Assigning resources in an attempt to find the shortest project schedule consistent with fixed resource limits is called resource _____.A.Allocation.B.PartitioningC.LevelingD.Quantification.E.None of above.
考题
Smoothing out resource requirements from period to period is called resource _____.A.Allocation.B.PartitioningC.Leveling.D.QuantificationE.None of above.
考题
对于一个正常的移动台主叫流程,下面的信令流程先后次序正确的是()
A.OriginationMessage-CMServiceRequest-Allocation-Establish-AssignmentComplete-TchPreambleB.OriginationMessage-CMServiceRequest-TchPreamble-Establish-AssignmentCompleteAllocationC.OriginationMessage-CMServiceRequest-Establish-Allocation-TchPreamble-AssignmentCompleteD.OriginationMessage-CMServiceRequest-Establish-AssignmentComplete-Allocation-TchPreamble
考题
172 Smoothing out resource requirements from period to period is called resource _____.A. Allocation.B. PartitioningC. Leveling.D. QuantificationE. None of above
考题
178 Assigning resources in an attempt to find the shortest project schedule consistent with fixed resource limits is called resource _____.A. Allocation.B. PartitioningC. LevelingD. Quantification.E. None of above.
考题
54 Smoothing out resource requirements from period to period is called resource _____.A. Allocation.B. PartitioningC. Leveling.D. QuantificationE. None of above
考题
60 Assigning resources in an attempt to find the shortest project schedule consistent with fixed resource limits is called resource _____.A. Allocation.B. PartitioningC. LevelingD. Quantification.E. None of above.
考题
WhichthreewebapplicationdeploymentdescriptorelementsallowwebcomponentstogainreferencestoresourcesorEJBcomponents?()
A.ejb-refB.jdbc-refC.servlet-refD.resource-refE.javamail-refF.resource-env-ref
考题
WhichoftheserepresentthemaincomponentsofDatabaseResourceManager?()
A.ResourceconsumergroupsB.ResourceplansC.Resource-plangroupsD.Resource-plandirectivesE.Alloftheabove
热门标签
最新试卷