
()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.A:Create scopE
B:Project stakeholder management
C:Project scope management
D:Project cost management
考题
()is the application of planned,systematic.quality activities to ensure that the project will employ all processes to meet requirements.A.Quality assurance
B.Quality planning
C.Quality control
D.Quality cost
考题
()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.A. Create scopE
B. Project stakeholder management
C. Project scope management
D. Project cost management
考题
Quality planning tools are often used to help plan effective quality management activities.( ) is one of such tools,which involves company actual or planned project practices to those or other projects to generate ideas for improvementand to provide a basis by which to measure performance.A、BenchmarkingB、Quality metricC、Quality checklistD、Brainstorming
考题
Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.A、ProjectB、project management teamC、performingorganizationD、customer
考题
Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.A、BenchmarkingB、Quality metricC、Quality checklistD、Brainstornung
考题
Project()Management includes the processes required to ensure that theproj ect includes all the work required, and only the work required, to complete the project successfully.A、IntegrationB、ScopeC、ConfigurationD、Requirement
考题
Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.A、IntegrationB、ScopeC、ConfigurationD、Requirement
考题
单选题Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.A
ProjectB
project management teamC
performingorganizationD
customer
考题
单选题Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.A
BenchmarkingB
Quality metricC
Quality checklistD
Brainstornung
考题
单选题Quality planning tools are often used to help plan effective quality management activities.( ) is one of such tools,which involves company actual or planned project practices to those or other projects to generate ideas for improvementand to provide a basis by which to measure performance.A
BenchmarkingB
Quality metricC
Quality checklistD
Brainstorming