A customer has reached the cooling limit in his datacenter, but still has room for additional IBM racks and servers. Which allow additinal future sales of the following?()
A
Rear Door HeateXchanger
B
ActiveEnery Manager(AEM)
C
Perforated doors
D
IBM Cool Blue
参考答案
参考解析
解析:
暂无解析
更多 “单选题A customer has reached the cooling limit in his datacenter, but still has room for additional IBM racks and servers. Which allow additinal future sales of the following?()A Rear Door HeateXchangerB ActiveEnery Manager(AEM)C Perforated doorsD IBM Cool Blue” 相关考题
考题
Which of the following Cool Blue technologies will help energy consumption budgeting of System x servers based upon current actual consumption? ()A、IBM Standalone Solutions Configuration Tool (SSCT)B、IBM Active Energy ManagerC、Rear Door Heat eXchangerD、IBM Power Configurator
考题
It takes a comprehensive strategy to grow data center capabilities while containing power and cooling costs. Which IBM thermal environment solution can best support this strategy with no effect on performance? ()A、IBM Rear Door Heat eXchangerB、IBM Active Energy ManagerC、IBM Calibrated Vector CoolingD、All of the above
考题
A new IBM x 3650 M3 customer has experienced support issues with problem resolution from their previous vendor. The biggest problem was with Microsoft applications failing intermittently. Which of the following IBM products covers this issue?()A、IBM Hardware Standard WarrantyB、TechlineC、Tivoli Problem Resolution Manager(TPRM)D、RTS
考题
A customer is interested in a power efficient server solution. The Sales Specialist has recommended a BladeCenter solution. The customer debates the price is high compared to rack servers. Which of the following should the Sales Specialist emphasize to address the pricing difference?()A、Higher rack density that reduces data center footprintsB、Internal upgrades that only IBM can offerC、Total Cost of Ownership (TCO) related to innovative components such as Integrated Switches D、The Rear Door Heat eXchanger that only IBM can offer
考题
A customer has been working with your company to purchase an iDataPlex cluster. They have a configuration from IBM and are getting ready to place an order. Which should be done of the following?()A、A solution sizing questionnaireB、Verify the customer has the proper racksC、A Technical Delivery AssessmentD、Verify the customer has enough cooling in the computer room
考题
You are speaking to an IT manager with 350 small servers. The IT manager is looking to reduce and consolidate systems. What strategy would you follow?()A、Tell the customer that IBM has the best scale-out server strategy.B、Show the benefit of server consolidation with IBM and the return on investment.C、Find out the mixture of server processor and application type.D、Tell the customer to buy smaller servers.
考题
A customer has a large HP Intel infrastructure and is actively managing these servers with Insight Manager. They recently purchased an IBM x346 server for a remote office database project. They do not want to run additional systems management software but require to be notified of PFA and hardware alerting on critical hardware components. Which of the following solutions would accomplish this?()A、Install an RSA II Slimline card on the IBM server and configure to send email alertsB、Enable the IBM management option in Insight ManagerC、Install and configure a Director agent on the IBM serverD、Configure the systems management processor on the IBM server
考题
An insurance customer installs two BladeCenter chassis in a rack with glass doors. After a short time, the blowers in both BladeCenters increase to full speed, and then one fails. Apart from replacing the broken blower, which additional action is required for a long term fix of the following?()A、Add Rear Door HeateXchangerB、Add fans to the top of the racksC、Increase circulation from Data Center raised floorD、Change to perforated doors
考题
When comparing capacity-to-capacity, the IBM Rear Door Heat eXchanger helps provide more advantages than other available thermal environment solutions, usually at a fraction of the cost. Which of the following statements is NOT an advantage of the IBM Rear Door Heat eXchanger? ()A、The IBM Rear Door Heat eXchanger may dramatically unburden existing AC units by cooling the air before it exhausts from the electronics into the hot aisle.B、The IBM Rear Door Heat eXchanger is a "hang, plug, and run" design so the units may be added quickly.C、The IBM Rear Door Heat eXchanger is equipped with two fans to help maintain water temperature at 18C (64.4F) and provide even air flow.D、The IBM Rear Door Heat eXchanger is designed to support a 42U rack.
考题
A customer is installing a new x3850 X5 server and has purchased a warranty upgrade on the server to 24 x 7 four hour response. The customer requested IBM help with setting up the RAID adapter. The customer was told IBM would not help them. Which of the following should be verified first?()A、The customer used their IBM Customer NumberB、The customer has activated their base warrantyC、The customer purchased Remote Technical Support ServicepacD、The customer escalated the issue to the Duty Manager
考题
Select 3 features of IBM’s CoolBlue Energy Management Innovation:()A、IBM Active Energy Manager, Calibrated Vectored Cooling, and Water Chilled Door eXchanger B、IBM Active Energy Manager, Front Door Heat eXchanger, and Calibrated Vectored CoolingC、Power Configurator, Calibrated Vectored Cooling, and Rear Door Heat eXchangerD、Thermal Diagnostics, Front Door Heat eXchanger, and Rear Door Heat eXchanger
考题
A customer plans to implement a network of x3690 X5 servers. The customer has very limited funds. Which of the following tools would allow installation of firmware updates?()A、ToolsCenterB、VMware vSphere 4C、Tivoli Provisioning Manager (TPM)D、Tivoli Storage Manager (TSM)
考题
An installed customer has developed human resource constraints in the IT department. Which of the following allows the sales professional to proceed with future sales?()A、Proof of conceptB、Volume sales discountsC、ServicePacsD、Industry leading technology
考题
A customer is running a number of non-IBM servers purchased two years ago and has settled on one of the new IBM xSeries servers as a migration path. From the following options, which is the preferred migration path?()A、Copy the image of the non-IBM servers and copy that image to the IBM servers, then reboot the IBM servers.B、Copy the image from the non-IBM servers with RDM and install them with IBM Director to the new IBM servers. Reboot the IBM servers.C、Install a fresh operating system using ServerGuide, and then install the applications and copy the data from the old servers.D、Install a fresh operating system on the IBM servers and then run ServerGuide on the IBM servers to migrate the applications and data to the IBM servers.
考题
A customer has reached the cooling limit in his datacenter, but still has room for additional IBM racks and servers. Which allow additinal future sales of the following?()A、Rear Door HeateXchangerB、ActiveEnery Manager(AEM)C、Perforated doorsD、IBM Cool Blue
考题
单选题When comparing capacity-to-capacity, the IBM Rear Door Heat eXchanger helps provide more advantages than other available thermal environment solutions, usually at a fraction of the cost. Which of the following statements is NOT an advantage of the IBM Rear Door Heat eXchanger? ()A
The IBM Rear Door Heat eXchanger may dramatically unburden existing AC units by cooling the air before it exhausts from the electronics into the hot aisle.B
The IBM Rear Door Heat eXchanger is a hang, plug, and run design so the units may be added quickly.C
The IBM Rear Door Heat eXchanger is equipped with two fans to help maintain water temperature at 18C (64.4F) and provide even air flow.D
The IBM Rear Door Heat eXchanger is designed to support a 42U rack.
考题
单选题A customer is interested in a power efficient server solution. The Sales Specialist has recommended a BladeCenter solution. The customer debates the price is high compared to rack servers. Which of the following should the Sales Specialist emphasize to address the pricing difference?()A
Higher rack density that reduces data center footprintsB
Internal upgrades that only IBM can offerC
Total Cost of Ownership (TCO) related to innovative components such as Integrated Switches D
The Rear Door Heat eXchanger that only IBM can offer
考题
单选题A customer has Symantec NetBackup installed and is concerned about restore times for a line ofbusiness server. Which IBM Tivoli Storage Manager feature addresses this customer’s concerns?()A
migrationB
collocationC
compressionD
subfile backup
考题
单选题An installed customer has developed human resource constraints in the IT department. Which of the following allows the sales professional to proceed with future sales?()A
Proof of conceptB
Volume sales discountsC
ServicePacsD
Industry leading technology
考题
单选题A customer plans to implement a network of x3690 X5 servers. The customer has very limited funds. Which of the following tools would allow installation of firmware updates?()A
ToolsCenterB
VMware vSphere 4C
Tivoli Provisioning Manager (TPM)D
Tivoli Storage Manager (TSM)
考题
单选题Select 3 features of IBM’s CoolBlue Energy Management Innovation:()A
IBM Active Energy Manager, Calibrated Vectored Cooling, and Water Chilled Door eXchanger B
IBM Active Energy Manager, Front Door Heat eXchanger, and Calibrated Vectored CoolingC
Power Configurator, Calibrated Vectored Cooling, and Rear Door Heat eXchangerD
Thermal Diagnostics, Front Door Heat eXchanger, and Rear Door Heat eXchanger
考题
单选题A new IBM x 3650 M3 customer has experienced support issues with problem resolution from their previous vendor. The biggest problem was with Microsoft applications failing intermittently. Which of the following IBM products covers this issue?()A
IBM Hardware Standard WarrantyB
TechlineC
Tivoli Problem Resolution Manager(TPRM)D
RTS
考题
单选题A customer is installing a new x3850 X5 server and has purchased a warranty upgrade on the server to 24 x 7 four hour response. The customer requested IBM help with setting up the RAID adapter. The customer was told IBM would not help them. Which of the following should be verified first?()A
The customer used their IBM Customer NumberB
The customer has activated their base warrantyC
The customer purchased Remote Technical Support ServicepacD
The customer escalated the issue to the Duty Manager
考题
单选题You are speaking to an IT manager with 350 small servers. The IT manager is looking to reduce and consolidate systems. What strategy would you follow?()A
Tell the customer that IBM has the best scale-out server strategy.B
Show the benefit of server consolidation with IBM and the return on investment.C
Find out the mixture of server processor and application type.D
Tell the customer to buy smaller servers.
考题
单选题A customer has been working with your company to purchase an iDataPlex cluster. They have a configuration from IBM and are getting ready to place an order. Which should be done of the following?()A
A solution sizing questionnaireB
Verify the customer has the proper racksC
A Technical Delivery AssessmentD
Verify the customer has enough cooling in the computer room
考题
单选题A customer has a large HP Intel infrastructure and is actively managing these servers with Insight Manager. They recently purchased an IBM x346 server for a remote office database project. They do not want to run additional systems management software but require to be notified of PFA and hardware alerting on critical hardware components. Which of the following solutions would accomplish this?()A
Install an RSA II Slimline card on the IBM server and configure to send email alertsB
Enable the IBM management option in Insight ManagerC
Install and configure a Director agent on the IBM serverD
Configure the systems management processor on the IBM server
考题
单选题A customer is running a number of non-IBM servers purchased two years ago and has settled on one of the new IBM xSeries servers as a migration path. From the following options, which is the preferred migration path?()A
Copy the image of the non-IBM servers and copy that image to the IBM servers, then reboot the IBM servers.B
Copy the image from the non-IBM servers with RDM and install them with IBM Director to the new IBM servers. Reboot the IBM servers.C
Install a fresh operating system using ServerGuide, and then install the applications and copy the data from the old servers.D
Install a fresh operating system on the IBM servers and then run ServerGuide on the IBM servers to migrate the applications and data to the IBM servers.
热门标签
最新试卷