● Project manager believes that modifying the project scope may provide added value for the customer. The project manager should (73) .
(73) A. change the scope baseline
B. contact the customer to determine if the change adds value
C. call a meeting of the change control board
D. change the project' s objectives
参考答案
更多 “ ● Project manager believes that modifying the project scope may provide added value for the customer. The project manager should (73) .(73) A. change the scope baselineB. contact the customer to determine if the change adds valueC. call a meeting of the change control boardD. change the project' s objectives ” 相关考题
考题
● Project(71)is an uncertain event or condition that, if it occurs, has a positive or a negative effect on at least one project objective, such as time, cost, scope, or quality.(71)A.riskB.problemC.resultD.data
考题
Project ______is an uncertain event or condition that,if it occurs,has a positive or a negative effect on at least one project objective,such as time,cost,scope,or quality.A.riskB.problemC.resultD.data
考题
以下关于Openstack租户Project说法错误的是()。
A、一个Project资源集合可供多个用户使用B、Project是Openstack各个服务中的一些可以访问的资源集合C、网络云各Project采用硬件共享,逻辑隔离的方式D、租户是一个有身份验证信息的API实体
考题
Project(71)is an uncertain event or condition that,if it occurs,has a positive or a negative effect on at least one project objective,such as time,cost,scope,or quality.A.riskB.problemC.resultD.data
考题
中国青少年发展基金会在网上的主页地址是()。
A.http://project-hopE.cydF.gov.cnB.http://project-hopE.cydF.acC.http://project-hopE.cydF.edu.cnD.http://project-hopE.cydF.com.cn
考题
Project()is an uncertain event or condition that,if it occurs,has a positiveor a negative effect on at least one project objective,such as time,cost,scope, or quality.A.risk
B.problem
C.result
D.data
考题
Project( )is an uncertain event or condition that,if it occurs,has a positive or a negative effect on at least one project objective,such as time,cost,scope,or quality.A.risk
B.problem
C.result
D.data
考题
在对原理图进行电气规则检查前,可以()打开规则设置界面。A.design-Document OptionsB.Project-Project OptionsC.Tools-Schematic PreferencesD.Project-Configuration Manager
考题
以下选项中哪个选项是根路径的表达方法?A.D:/Program Files/.Net/Project1B./root/.Net/Project1C../home/.Net/Project1D.file://D:/Program Files/.Net/Project1
热门标签
最新试卷