Typical characteristics of a work package include:
ARepresentation of units of work at a level where work is performed
BClearly distinguishes one work package from all others assigned to a single functional group
CLimits the work to be performed to relatively short periods of time
DAll of the above
EA and B only
参考答案
更多 “ Typical characteristics of a work package include:ARepresentation of units of work at a level where work is performedBClearly distinguishes one work package from all others assigned to a single functional groupCLimits the work to be performed to relatively short periods of timeDAll of the aboveEA and B only ” 相关考题
考题
Work packages are used to:A . Represent units of work at a level where work is performed.B . Clearly distinguish one work package from all others assigned to a single functional group.C . Limit the work to be performed to relatively short periods of time.D . All of the above.E . A and B only
考题
When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at theA.taskB.level of effortC.sub-taskD.projectE.work package
考题
Using the WBS shown in the Special window, a typical work package would be:ASoftware developmentBSystems designCCodingDA, B, and CENone of the above.
考题
A task-oriented family tree of activities is a:A.Detailed plan.B.Linear responsibility chart.C.Work breakdown structure.D.Cost account coding system.E.Work package description.
考题
The Cost Performance Index (CPI) measures:A.cost of work performed vs planned costs.B.work performed vs cost of work performed.C.work performed vs planned work.D.direct costs vs indirect costs.E.floating costs vs. sunk costs.
考题
The Cost Performance Index is computed as:A . budget cost of work performed divided by actual cost of work performedB . budget cost of work performed minus actual cost of work performedC . budget cost of work performed minus budget cost of work scheduledD . budget cost of work scheduled divided by budget cost of work performedE . actual cost of work scheduled divided by budget cost of work performed
考题
96 A task-oriented family tree of activities is a:A. Detailed plan.B. Linear responsibility chart.C. Work breakdown structure.D. Cost account coding system.E. Work package description.
考题
114 The Cost Performance Index is computed as:A. budget cost of work performed divided by actual cost of work performedB. budget cost of work performed minus actual cost of work performedC. budget cost of work performed minus budget cost of work scheduledD. budget cost of work scheduled divided by budget cost of work performedE. actual cost of work scheduled divided by budget cost of work performed
考题
115 Typical characteristics of a work package include:A. Representation of units of work at a level where work is performedB. Clearly distinguishes one work package from all others assigned to a single functional group C. Limits the work to be performed to relatively short periods of timeD. All of the aboveE. A and B only
考题
63 When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at theA. taskB. level of effortC. sub-taskD. projectE. work package
考题
68 The Cost Performance Index (CPI) measures:A. cost of work performed vs planned costs.B. work performed vs cost of work performed.C. work performed vs planned work.D. direct costs vs indirect costs.E. floating costs vs. sunk costs.
考题
133 Using the WBS shown in the Special window, a typical work package would be:A. Software developmentB. Systems designC. CodingD. A, B, and CE. None of the above
考题
148 Work packages are used to:A. Represent units of work at a level where work is performed.B. Clearly distinguish one work package from all others assigned to a single functional group.C. Limit the work to be performed to relatively short periods of time.D. All of the above.E. A and B only
考题
● When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at theA taskB level of effortC sub-taskD projectE work package
考题
对一个风险事件的临时应对措施叫做:( )A.工作项(work item)B.工作包(work package)C.权变措施(workaround)D.工作分解结构(work breakdown structure)
考题
● Using the WBS shown in the Special window, a typical work package would be:A Software developmentB Systems designC CodingD A, B, and CE None of the above.
考题
● Typical characteristics of a work package include:A Representation of units of work at a level where work is performedB Clearly distinguishes one work package from all others assigned to a single functional groupC Limits the work to be performed to relatively short periods of timeD All of the aboveE A and B only
考题
● A task-oriented family tree of activities is a:A Detailed plan.B Linear responsibility chart.C Work breakdown structure.D Cost account coding system.E Work package description.
考题
● Using the WBS in the Special window, an instance of a work package is:A Build houseB ExcavateC Prepare FoundationD B and CE None of the above
考题
● (66) from one phase are usually reviewed for completeness and accuracyand approved before work starts on the next phase.A.ProcessB.MilestoneC.Work D.Deliverables
考题
● Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the (75) level.(75)A.independent resourceB.individual work loadC.work milestoneD.work package
考题
( )is the sum of all budgets established for the work to be performed.A.CPI
B.BAC
C.SPI
D.EAC
考题
Define Activities is the process of identifying the specific actions to be performed to produce the ( ) . A.project elements
B.work drafts
C.work package
D.project deliverables
考题
Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the ( ) level. A.independent resource
B.individual work loaD.
C.work milestone
D.work package
考题
Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the ( ) level.A.independent resource
B.individual work load
C.work milestone
D.work package
考题
哪些相关work units(工时单位)描述是错的?()A、操作文本和work units让客户,车间及戴姆勒股份公司沟通更容易B、Work units仅满足保修工作的需要C、一个work units对应到5分钟;12个work units是1小时D、Work units历来细分为基本时间和津贴补偿时间E、领取到维修工单和车辆移动不包括在work units中
考题
单选题The master shall ensure that any seafarers()are provided with an adequate period of rest.A
who have performed work for 14 hoursB
who have performed work in a scheduled rest periodC
who have performed work in a scheduled work periodD
who works hard
热门标签
最新试卷