The most frequently used construct in Precedent Diagramming Method is:A.Start to Start.B.Finish to Finish.C.Start to Finish.D.Finish to Start.E.Dummy activity.
考题
The logical relationship that communicates a delay between the start/finish of one activity and the start/finish of another activity is referred to as:A.SlackB.Free float.C.Restricted float.D.Level float.E.Lag
考题
An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?A.Total float for the activity is 9 days.B.The early finish date ofthe activity is the end ofthe day on the 14th.C.The late finish date is the 25th.D.The activity can be completed in 2 days ifthe resources devoted to it are doubled.
考题
PDM includes four types of dependencies or precedence relationships:().The completion ofthe successor activity depends upon the initiation of the predecessor activity.
A.Finish-to-StartB.Finish-to-FinishC.Start-to-StartD.Start-to-Finish
考题
PDM includes four types of dependencies or precedence relationships: (). The completion of the successor activity depends upon the initiation of the predecessor activity.
A.Finish-to-StartB.Finish-to-FinishC.Start-to-StartD.Start-to-Finish
考题
● The most frequently used construct in Precedent Diagramming Method is:A Start to Start.B Finish to Finish.C Start to Finish.D Finish to Start.E Dummy activity.
考题
PDM includes four types of dependencies or precedence relationships.( ),the initiation of the successor activity,depends upon the initiation ofthe predecessor activity. A.Start-to-Start B.Finish-to-Finish C.Start-to-Finish D.Finish-to—Start
考题
导致一个Activity的onDestroy()方法被调用的原因是什么?()
A.该Activity被暂停或者停止,并且它的资源被操作系统回收B.启动该Activity的Activity调用了finishActivity()C.活动(Activity)调用finish()D.三项原因都是
考题
● Precedence Diagramming Method (PDM) is a method used in activity sequencing. There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called __(75)__.(75)A.Finish-to-StartB.Finish-to-FinishC.Start-to-StartD.Start-to-Finish
考题
Precedence Diagramming Method(PDM) is a method used in activity sequencing. There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called ( ). A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish
考题
导致一个Activity的onDestroy()方法被调用的原因是什么?()A、该Activity被暂停或者停止,并且它的资源被操作系统回收B、启动该Activity的Activity调用了finishActivity()C、活动Activity调用finish()D、A、B、C选项都是
考题
PDM includes four types of dependencies or precedence relationships: (). The completion of the successor activity depends upon the initiation of the predecessor activity.A、Finish-to-StartB、Finish-to-FinishC、Start-to-StartD、Start-to-Finish
考题
当第二个Activity退出的时候需要返回一些信息给第一个Activity。那么在第一个Activity中接受返回数据的()。A、on Option sItem()B、on Option sItem Selected()C、on Activity Result()D、Option sItem Selected()
考题
PDM includes four types of dependencies or precedence relationships:().The completion ofthe successor activity depends upon the initiation of the predecessor activity.A、Finish-to-StartB、Finish-to-FinishC、Start-to-StartD、Start-to-Finish
考题
单选题导致一个Activity的onDestroy()方法被调用的原因是什么?()A
该Activity被暂停或者停止,并且它的资源被操作系统回收B
启动该Activity的Activity调用了finishActivity()C
活动Activity调用finish()D
A、B、C选项都是
考题
单选题当第二个Activity退出的时候需要返回一些信息给第一个Activity。那么在第一个Activity中接受返回数据的()。A
on Option sItem()B
on Option sItem Selected()C
on Activity Result()D
Option sItem Selected()
考题
单选题An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?A
Total float for the activity is 9 days.B
The early finish date ofthe activity is the end ofthe day on the 14th.C
The late finish date is the 25th.D
The activity can be completed in 2 days ifthe resources devoted to it are doubled.