网友您好, 请在下方输入框内输入要搜索的题目:

题目内容 (请给出正确答案)
单选题
Prior to implementing an LPAR system, which of the following needs to be done?()
A

A graphics monitor must be attached to the server

B

Cluster System Management (CSM) software must be installed

C

The LPAR system must have an Hardware Management Console (HMC) connected

D

Each LPAR must be configured with a CDROM for operating system installation


参考答案

参考解析
解析: 暂无解析
更多 “单选题Prior to implementing an LPAR system, which of the following needs to be done?()A A graphics monitor must be attached to the serverB Cluster System Management (CSM) software must be installedC The LPAR system must have an Hardware Management Console (HMC) connectedD Each LPAR must be configured with a CDROM for operating system installation” 相关考题
考题 A customer has 4 POWER6 servers managed by a Hardware Management Console (HMC). They plan to install a second HMC for redundancy.  Which of the following statements correctlydescribes the dual HMC environment? ()A、 To provide the Service Agent function, both HMCs must have Service Agent enabled and a dedicated modem and phone line.B、 Authorized users must have the same username and password on both HMCs, so that every user of one HMC is automatically authorized on the other.C、 Both HMCs are automatically notified of any changes that occur in the managed systems, so results of changes made to the managed system by one HMC are visible on theD、 Both HMCs must be running the same software revision. Software maintenance must be performed on both HMCs at the same time, but one HMC should be disconnected from

考题 A system administrator needs to provision storage for a 200GB database. The database must have extremely low seek time. Which of the following is the BEST solution?()A、A JBODB、A RAID 50 arrayC、A NASD、A single SSD

考题 A customer has an entry level Power System that is currently partitioned and managed by a Hardware Management Console (HMC). For operational reasons, it must be disconnected from the HMC and configured as a new development system.  How should the customer proceed to implement PowerVM Express and Integrated Virtualization Manager (IVM) on this Power System? ()A、 Install a VIO server as an additional partition and DLPAR the resources from the existing partition to the VIO server.B、 Create a service partition and install a VIO server. This will automatically move resources to the VIO server on reboot of the managed system.C、 Delete all the existing LPARs, create a new LPAR and assign all the system resources to this LPAR and then install the VIO server on this LPAR.D、 Reset the machine to Manufacturing Default Configuration and install the VIO server on the resulting partition created, which will own all system resources.

考题 Which of the following can deploy system plans generated by the IBM System Planning Tool (SPT)?()A、 The Hardware Management Console (HMC) and Integrated Virtualization Manager (IVM).B、 The Hardware Management Console (HMC) and Advanced System Manager Interface (ASMI).C、 Integrated Virtualization Manager (IVM) and Advanced System Manager Interface (ASMI).D、 Integrated Virtualization Manager (IVM) and BladeCenter Advanced Management Module (AMM).

考题 Prior to implementing an LPAR system, which of the following needs to be done?()A、A graphics monitor must be attached to the serverB、Cluster System Management (CSM) software must be installedC、The LPAR system must have an Hardware Management Console (HMC) connectedD、Each LPAR must be configured with a CDROM for operating system installation

考题 Which of the following statements is true regarding implementing Live Partition Mobility on two existing POWER6 based systems?()A、The systems must use internal storage for boot purposes. B、All virtualized ethernet adapters must be numbered below 10. C、The mobile partition's network and disk access must be virtualized. D、Each system must be controlled by a different Hardware Management Console (HMC). 

考题 An administrator issued a command to update thefirmware of an Ethernet adapter on a partitioned system, but received an error. What is the most likely cause of the problem?()A、The adapter must be taken offline prior to the firmware update.B、The system has not been rebooted since the adapter was added to the LPAR.C、The adapter must be assigned to the service partition prior to updating the firmware.D、The adapter must be dynamically removed from the LPAR prior to updating thefirmware.

考题 Which one of these statements is true regarding hot pluggable PCIe and PCI-X slots in a Power 550?()A、Cards can be added and then enabled via Hardware Management Console (HMC) GUI or command line. B、The HMC allows access to the Advanced System Management Interface (ASMI), where the slots can be managed. C、If the empty slot was already allocated to an LPAR, the LPAR can use the card after the cfgmgr script has been run. D、The Hardware Management Console (HMC) GUI can guide a customer through the process of adding a card to an empty slot. 

考题 Which of the following interfaces is required to implement Workload Partition Mobility? ()A、 Workload Partitions Manager for AIXB、 Hardware Management Console (HMC) GUIC、 Integrated Virtualization Manager (IVM)D、 Advanced System Management Interface (ASMI)

考题 A System p distribution customer is very concerned about Reliability, Availability and  Serviceability (RAS). They are planning to install several p6 servers in their facilities and want to be able to move an LPAR from one System p to another.  Which of the following would accomplish this()A、System p servers using similar SAN storageB、System p servers must share an HMCC、System p servers must have the same level HMCD、System p servers with VIOS

考题 A System p administrator in a manufacturing customer plans to migrate an AIX 5.2 system to a new LPAR on an existing System p using VIOS.  Which of the following must be completed prior to this migration ()A、Upgrade system firmware to latest levelB、Upgrade to AIX 5.3C、Upgrade HMC to version 6.1D、Convert rootvg filesystems to JFS2

考题 System configurations on the HMC have been backed up correctly. After a restore, the partitions are defined with different characteristics than the running systems. What is the most probable cause of this problem?()A、The LPAR Configuration backup is corruptB、The LPAR Configuration has been altered using DLPARC、The LPAR Configuration backup was performed on a different HMCD、The LPAR Configuration has been altered through the Advanced System Management Interface (ASMI) on the server after the backup was performed

考题 Which statement must you issue to an already-running Automatic Storage Management (ASM) instance to prevent database instances from connecting to the ASM instance?() A、 ALTER SYSTEM KILL SESSIONB、 ALTER SYSTEM DISCONNECT SESSIONC、 ALTER SYSTEM QUIESCE RESTRICTEDD、 ALTER SYSTEM ENABLE RESTRICTED SESSION

考题 单选题Prior to implementing an LPAR system, which of the following needs to be done?()A A graphics monitor must be attached to the serverB Cluster System Management (CSM) software must be installedC The LPAR system must have an Hardware Management Console (HMC) connectedD Each LPAR must be configured with a CDROM for operating system installation

考题 单选题Which of the following can deploy system plans generated by the IBM System Planning Tool (SPT)?()A  The Hardware Management Console (HMC) and Integrated Virtualization Manager (IVM).B  The Hardware Management Console (HMC) and Advanced System Manager Interface (ASMI).C  Integrated Virtualization Manager (IVM) and Advanced System Manager Interface (ASMI).D  Integrated Virtualization Manager (IVM) and BladeCenter Advanced Management Module (AMM).

考题 单选题Which one of these statements is true regarding hot pluggable PCIe and PCI-X slots in a Power 550?()A Cards can be added and then enabled via Hardware Management Console (HMC) GUI or command line. B The HMC allows access to the Advanced System Management Interface (ASMI), where the slots can be managed. C If the empty slot was already allocated to an LPAR, the LPAR can use the card after the cfgmgr script has been run. D The Hardware Management Console (HMC) GUI can guide a customer through the process of adding a card to an empty slot. 

考题 单选题A customer has 4 POWER6 servers managed by a Hardware Management Console (HMC). They plan to install a second HMC for redundancy.  Which of the following statements correctlydescribes the dual HMC environment? ()A  To provide the Service Agent function, both HMCs must have Service Agent enabled and a dedicated modem and phone line.B  Authorized users must have the same username and password on both HMCs, so that every user of one HMC is automatically authorized on the other.C  Both HMCs are automatically notified of any changes that occur in the managed systems, so results of changes made to the managed system by one HMC are visible on theD  Both HMCs must be running the same software revision. Software maintenance must be performed on both HMCs at the same time, but one HMC should be disconnected from

考题 单选题Which of the following interfaces is required to implement Workload Partition Mobility? ()A  Workload Partitions Manager for AIXB  Hardware Management Console (HMC) GUIC  Integrated Virtualization Manager (IVM)D  Advanced System Management Interface (ASMI)

考题 单选题Which of the following statements is true regarding implementing Live Partition Mobility on two existing POWER6 based systems? ()A  The systems must use internal storage for boot purposes.B  All virtualized Ethernet adapters must be numbered below 10.C  The mobile partition’s network and disk access must be virtualized.D  Each system must be controlled by a different Hardware Management Console (HMC).

考题 单选题System configurations on the HMC have been backed up correctly. After a restore, the partitions are defined with different characteristics than the running systems. What is the most probable cause of this problem?()A The LPAR Configuration backup is corruptB The LPAR Configuration has been altered using DLPARC The LPAR Configuration backup was performed on a different HMCD The LPAR Configuration has been altered through the Advanced System Management Interface (ASMI) on the server after the backup was performed

考题 单选题A company is looking to improve upon their current remote management capabilities.  Thecompany must ensure that access is removed from all systems when a user is terminated and that administrators can remotely manage a system’s BIOS.  Which of the following remote management systems would support both these requirements?()A Remote management cardB Terminal servicesC Remote desktopD LDAP enabled IP KVM

考题 单选题A System p distribution customer is very concerned about Reliability, Availability and  Serviceability (RAS). They are planning to install several p6 servers in their facilities and want to be able to move an LPAR from one System p to another.  Which of the following would accomplish this()A System p servers using similar SAN storageB System p servers must share an HMCC System p servers must have the same level HMCD System p servers with VIOS

考题 单选题An administrator issued a command to update thefirmware of an Ethernet adapter on a partitioned system, but received an error. What is the most likely cause of the problem?()A The adapter must be taken offline prior to the firmware update.B The system has not been rebooted since the adapter was added to the LPAR.C The adapter must be assigned to the service partition prior to updating the firmware.D The adapter must be dynamically removed from the LPAR prior to updating thefirmware.

考题 单选题A System p administrator in a manufacturing customer plans to migrate an AIX 5.2 system to a new LPAR on an existing System p using VIOS.  Which of the following must be completed prior to this migration ()A Upgrade system firmware to latest levelB Upgrade to AIX 5.3C Upgrade HMC to version 6.1D Convert rootvg filesystems to JFS2

考题 单选题A system administrator needs to provision storage for a 200GB database. The database must have extremely low seek time. Which of the following is the BEST solution?()A A JBODB A RAID 50 arrayC A NASD A single SSD

考题 单选题Which statement must you issue to an already-running Automatic Storage Management (ASM) instance to prevent database instances from connecting to the ASM instance?()A  ALTER SYSTEM KILL SESSIONB  ALTER SYSTEM DISCONNECT SESSIONC  ALTER SYSTEM QUIESCE RESTRICTEDD  ALTER SYSTEM ENABLE RESTRICTED SESSION

考题 单选题A customer has an entry level Power System that is currently partitioned and managed by a Hardware Management Console (HMC). For operational reasons, it must be disconnected from the HMC and configured as a new development system.  How should the customer proceed to implement PowerVM Express and Integrated Virtualization Manager (IVM) on this Power System? ()A  Install a VIO server as an additional partition and DLPAR the resources from the existing partition to the VIO server.B  Create a service partition and install a VIO server. This will automatically move resources to the VIO server on reboot of the managed system.C  Delete all the existing LPARs, create a new LPAR and assign all the system resources to this LPAR and then install the VIO server on this LPAR.D  Reset the machine to Manufacturing Default Configuration and install the VIO server on the resulting partition created, which will own all system resources.

考题 单选题All of the following statements accurately describe process for administering file systems EXCEPT:()A A logical volume must exist prior to running the crfs command to create a file systemB A file system must be unmounted before it can be removedC Defining a file system imposes a structure on a logical volumeD Removing a file system using rmfs automatically removes the underling logical volume