SWOT analysis is a kind of risk identification method. If the project team chose the SO strategy, they should()

A.make full use of the advantage and catch the opportunity
B.overcome the weakness and catch the opportunity
C.make full use of the advantage and reduce the threat
D.overcome the weakness and reduce the threat

参考答案

参考解析
解析:SWOT分析是一种风险识别的方法,如果项目团队选择SO战略(优势、机会),他们应该(75)。A.充分利用优势并抓住机会B.克服弱点并抓住机会C.充分利用优势并减少威胁D.克服弱点并减少威胁
更多 “SWOT analysis is a kind of risk identification method. If the project team chose the SO strategy, they should()A.make full use of the advantage and catch the opportunity B.overcome the weakness and catch the opportunity C.make full use of the advantage and reduce the threat D.overcome the weakness and reduce the threat ” 相关考题
考题 A project manager trying to communicate accurately to the team should use:A the language of the team membersB the language of the project managerC non-verbal methodsD written memosE All of the above.

考题 Risk mitigation includes all but which of the following:A Developing system (policies, procedures, responsibilities)B Obtaining insurance against lossC performing contingent planningD developing planning alternativesE identification of project risks.

考题 Sensitivity analysis can be used in risk analysis to:A Substitute for uncertainty analysis in risk quantificationB estimate the level of risk aversion adopted by managementC estimate the effect of change of one project variable on the overall projectD A and BE All of the above.

考题 Total Project Risk:A should not be calculated for small projectsB is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the project.C Is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.D A and BE A and C

考题 Risk management allows the project manager and the project team to:A eliminate most risks during the planning phase of the projectB identify project risksC identify impacts of various risksD plan suitable responsesE B, C and D only

考题 84 Risk management allows the project manager and the project team to:A. eliminate most risks during the planning phase of the projectB. identify project risksC. identify impacts of various risksD. plan suitable responsesE. B, C and D only

考题 193 A project manager trying to communicate accurately to the team should use:A. the language of the team membersB. the language of the project managerC. non-verbal methodsD. written memosE. All of the above.

考题 122 Total Project Risk:A. should not be calculated for small projectsB. is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the project.C. Is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.D. A and BE. A and C

考题 157 Sensitivity analysis can be used in risk analysis to:A. Substitute for uncertainty analysis in risk quantificationB. estimate the level of risk aversion adopted by managementC. estimate the effect of change of one project variable on the overall projectD. A and BE. All of the above

考题 75 A project manager trying to communicate accurately to the team should use:A. the language of the team membersB. the language of the project managerC. non-verbal methodsD. written memosE. All of the above

考题 ● Risk management allows the project manager and the project team not to(71).(71)A.eliminate most risks during the planning phase of the projectB.identify project risksC.identify impacts of various risksD.plan suitable responses

考题 Risk management allows the project manager and the project team not to(71). A.eliminate most risks during the planning phase of the project B.identify project risks C.identify impacts of various risks D.plan suitable responses

考题 SWOT analysis is a kind of risk identification method.If the project team chose me WT strategy, they should( ). A.overcome the weakness and reduce the threat B.make full use of the advantage and reduce the threat C.overcome the weakness and catch the opportunity D.make full use of the advantage and catch the opportunity

考题 The( )process ascertains which risks have the potential of affecting the project and documenting the risks’characteristics. A.Risk Identification B.Quantitative Risk Analysis C.Qualitative Risk Analysis D.Risk Monitoring and Control

考题 The()process analyzes the effect of risk events and assigns a numerical rating to those risks.()A.Risk Identification B.Quantitative Risk AnalysisC.Qualitative Risk Analysis D.Risk Monitoring and Control

考题 ● SWOT analysis is a kind of risk identification method. If the project team chose the SO strategy, they should __(75)__.(75)A.make full use of the advantage and catch the opportunityB.overcome the weakness and catch the opportunityC.make full use of the advantage and reduce the threatD.overcome the weakness and reduce the threat

考题 Setting redundant components in subsystem to handle with the risks brought by the defaults of original components, what kind of risk response strategy is this ? ( 75 ).A.Risk avoidanceB.Risk acceptanceC.Risk mitigationD.Contingency plan

考题 setting redundant components in subsystem to handle with the risks brought by the defaultsof original components,what kind of risk response strategy is this?()A.risk avoidanceB.risk acceptanceC.risk mitigationD.contingency plan

考题 Risk management allows the project manager and the project team not to (71).A.eliminate most risks during the planning phase of the projectB.identify project risksC.identify impacts of various risksD.plan suitable responses

考题 试题(71)~(75)The analysis phase answers the questions of who will use the system, what the system will do, and where and when it will be used. During this phase, the project team investigates ny current system,identifies (71) , and develops a concept for the new system. This phase as three steps: first, (72) is developed to guide the project team's efforts. It usually ncludes an analysis of the current system and its problems, and the ways to design a new ystem. The next step is (73) The analysis ofthis information - in conjunction withinput rom the project sponsor and many other people - leads to the development of a concept for a ew system. The system concept is then used as a basis to develop a set ofbusiness analysis odels that describes how the business will operate if the new system were developed. The set of models typically includes models that represent the (74) necessary to support the nderlying business process. Last, the analyses, system concepts, and models are combined nto a document called the (75), which is presented to the project sponsor and other key ecision makers that decide whether the project should continue to move forward.(71) A. improvementopportunitiesB. logicalmodelC. systemrequirementsD. systemarchitecture(72) A. a user manualB. an analysis strategyC. an analysis use caseD. a design user case(73) A. project scope definitionB. prob,lems analysisC. decisionanalysisD. requirementsgathering(74) A. dataandprocessesB. systeminfrastructuresC. externalagentsD. systemsoftware(75) A. requirementsstatementB. designspecificationC. systemproposalD. project charter

考题 setting redundant components in subsystem to handle with the risks brought by the defaults of original components,what kind of risk response strategy is this? ( ) . A.risk avoidance B.risk acceptance C.risk mitigation D.contingency plan

考题 Many useful tools and techniques are used in developing schedule. ( ) is a schedule network analysis technique that modifies the project schedule to account for limited resource.A.PERT B.Resource levelling C.Schedule compression D.Critical chain methoD.

考题 The ( ) process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics. A.Risk Identification B.Quantitative Risk Analysis C.Qualitative Risk Analysis D.Risk Monitoring anD.Control

考题 ( ) Assesses the priority of identified risks using their probability of occurring,the corresponding impact on project objectives if the risks do occur,as well as other factors such as the time frame and risk tolerance of the project constraints of cost,schedule,scope,and quality. A.Quantitative Risk Analysis B.Qualitative Risk Analysis C.Enterprise Environmental Factors D.Risk Management Plan

考题 setting redundant components in subsystem to handle with the risks brought by the defaults of original components,what kind of risk response strategy is this?()A、risk avoidanceB、risk acceptanceC、risk mitigationD、contingency plan

考题 Team member listing, scheduled tasks, and risk identification are part of the:()A、project plan.B、project charter.C、communication plan.D、WBS (Work Breakdown Structure).

考题 单选题Team member listing, scheduled tasks, and risk identification are part of the:()A project plan.B project charter.C communication plan.D WBS (Work Breakdown Structure).