Precedence Diagramming Method(PDM) is a method used in activity sequencing. There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called ( ).

A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish

参考答案

参考解析
解析:前导图法是用于活动排序的技术。前导图法包括四种活动依赖关系。先行活动结束后续活动才能开展的关系是结束—开始关系。
更多 “Precedence Diagramming Method(PDM) is a method used in activity sequencing. There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called ( ). A.Finish-to-Start B.Finish-to-Finish C.Start-to-Start D.Start-to-Finish ” 相关考题
考题 The most frequently used construct in Precedent Diagramming Method is:A.Start to Start.B.Finish to Finish.C.Start to Finish.D.Finish to Start.E.Dummy activity.

考题 ADM is an activity-on-arrow method. In this method, a dummy activity:A.Denotes a critical path relationship.B.Denotes any dependency relationship.C.Shows slack.D.Identifies customer deliverables dates.E.Identifies customer team meeting dates.

考题 On a precedence diagram, the arrow between two boxes is called:A.An activity.B.A constraint.C.An event.D.The critical path.E.None of above.

考题 PDM includes four types of dependencies or precedence relationships:().The completion ofthe successor activity depends upon the initiation of the predecessor activity. A.Finish-to-StartB.Finish-to-FinishC.Start-to-StartD.Start-to-Finish

考题 PDM includes four types of dependencies or precedence relationships: (). The completion of the successor activity depends upon the initiation of the predecessor activity. A.Finish-to-StartB.Finish-to-FinishC.Start-to-StartD.Start-to-Finish

考题 ● The most frequently used construct in Precedent Diagramming Method is:A Start to Start.B Finish to Finish.C Start to Finish.D Finish to Start.E Dummy activity.

考题 ● ADM is an activity-on-arrow method. In this method, a dummy activity:A Denotes a critical path relationship.B Denotes any dependency relationship.C Shows slack.D Identifies customer deliverables dates.E Identifies customer team meeting dates.

考题 ● (73) is one of the techniques used for estimating activity durations.(73)A.Analogous EstimatingB.Precedence Diagramming Method (PDM)C.Dependency DeterminationD.Schedule network Templates

考题 ______is one of the techniques used for estimating activity durations.A.Analogous EstimatingB.Precedence Diagramming Method(PDM)C.Dependency DeterminationD.Schedule network Templates

考题 ● (73) is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the logical relationships that exist betweenthem.(73)A.PERTB.AOAC.WBSD.PDM

考题 PDM includes four types of dependencies or precedence relation ships:(73)The completion of the successor activity depends upon the initiation of the predecessor activity.A.Finish-to-StartB.Finish-to-FinishC.Start-to-StartD.Start-to-Finish

考题 is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies or precedence relationships:(67), the initiation of the successor activity, depends upon the completion of the predecessor activity.(68), the initiation of the successor activity, depends upon the initiation of the predecessor activity.A.PDMB.CPMC.PERTD.AOA

考题 PDM includes four types of dependencies or precedence relationships.( ),the initiation of the successor activity,depends upon the initiation ofthe predecessor activity. A.Start-to-Start B.Finish-to-Finish C.Start-to-Finish D.Finish-to—Start

考题 is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activites and connects them with arrows that arrow the dependencies.This method includes following types of dependcies orprecedence relationships: (2)the initiation of the successor activity, depends upon the completion of the predecessor activity. (3)the initiation of the successor activity, depends upon the initiation of the predecessor activity.A.PDMB.CPMC.PERTD.AOA

考题 PDM includes four types of dependencies or precedence relationships…(73),the initiation of the successor activity,depends upon the initiation of the predecessor activity.A.Finish-to-StartB.Finish-to-FinishC.Start-to-StartD.Start-to-Finish

考题 is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the logical relationships that exist between them.A.PERTB.AOAC.WBSD.PDM

考题 () is one of the tools and techniques.A.DecompositionB.Fishbone DiagramC.Precedence Diagramming Method of Sequence ActivitiesD.Expert Judgment

考题 ● Precedence Diagramming Method (PDM) is a method used in activity sequencing. There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called __(75)__.(75)A.Finish-to-StartB.Finish-to-FinishC.Start-to-StartD.Start-to-Finish

考题 In a project plan,when the project manager scheouies activities,he(or sha)often uses( )method,precedence relationships between acticities are represented by cireles connected by one or more arrows.The length of the arrow represents the duration of the relevant activity.A.causality diagram B.Gantt?chart C.histogram D.arrow djgram

考题 PDM is a method of constructing a project schedule network diagram that uses boxesor rectangles, referred to as nodes, to represent activities and connects them with arrows thatshow the dependencies.This method includes following types of dependencies or precedence relationships:F-S, the initiation of the successor activity, depends upon the completion of thepredecessor activity.() , the initiation of the successor activity, depends upon the initiation of thepredecessor activity. A.F-S B.F-F C.S-F D.S-S

考题 ( )is one of the tools and techniques. A.Decomposition B.Fish bone Diagram C.Precedence Diagramming MethoD.of Sequence Activities D.Expert Judgment

考题 (1) is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies or precedence relationships: (2) the initiation of the successor activity, depends upon the completion ofthe predecessor activity.(3) the initiation ofthe successor activity, depends upon the initiation ofthe predecessor activity. 空白(3)处填()A、F-SB、F-FC、S-FD、S-S

考题 PDM includes four types of dependencies or precedence relationships: (). The completion of the successor activity depends upon the initiation of the predecessor activity.A、Finish-to-StartB、Finish-to-FinishC、Start-to-StartD、Start-to-Finish

考题 PDM includes four types of dependencies or precedence relationships:().The completion ofthe successor activity depends upon the initiation of the predecessor activity.A、Finish-to-StartB、Finish-to-FinishC、Start-to-StartD、Start-to-Finish

考题 (1) is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies or precedence relationships: (2) the initiation of the successor activity, depends upon the completion ofthe predecessor activity.(3) the initiation ofthe successor activity, depends upon the initiation ofthe predecessor activity. 空白(1)处填()A、PDMB、CPMC、PERTD、AOA

考题 单选题PDM includes four types of dependencies or precedence relationships: (). The completion of the successor activity depends upon the initiation of the predecessor activity.A Finish-to-StartB Finish-to-FinishC Start-to-StartD Start-to-Finish

考题 单选题(1) is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies or precedence relationships: (2) the initiation of the successor activity, depends upon the completion ofthe predecessor activity.(3) the initiation ofthe successor activity, depends upon the initiation ofthe predecessor activity. 空白(3)处填()A F-SB F-FC S-FD S-S