理想情况下,资源均等(resource leveling)应作用于哪些活动?()
A

负浮动的活动

B

正浮动的活动

C

零浮动的活动

D

在关键路径上的活动


参考答案

参考解析
解析: 暂无解析
更多 “单选题理想情况下,资源均等(resource leveling)应作用于哪些活动?()A 负浮动的活动B 正浮动的活动C 零浮动的活动D 在关键路径上的活动” 相关考题
考题 Resource leveling _____.A.Allocates resources to activities to find shortest schedule within fixed resource limits.B.Smoothes out resource requirements by rescheduling activities within their float time.C.Smooths out resource requirements by substituting activities with unassigned resources.D.Attempts to reduce resource requirements within a constraint on project durationE.B or D

考题 Resource leveling will often affect the project by making it:A.Shorter.B.LongerC.More responsive to customer needs.D.A and CE.B and C.

考题 Planning activities such that predetermined resource availability pools are not exceeded is called:A.Resource leveling.B.Manpower leveling.C.Resource limited planning.D.Manpower planning.E.Manpower contingency planning.

考题 Smoothing out resource requirements from period to period is called resource _____.A.Allocation.B.PartitioningC.Leveling.D.QuantificationE.None of above.

考题 172 Smoothing out resource requirements from period to period is called resource _____.A. Allocation.B. PartitioningC. Leveling.D. QuantificationE. None of above

考题 40 Resource leveling will often affect the project by making it:A. Shorter.B. LongerC. More responsive to customer needs.D. A and CE. B and C

考题 171 Resource leveling _____.A. Allocates resources to activities to find shortest schedule within fixed resource limits.B. Smoothes out resource requirements by rescheduling activities within their float time.C. Smooths out resource requirements by substituting activities with unassigned resources.D. Attempts to reduce resource requirements within a constraint on project durationE. B or D

考题 116 Planning activities such that predetermined resource availability pools are not exceeded is called: A. Resource leveling.B. Manpower leveling.C. Resource limited planning.D. Manpower planning.E. Manpower contingency planning.

考题 ● Resource leveling _____.A Allocates resources to activities to find shortest schedule within fixed resource limits.B Smoothes out resource requirements by rescheduling activities within their float time.C Smooths out resource requirements by substituting activities with unassigned resources.D Attempts to reduce resource requirements within a constraint on project durationE B or D

考题 ● Resource leveling will often affect the project by making it:A Shorter.B LongerC More responsive to customer needs.D A and CE B and C.

考题 物理层定义了『____』资源块和物理资源块。(Physical layer defines『____』resource block and the physical resource block .)

考题 资源粒子组用于定义『____』到资源粒子的映射。(The resource particle group is used to define the mapping for『____』to resource particle.)

考题 调度请求用于请求新传输的『____』资源。(Scheduling request is used to request 『____』resource for new transmission.)

考题 经济资源(Economic resource)

考题 Resource allocation资源配置

考题 TD-LTE最小的时频资源单位是()。 A.Resource ELementB.Resource Element groupC.Control Channel ElementD.Resource Block

考题 以下哪些触发器不是用于触发策略的() A.1PCANSessionEstablishB.Resource-limitationC.GSNChangeD.Gw-or-pcef-malfunction

考题 Schedule compression shortens the project schedule without changing the project scope,to meet schedule constraints,imposed dates,or other schedule objectives.Schedule compression techniques include crashing and( ). A.fast tracking B.what-if scenario analysis C.resource leveling D.critical chain methoD.

考题 Your project is behind schedule due to conflict between team members. Having resolved the conflict,to get the project back on schedule,you should consider ( ) . A.crashing the schedule B.performing resource leveling C.conducting reverse resource allocation scheduling D.utilizing the critical chair resources

考题 资源(resource)

考题 理想情况下,资源均等(resource leveling)应作用于哪些活动?()A、负浮动的活动B、正浮动的活动C、零浮动的活动D、在关键路径上的活动

考题 TD-LTE最小的时频资源单位是()。A、Resource ELementB、Resource Element groupC、Control Channel ElementD、Resource Block

考题 理想情况下,哪些活动可以采用资源平衡技术?()A、负浮动B、零浮动C、正浮动D、在关键路径上

考题 在工期固定的情况下,理想的资源计划应该是()

考题 URL是()的简写,中文译作()。A、Uniform Real Locator,全球定位B、Unin Resource Locator,全球资源定位C、Uniform Real Locator,全球资源定位D、Uniform Resource Locator,全球资源定位(统一资源定位)

考题 单选题理想情况下,哪些活动可以采用资源平衡技术?()A 负浮动B 零浮动C 正浮动D 在关键路径上

考题 单选题URL是()的简写,中文译作()A Uniform Real Locator,全球定位B Enin Resource Locator,全球资源定位C Uniform ReM Locator,全球资源定位D Uniform Resource Locator,全球资源定位