● Interfacing with the customer after project go-ahead is the responsibility of:

A Project sponsor

B Project team

C Project manager

D Functional manager

E All of the above are possible, based upon the size and complexity of the project


参考答案

更多 “ ● Interfacing with the customer after project go-ahead is the responsibility of:A Project sponsorB Project teamC Project managerD Functional managerE All of the above are possible, based upon the size and complexity of the project ” 相关考题
考题 The scope of a project can be expected to change if:A.The project manager must provide cost estimates without having a design conceptB.Oversimplification (underestimating) of the nature of the work occursC.The project manager is assigned after the project is defined, and the cost and schedule are approvedD.A clear objective is not providedE.All of the above are possible based upon the situation

考题 The appointment or selection of a project sponsor is often based upon:AThe strategic importance of the projectBWho the customer isCWhether the organization is project or non-project-drivenDThe profitability of the projectEAll of the above

考题 Interfacing with the customer after project go-ahead is the responsibility of:AProject sponsorBProject teamCProject managerDFunctional managerEAll of the above are possible, based upon the size and complexity of the project

考题 Ensuring that all work is both authorized and funded by contractual documentation is the responsibility of:AThe project managerBThe functional managerCThe project sponsorDThe clientEAll of the above

考题 The scope baseline/project charter is prepared by the:AProject managerBProject manager and project officeCProject manager, project office and functional teamDProject manager, project office, functional team and project sponsorEProject manager, project sponsor and customer/user

考题 Scheduling systems such as PERT, ADM, and PDM are project management tools to be used by:A.The project manager and project office personnel.B.The project team and functional managers.C.The project sponsor.D.All of the above.E.A and B only.

考题 The quality objectives are approved in the conceptual stage of the project by the:A . Project EngineerB . Project ManagerC . Functional ManagerD . Quality Assurance ManagerE . Project Owner

考题 Of the following, who has the ultimate responsibility for meeting project quality objectives?A . Project EngineerB . Project ManagerC . Functional ManagerD . Quality Assurance ManagerE . Project Owner

考题 ● Project Quality Management processes include all the activities of the (71) that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.(71)A. projectB. project management teamC. performing organizationD. customer

考题 The main player in project communication is theA sponsorB project managerC functional managerD functional teamE All of the above.

考题 92 The main player in project communication is theA. sponsorB. project managerC. functional managerD. functional teamE. All of the above

考题 112 Of the following, who has the ultimate responsibility for meeting project quality objectives?A. Project EngineerB. Project ManagerC. Functional ManagerD. Quality Assurance ManagerE. Project Owner

考题 121 The quality objectives are approved in the conceptual stage of the project by the:A. Project EngineerB. Project ManagerC. Functional ManagerD. Quality Assurance ManagerE. Project Owner

考题 123 The scope baseline/project charter is prepared by the:A. Project managerB. Project manager and project officeC. Project manager, project office and functional teamD. Project manager, project office, functional team and project sponsorE. Project manager, project sponsor and customer/user

考题 142 Ensuring that all work is both authorized and funded by contractual documentation is the responsibility of:A. The project managerB. The functional managerC. The project sponsorD. The clientE. All of the above

考题 18 Interfacing with the customer after project go-ahead is the responsibility of:A. Project sponsorB. Project teamC. Project managerD. Functional managerE. All of the above are possible, based upon the size and complexity of the project

考题 32 The appointment or selection of a project sponsor is often based upon:A. The strategic importance of the projectB. Who the customer isC. Whether the organization is project or non-project-drivenD. The profitability of the projectE. All of the above

考题 41 The scope of a project can be expected to change if:A. The project manager must provide cost estimates without having a design concept B. Oversimplification (underestimating) of the nature of the work occursC. The project manager is assigned after the project is defined, and the cost and schedule are approvedD. A clear objective is not providedE. All of the above are possible based upon the situation

考题 Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.A.ProjectB.project management teamC.performingorganizationD.customer

考题 123 The scope of a project can be expected to change if:A. The project manager must provide cost estimates without having a design concept B. Oversimplification (underestimating) of the nature of the work occursC. The project manager is assigned after the project is defined, and the cost and schedule are approved D. A clear objective is not providedE. All of the above are possible based upon the situation

考题 ● The scope of a project can be expected to change if:A The project manager must provide cost estimates without having a design conceptB Oversimplification (underestimating) of the nature of the work occursC The project manager is assigned after the project is defined, and the cost and schedule are approvedD A clear objective is not providedE All of the above are possible based upon the situation

考题 ● The appointment or selection of a project sponsor is often based upon:A The strategic importance of the projectB Who the customer isC Whether the organization is project or non-project-drivenD The profitability of the projectE All of the above

考题 ● Ensuring that all work is both authorized and funded by contractual documentation is the responsibility of:A The project managerB The functional managerC The project sponsorD The clientE All of the above

考题 ● The scope baseline/project charter is prepared by the:A Project managerB Project manager and project officeC Project manager, project office and functional teamD Project manager, project office, functional team and project sponsorE Project manager, project sponsor and customer/user

考题 ● Scheduling systems such as PERT, ADM, and PDM are project management tools to be used by:A The project manager and project office personnel.B The project team and functional managers.C The project sponsor.D All of the above.E A and B only.

考题 Project Quality Management processes include all the activities of the (75) that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.A.performing organizationB.project management teamC.projectD.customer

考题 Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.A、ProjectB、project management teamC、performingorganizationD、customer