网友您好, 请在下方输入框内输入要搜索的题目:

题目内容 (请给出正确答案)

Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to(75) progress.

A.analyze

B.track

C.level

D.extend


参考答案

更多 “ Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to(75) progress.A.analyzeB.trackC.levelD.extend ” 相关考题
考题 The Work Breakdown Structure (WBS) is the basis for communicating:A.Project scope, cost control, schedule, qualityB.Project objectives, dependencies, plan, cost controlC.Project scope, schedule, staffing, cost controlD.Project scope, quality, schedule, dependenciesE.Project budget, schedule, risk factors, work assignments.

考题 120 The Work Breakdown Structure (WBS) is the basis for communicating:A. Project scope, cost control, schedule, qualityB. Project objectives, dependencies, plan, cost controlC. Project scope, schedule, staffing, cost controlD. Project scope, quality, schedule, dependenciesE. Project budget, schedule, risk factors, work assignments

考题 2 The Work Breakdown Structure (WBS) is the basis for communicating:A. Project scope, cost control, schedule, qualityB. Project objectives, dependencies, plan, cost controlC. Project scope, schedule, staffing, cost controlD. Project scope, quality, schedule, dependenciesE. Project budget, schedule, risk factors, work assignments

考题 ● The Work Breakdown Structure (WBS) is the basis for communicating:A Project scope, cost control, schedule, qualityB Project objectives, dependencies, plan, cost controlC Project scope, schedule, staffing, cost controlD Project scope, quality, schedule, dependenciesE Project budget, schedule, risk factors, work assignments.

考题 ● The Estimate Activity Resource process is closely coordinated with the (73)process.(73)A. Estimate CostsB. Sequence ActivitiesC. Plan CommunicationsD. Conduct Procurements

考题 The Estimate Activity Resource process is closely coordinated with the (73)process.(73)A. Estimate CostsB. Sequence ActivitiesC. Plan CommunicationsD. Conduct Procurements

考题 Our meeting was quite accidental.A:occasional B:unexpected C:usual D:planned

考题 He's spent years cultivating a knowledge of art.A:using B:denying C:sharing D:developing

考题 The cost performance index(CPI) is the ratio of earned value to ( ) and can be used to estimate the projected cost of completing the project. A. cost variance B.planneD.cost C.PlanneD.value D.actual cost

考题 He's spent years cultivating a knowledge of art.A:denying B:using C:sharing D:developing