The customer asks your project to be completed 6 months earlier than planned.You think this target can be reached by-overlapping project activities. This approach is known as ().
A.balance engineering
B.fast-tracking
C.leveling
D.crashing
参考答案
更多 “ The customer asks your project to be completed 6 months earlier than planned.You think this target can be reached by-overlapping project activities. This approach is known as ().A.balance engineeringB.fast-trackingC.levelingD.crashing ” 相关考题
考题
66 A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:A. Change the scope baselineB. Prepare a variance reportC. Call a meeting of the configuration control boardD. Change the project's objectivesE. Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
考题
● A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:A Change the scope baselineB Prepare a variance reportC Call a meeting of the configuration control boardD Change the project's objectivesE Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
考题
BPeople usually think that boys are stronger,heavier and taller than girls. Maybe it's true.Some people even think that boys are smarter than girls.Expert's view:l can' t agree with them. If you say that girls learn faster than boys,you may be right,at least when it comes to young chimps(猩猩) using tools.People found that girl chimps in Tanzania,East Africa,use sticks to find tasty insects(昆虫) two years earlier than boy chimps. This is because young girl chimps watch their moms col-lect bugs,while the boy chimps climb trees.But young boy chimps may hunt and throw(扔) sooner than girl clumps.It's also true for humans.It-s easier for girls to learn to write and draw earlier,but boys often run and throw balls earlier than girls.Teacher's view:l think boys and girls both have their special advantages. Boys are good at sports. They are very athletic. But girls do well in performance. They are very calm.( )26. People usually think boys are _________'than girls.A. tallerB. strongerC. heavierD. All of the above
考题
A project manager believes that modifying the scope of the project may provide added value service for the customer.The project manager should______.A.assign change tasks to project membersB.call a meeting of the configuration control boardC.change the scope baselineD.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
考题
The earned value technique is a commonly used method of performance measurement.It integrates project scope,schedule,and cost measures to help the project management team assess project performance.If a project’s Cost Performance Index(CPI=EV/AC)value less than 1.0,it means that( )。 A.the cost savings for work completed B.the project is ahead of its planned schedule C.the cost overrun for work completed D.1ess work was completed than was planned
考题
It seems that the new project in Nanjing will be even() than your current project.
A、goodB、bestC、better
考题
We () the project on time without your kind assistance.
A、hadn t had completedB、didn t have completedC、couldn t have completedD、cannot have completed
考题
● The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that __(74)__.(74)A.the project is ahead of its planned scheduleB.less work was completed than was plannedC.the cost overrun for work completedD.the cost under-run of performance to date
考题
The earned value technique is a commonlyused method of performance measurement. It integrates project scope, cost, andschedule measures to help the project management team assess projectperformance.If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, itmeans that (74).A.the project is ahead of its planned scheduleB.less work was completed than was plannedC.the cost overrun for work completedD.the cost under-run of performance to date
考题
● Your company CEO just sent you an E-mail asking you to make a presentation on your project, which has been in progress for 10 months, to all identified internal and external stakeholders. He scheduled the presentation for next Monday. You expect more than 50 people to attend. The first step in preparing the presentation is to__(71)__.(71)A.define the audienceB.determine the objectiveC.decide on the general form. of the presentationD.plan a presentation strategy
考题
Your company CEO just sent you an E-mail asking youto make a … on your project , which has been in progress for 10 months , to all Identified internal and external stakeholders. He scheduled the presentation for next Monday.You expect more than 50 people to attend.The first step in preparing the presentation is to ( ).A.define the audienceB.determine the objectiveC.decide on the general form of the presentationD.plan a presentation strategy
考题
What does a CPI of 80% mean? ( ) .A.As of now we expect the total pr gject cost of 80% more than plannedB.When the project is completed, we will have spent 80% moreC.Your project is only progressing at 80% of that plannedD.Your project is only getting 80 cents out of every RMB invested
考题
______ of the following statements is INCORRECT regarding a fire and boat drill on board your cargo vessel.A.At least one fire and boat drill shall be held within 24 hours of leaving a port where more than 25 percent of the crew has been replacedB.The Master is responsible in seeing that each lifeboat is lowered to the water at least once in each 6 months.C.Lifeboat equipment shall be examined at least once each month to insure that it is completeD.An entry shall be made in the vessel's Official Logbook relative to each fire and boat drill
考题
A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should ( ) A.assign change tasks to project members
B.call a meeting of the configuration control board
C.change the scope baseline
D. postpone the modification until a separate enhancement project is fundedafter this project is completed according to the original baseline
考题
The customer asks your project to be completed 6 months earlier than planned.You think this target can be reached by over- lapping project activities.This approach is known as( ).A.balance engineering
B.fast-tracking
C.leveling
D.crashing
考题
Questions 67~68 refer to the following memo.
Bayside View Hotel
To: ALL Employees
From: Edgar Wagner, Hotel Manager
Re: Bayside View Hotel Customer Satisfaction Survey
July 20
Dear Employees,
As part of our ongoing effort to ensure that the Bayside View Hotel remains one of the premier hotels in the country, we have conducted our annual customer satisfaction survey.
The survey results showed customer satisfaction improved in two of four key service areas compared with the results from a survey done twelve months earlier. The areas showing improvement are Housekeeping and Food Services. Customer rating for Concierge Services remained the same, while a noticeable drop was shown for Front Desk Services.
Your department managers will provide you with more detailed results of the survey that pertain to your specific area of work, and will suggest ways to improve on services rated less than satisfactory.
What is indicated about the survey?
A. It was completed by hotel staff.
B. It will be used to decide promotions.
C. It was recently revised.
D. It is conducted every year.
考题
Questions 67~68 refer to the following memo.
Bayside View Hotel
To: ALL Employees
From: Edgar Wagner, Hotel Manager
Re: Bayside View Hotel Customer Satisfaction Survey
July 20
Dear Employees,
As part of our ongoing effort to ensure that the Bayside View Hotel remains one of the premier hotels in the country, we have conducted our annual customer satisfaction survey.
The survey results showed customer satisfaction improved in two of four key service areas compared with the results from a survey done twelve months earlier. The areas showing improvement are Housekeeping and Food Services. Customer rating for Concierge Services remained the same, while a noticeable drop was shown for Front Desk Services.
Your department managers will provide you with more detailed results of the survey that pertain to your specific area of work, and will suggest ways to improve on services rated less than satisfactory.
What department will probably have to make the most improvements in customer service?
A. Housekeeping
B. Concierge Services
C. Food Services
D. Front Desk Services
考题
What does A.CPI of 80%mean?( ).A.As of now we expect the total project cost of 80%more than planned
B.When the project is completed,we will have spent 80%more
C.Your project is only progressing at 80%of that planned
D.Your project is only getting 80 cents out of every RMB invested
考题
A project is a[temporary](请作答此空)of unique,complex,and connected activities having one goal or purpose and that must be completed by a specific time,within budget,and according to( ).Project management is the process of scoping,planning,staffing,organizing,directing,and controlling the development of a(n)( )system at a minimum cost within a specified time frame.For any systems development project,effective project management is necessary to ensure that the project meets the( ),is developed within an acceptable budget,and fulfills customer expectations and specifications,Project management is a process that starts at the beginning of a project,extends through a project,and doesn't culminate until the project is completed.The prerequisite for good project management is a well-defined system development process.Process management is an ongoing activity that documents,manages the use of,and improves an organization s chosen methodology(the“process”)for system development,Process management is concerned with the activities,deliverables,and quality standards to be applied to( )project(s).A.task
B.work
C.sequence
D.activity
考题
Creating a clear map of where the project is going is an important first step.It lets you identify risks,clarify objectives,and determine if the project even makes sense.The only thing more important than the release plan is not to take it too seriously.Release planning is creating a game plan for your Web project( )what you think you want your Web site to be.The plan is a guide for the content,design elements,and functionality of a Web site to be released to the public,to partners,or internally.It also( )how long the project will take and how much it will cost.What the plan is not is a functional( )that defines the project in detail or that produces a budget you can take to the bank.Basically you use a release Plan to do an initial sanity check of the project's( )and worthiness.Release Plans are useful road maps,but don't think of them as guides to the interstate road system.Instead,think of them as the(请作答此空)used by early explorers-half rumor and guess and half hope and expectation.It's always a good idea to have a map of where a project is headed.A.navigators
B.maps
C.guidance
D.goals
考题
A project is a[temporary]( )of unique,complex,and connected activities having one goal or purpose and that must be completed by a specific time,within budget,and according to( ).Project management is the process of scoping,planning,staffing,organizing,directing,and controlling the development of a(n)(请作答此空)system at a minimum cost within a specified time frame.For any systems development project,effective project management is necessary to ensure that the project meets the( ),is developed within an acceptable budget,and fulfills customer expectations and specifications,Project management is a process that starts at the beginning of a project,extends through a project,and doesn't culminate until the project is completed.The prerequisite for good project management is a well-defined system development process.Process management is an ongoing activity that documents,manages the use of,and improves an organization s chosen methodology(the“process”)for system development,Process management is concerned with the activities,deliverables,and quality standards to be applied to( )project(s).A.perfect
B.acceptable
C.controlled
D.completed
考题
Your company CEO just sent you an E-mail asking you to make a …on your project,which has been in progress for 10 months,to allIdentified internal and external stakeholders. He scheduled the presentation for next Monday.You expect more than 50 people to attenD.The first step in preparing the presentation is to ( ) . A.define the audience
B.determine the objective
C.decide on the general form of the presentation
D.plan A.presentation strategy
考题
A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should ( ) . A.assign change tasks to project members
B.call A.meeting of the configuration control board
C.change the scope baseline
D.postpone the modification until A.separate enhancement project is fundeD.after this project is completeD.according to the original baseline
考题
单选题Putting your mobile phone on a restaurant table may make your friends think _____.A
you prefer to talk to your friends at the tableB
you value your calls more than your friendsC
you are enjoying the company of your friendsD
you are polite and considerate of your friends
考题
单选题Your company CEO just sent you an E-mail asking you to make a … on your project , which has been in progress for 10 months , to all Identified internal and external stakeholders. He scheduled the presentation for next Monday.You expect more than 50 people to attend. The first step in preparing the presentation is to ( ).A
define the audienceB
determine the objectiveC
decide on the general form of the presentationD
plan a presentation strategy
考题
单选题After months of negotiations and several proposals, the customer indicates that they may be ready to purchase a pSeries system. Rather than quickly ordering the last configuration proposed, what is the most appropriate next step for a pSeries technical specialist to improve the chance of a successful project?()A
Obtain buy-in and feedback from the customer.B
First ask the client executive if financing has been arranged.C
Plan the installation and rollout schedule before ordering.D
Confirm that any additional requirements are handled by others.