It is recommended that the project _____ until all the preparations have been made.
A
not be started
B
will not be started
C
is not started
D
is not to be started
参考答案
参考解析
解析:
句意:建议在所有的准备工作完成之前,这项工程不要开始。It is recommended后面的主语从句用虚拟语气,用“should+动词原形”的形式,should可省略,因此本题选择A项。
句意:建议在所有的准备工作完成之前,这项工程不要开始。It is recommended后面的主语从句用虚拟语气,用“should+动词原形”的形式,should可省略,因此本题选择A项。
更多 “单选题It is recommended that the project _____ until all the preparations have been made.A not be startedB will not be startedC is not startedD is not to be started” 相关考题
考题
Which of the following are included as part of a scope statement?A.Project justificationB.Project deliverablesC.Project objectivesD.All of the aboveE.B and C
考题
The project life-cycle can be described as:A.project concept, project planning, project execution, and project close-out.B.project planning, work authorization, and project reporting.C.project planning, project control, project definition, WBS development, and project termination.D.project concept, project execution, and project reporting.E.All of the above.
考题
A common way by which executives provide the project manager with written authority is through:A . A common job description for all project managersB . An appointment letterC . A project charterD . All of the aboveE . B and C only
考题
The main player in project communication is theA sponsorB project managerC functional managerD functional teamE All of the above.
考题
Total project risk can be defined as:A the sum of the probabilities of project risks events times the sum of consequences of those risksB the sum of the products of each project risk event times its consequencesC the sum of the consequences of all project risk eventsD the sum of the probabilities of all project risk eventsE 1 - the sum of the probabilities of all project risk events.
考题
15 Total project risk can be defined as:A. the sum of the probabilities of project risks events times the sum of consequences of those risksB. the sum of the products of each project risk event times its consequencesC. the sum of the consequences of all project risk eventsD. the sum of the probabilities of all project risk eventsE. 1 - the sum of the probabilities of all project risk events
考题
118 A common way by which executives provide the project manager with written authority is through:A. A common job description for all project managersB. An appointment letterC. A project charterD. All of the aboveE. B and C only
考题
167 The project life-cycle can be described as:A. project concept, project planning, project execution, and project close-out.B. project planning, work authorization, and project reporting.C. project planning, project control, project definition, WBS development, and project termination. D. project concept, project execution, and project reporting.E. All of the above
考题
66 A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:A. Change the scope baselineB. Prepare a variance reportC. Call a meeting of the configuration control boardD. Change the project's objectivesE. Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
考题
142 Ensuring that all work is both authorized and funded by contractual documentation is the responsibility of:A. The project managerB. The functional managerC. The project sponsorD. The clientE. All of the above
考题
18 Interfacing with the customer after project go-ahead is the responsibility of:A. Project sponsorB. Project teamC. Project managerD. Functional managerE. All of the above are possible, based upon the size and complexity of the project
考题
● Which of the following are included as part of a scope statement?A Project justificationB Project deliverablesC Project objectivesD All of the aboveE B and C
考题
● Interfacing with the customer after project go-ahead is the responsibility of:A Project sponsorB Project teamC Project managerD Functional managerE All of the above are possible, based upon the size and complexity of the project
考题
● Ensuring that all work is both authorized and funded by contractual documentation is the responsibility of:A The project managerB The functional managerC The project sponsorD The clientE All of the above
考题
● A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:A Change the scope baselineB Prepare a variance reportC Call a meeting of the configuration control boardD Change the project's objectivesE Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
考题
● A Work Breakdown Structure:A assures all work is identifiedB subdivides the project into manageable segmentsC provides the project sponsor with a time-phase task summaryD both A and BE All of the above.
考题
A project manager believes that modifying the scope of the project may provide added value service for the customer.The project manager should______.A.assign change tasks to project membersB.call a meeting of the configuration control boardC.change the scope baselineD.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
考题
It is recommended that the project _____ until 选择
Itisrecommendedthattheproject_____untilallthepreparationshavebeenmade.(A)isnotstarted(C)notbestarted(B)willnotbestarted(D)isnottobestarted
考题
A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should ( ) A.assign change tasks to project members
B.call a meeting of the configuration control board
C.change the scope baseline
D. postpone the modification until a separate enhancement project is fundedafter this project is completed according to the original baseline
考题
A project is a[temporary]( )of unique,complex,and connected activities having one goal or purpose and that must be completed by a specific time,within budget,and according to( ).Project management is the process of scoping,planning,staffing,organizing,directing,and controlling the development of a(n)( )system at a minimum cost within a specified time frame.For any systems development project,effective project management is necessary to ensure that the project meets the( ),is developed within an acceptable budget,and fulfills customer expectations and specifications,Project management is a process that starts at the beginning of a project,extends through a project,and doesn't culminate until the project is completed.The prerequisite for good project management is a well-defined system development process.Process management is an ongoing activity that documents,manages the use of,and improves an organization s chosen methodology(the“process”)for system development,Process management is concerned with the activities,deliverables,and quality standards to be applied to(请作答此空)project(s).A.a single
B.a particular
C.some
D.all
考题
A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should ( ) . A.assign change tasks to project members
B.call A.meeting of the configuration control board
C.change the scope baseline
D.postpone the modification until A.separate enhancement project is fundeD.after this project is completeD.according to the original baseline
考题
The engineer recommended()Awhenwelookatthisquestion.Bthatvalueshisnewideas.Cthattheprocesscanbemadesimpler.DwhichistheMark2project.
考题
The engineer recommended()A、whenwelookatthisquestion.B、thatvalueshisnewideas.C、thattheprocesscanbemadesimpler.D、whichistheMark2project.
考题
We can't tell you the results until we have looked at()A、all the datumB、the all dataC、all the dataD、the all datum
考题
The intention of the()is to schedule, organize and control all activities to achieve the project goal eventually.no matter how difficult it is and what kind of risks are there.A、project work breakdownB、project security authenticationC、project managementD、project flowchart
考题
单选题The engineer recommended()A
whenwelookatthisquestion.B
thatvalueshisnewideas.C
thattheprocesscanbemadesimpler.D
whichistheMark2project.
考题
单选题It is recommended that the project ______ until all the preparations have been made.A
not be started B
will not be startedC
is not started D
is not to be started
热门标签
最新试卷