Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the ( ) level.
A.independent resource
B.individual work loaD.
C.work milestone
D.work package
B.individual work loaD.
C.work milestone
D.work package
参考答案
参考解析
解析:WBS(工作分解结构)是面向可交付物的层次性分析结构,是对完成项目目标、创造可交付物所需执行的项目工作的分解。WBS把项目工作细分为更小、更易管理的工作单元,随着WBS层次的降低,意味着项目工作也越来越详细,直到工作包(work package)的层次。
(75) A.独立资源 B.个人工作负荷 C.工作里程碑 D.工作包
(75) A.独立资源 B.个人工作负荷 C.工作里程碑 D.工作包
更多 “Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the ( ) level. A.independent resource B.individual work loaD. C.work milestone D.work package ” 相关考题
考题
● The project (73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.(73)A. work performance informationB. scope statementC. change requestsD. process analysis
考题
Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()
A.independentresourceB.individualworkloadC.workmilestoneD.workpackage
考题
The()describes, in detail, the project's deliverables and the work required to create those deliverables.
A.project scope statementB.project requirementC.project charterD.product specification
考题
●(74) describes, in detail, the project' s deliverables and the work required to create those deliverables.(74) A. Product scope descriptionB. Project objectivesC. Product specificationD. The project scope statement
考题
● Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the (75) level.(75)A.independent resourceB.individual work loadC.work milestoneD.work package
考题
The project()is a key input to quality planning since it documents major project deliverables,the project objectives that serve to define important stakeholder requirements,thresholds,and acceptance criteriaA.work performance informationB.scope statementC.change requestsD.process analysis
考题
______describes,in detail,the project's deliverables and the work required to create those deliverables.A.Product scope descriptionB.Project objectivesC.Stakeholder AnalysisD.The project scope statement
考题
The project(73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.A.work performance informationB.scope statementC.change requestsD.process analysis
考题
● Which of the following Project Scope Management processes involves subdividing the major project deliverables into smaller, more manageable components? (74)(74)A. Scope PlanningB. Scope VerificationC. Scope Change ControlD. Scope Definition
考题
()is a document generated by the creating WBS process that support the WBS,which provides more detailed descriptions of the components in the WBS.A.The project charterB.The project scope statementC.The WBS dictionaryD.The activity list
考题
The scope management plan is how the team will prepare the()a document that includes descriptions of create the WBS, verify completion of the project deliverables, and control requests for changes to the project scope.A.project charterB.project scope goalC.project budgetD.project scope statement
考题
The ()describes, in detail, the project’s deliverables and the work required to create those deliverables.A.project scope statement
B.project requirement
C.project charter
D.product specification
考题
()describees,indetail,the project's deliverables and the work required to create those deliverables.
A.Product scope description
B.Project objectives
C.Produce specification
D.The project scope statement
考题
Which of the following Project Scope Management processes involves subdividing the major projectdeliverablesinto smaller, more manageable components)()A.Scope Planning
B.Scope Verification
C.Scope Change Control
D.Scope Definition
考题
( ) describes,in detail,the project’s deliverables and the work required to create those deliverables. A.Product scope description
B.Project objectives
C.Stakeholder Analysis
D.The project scope statement
考题
The creation of a work breakdown structure(WBS)is the process of ( ) the major project deliverables. A.subdividing
B.assessing
C.planning
D.integrating
考题
The scope management plan is how the team will prepare the( )a document that includes descriptions of create the WBS,verify completion of the project deliverables,and control requests for changes to the project scope. A.project charter
B.project scope goal
C.project budget
D.project scope statement
考题
Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the ( ) level.A.independent resource
B.individual work load
C.work milestone
D.work package
考题
()describes, in detail, the project’s deliverables and the work required to create those deliverables.A、Product scope descriptionB、Project objectivesC、Stakeholder AnalysisD、The project scope statement
考题
() is the process of obtaining the stakeholders' formal acceptance of the completed project scope .verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.A、projectacceptanceB、scopeverificationC、scopedefinitionD、WBS Creation
考题
The () describes, in detail, the project's deliverables and the work required to create those deliverables.A、project scope statementB、project requirementC、project charterD、product specification
考题
()is the process of obtaining the stakeholders’ formal acceptance of the completed project scope.Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.A、Project acceptanceB、Scope verificationC、Scope definitionD、WBS Creation
考题
单选题The()describes, in detail, the project's deliverables and the work required to create those deliverables.A
project scope statementB
project requirementC
project charterD
product specification
考题
单选题()describes, in detail, the project’s deliverables and the work required to create those deliverables.A
Product scope descriptionB
Project objectivesC
Stakeholder AnalysisD
The project scope statement
考题
单选题The project()is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements,thresholds, and acceptance criteria.A
work performance informationB
scope statementC
changerequestsD
process analysis
考题
单选题The creation ofa work breakdown structure (WBS) is the process of()the major project deliverables.A
subdividingB
assessingC
planningD
integrating
考题
单选题Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()A
independentresourceB
individualworkloadC
workmilestoneD
workpackage