Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to(75) progress.
A.analyze
B.track
C.level
D.extend
参考答案
更多 “ Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to(75) progress.A.analyzeB.trackC.levelD.extend ” 相关考题
考题
The Work Breakdown Structure (WBS) is the basis for communicating:A.Project scope, cost control, schedule, qualityB.Project objectives, dependencies, plan, cost controlC.Project scope, schedule, staffing, cost controlD.Project scope, quality, schedule, dependenciesE.Project budget, schedule, risk factors, work assignments.
考题
120 The Work Breakdown Structure (WBS) is the basis for communicating:A. Project scope, cost control, schedule, qualityB. Project objectives, dependencies, plan, cost controlC. Project scope, schedule, staffing, cost controlD. Project scope, quality, schedule, dependenciesE. Project budget, schedule, risk factors, work assignments
考题
2 The Work Breakdown Structure (WBS) is the basis for communicating:A. Project scope, cost control, schedule, qualityB. Project objectives, dependencies, plan, cost controlC. Project scope, schedule, staffing, cost controlD. Project scope, quality, schedule, dependenciesE. Project budget, schedule, risk factors, work assignments
考题
● The Work Breakdown Structure (WBS) is the basis for communicating:A Project scope, cost control, schedule, qualityB Project objectives, dependencies, plan, cost controlC Project scope, schedule, staffing, cost controlD Project scope, quality, schedule, dependenciesE Project budget, schedule, risk factors, work assignments.
考题
● The Estimate Activity Resource process is closely coordinated with the (73)process.(73)A. Estimate CostsB. Sequence ActivitiesC. Plan CommunicationsD. Conduct Procurements
考题
The Estimate Activity Resource process is closely coordinated with the (73)process.(73)A. Estimate CostsB. Sequence ActivitiesC. Plan CommunicationsD. Conduct Procurements
考题
The cost performance index(CPI) is the ratio of earned value to ( ) and can be used to estimate the projected cost of completing the project. A. cost variance
B.planneD.cost
C.PlanneD.value
D.actual cost
考题
He's spent years cultivating a knowledge of art.A:denying
B:using
C:sharing
D:developing