网友您好, 请在下方输入框内输入要搜索的题目:

题目内容 (请给出正确答案)

You are working on the cost budget for one project. Which of the following is true()

  • A、This process assigns cost estimates to project activities including risks and contingency plans.
  • B、The cost baseline will be used to measure variances and future project performance.
  • C、This process assigns cost estimates for expected future period operating costs.
  • D、The cost baseline is the expected cost for the project.

参考答案

更多 “ You are working on the cost budget for one project. Which of the following is true()A、This process assigns cost estimates to project activities including risks and contingency plans.B、The cost baseline will be used to measure variances and future project performance.C、This process assigns cost estimates for expected future period operating costs.D、The cost baseline is the expected cost for the project.” 相关考题
考题 Project trade-offs vary betweenA . risk, cost and schedule.B . direct cost, indirect cost, and resource availabilityC . quality, schedule and timeD . cost, quality and scheduleE . contract terms, scope and budget

考题 The Work Breakdown Structure (WBS) is the basis for communicating:A.Project scope, cost control, schedule, qualityB.Project objectives, dependencies, plan, cost controlC.Project scope, schedule, staffing, cost controlD.Project scope, quality, schedule, dependenciesE.Project budget, schedule, risk factors, work assignments.

考题 Which of the following is referred to as sunk cost:A . management reserveB . contingency fundC . cost budgeted for construction under waterD . expended funds over which there is no further controlE . forecasted budget over-runs

考题 Which of the following is considered a direct cost for producing a widget?A . The cost of the materials used to produce a widget.B . The labor costs of the workers who actually produced the widget.C . The rent for the building in which the widget was manufacturedD . The salary of senior management and the project sponsorE . A and B only

考题 Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the:A . Baseline costsB . Budgeted costs.C . Estimates upon completion costsD . Scheduled costsE . None of the above

考题 A negative cost variance and positive schedule variance means:A The project is under budget and ahead of scheduleB The project is over budget and behind scheduleC The project is over budget and ahead of scheduleD The project will be overrun but ahead of schedule at completion

考题 A Project Status Report would include all of the following except:A Cost and schedule reportsB Changes to scope. cost or scheduleC Narrative explanation of variancesD Personnel problems on the projectE Upcoming activities

考题 23 Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the:A. Baseline costsB Budgeted costs.C. Estimates upon completion costsD. Scheduled costsE. None of the above

考题 35 Which of the following is considered a direct cost for producing a widget?A. The cost of the materials used to produce a widget.B. The labor costs of the workers who actually produced the widget.C. The rent for the building in which the widget was manufacturedD. The salary of senior management and the project sponsorE. A and B only

考题 65 Which of the following is referred to as sunk cost:A. management reserveB. contingency fundC. cost budgeted for construction under waterD. expended funds over which there is no further controlE. forecasted budget over-runs

考题 185 Life Cycle Costing:A. is the concept of including all costs within the total life of a project.B. is an activity devoted to optimizing cost/performanceC. is an activity of appraising the cost and technical performance of a completed project.D. is a process of predicting the life of a project.E. None of the above

考题 105 Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the:A. Baseline costsB. Budgeted costs.C. Estimates upon completion costsD. Scheduled costsE. None of the above

考题 You are working on the cost budget for one project. Which of the following is true() A.This process assigns cost estimates to project activities including risks and contingency plans.B.The cost baseline will be used to measure variances and future project performance.C.This process assigns cost estimates for expected future period operating costs.D.The cost baseline is the expected cost for the project.

考题 67 Life Cycle Costing:A. is the concept of including all costs within the total life of a project.B. is an activity devoted to optimizing cost/performanceC. is an activity of appraising the cost and technical performance of a completed project.D. is a process of predicting the life of a project.E. None of the above.

考题 ● The scope of a project can be expected to change if:A The project manager must provide cost estimates without having a design conceptB Oversimplification (underestimating) of the nature of the work occursC The project manager is assigned after the project is defined, and the cost and schedule are approvedD A clear objective is not providedE All of the above are possible based upon the situation

考题 ● The Work Breakdown Structure (WBS) is the basis for communicating:A Project scope, cost control, schedule, qualityB Project objectives, dependencies, plan, cost controlC Project scope, schedule, staffing, cost controlD Project scope, quality, schedule, dependenciesE Project budget, schedule, risk factors, work assignments.

考题 Estimating schedule activity costs involves developing an(69)of the costs of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in most application areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estimates are generally expressed in units of(70)to facilitate comparisons both within and across projects.The(71 )describes the business need, justification, requirements, and current boundaries for the project. It provides important information about project requirements that is considered during cost estimating.A.accuracyB.approximationC.specificationD.summary

考题 ● ()is primarily concerned with defining and concerning what is and is not included in the project.()A. Project Time ManagementB. Project Cost ManagementC. Project Scope ManagementD. Project Communications Management

考题 ( )is the approved version of the time-phased project budget,excluding any management reserves,which can only be changed through formal change control precedures and is used as a basis for comparison to actual results.A.The control accountsB.Funding requirementC.The cost estimatesD.The cost baseline

考题 ( )is a process of monitoring the status of the project to update the project costs and manage changes is the cost baseline.A.Plan Cost Management B.Estimate Costs C.Determine Budget D.Control costs

考题 Managing risk and documenting them is very important in project planning process.You are in the process of defining key risks, including constraints and assumptions, and planned responses and contingencies. These details will be included in the(73) .A.project management plan B.project baseline C.riskresponse plan D.risk baseline

考题 A project is a[temporary](请作答此空)of unique,complex,and connected activities having one goal or purpose and that must be completed by a specific time,within budget,and according to( ).Project management is the process of scoping,planning,staffing,organizing,directing,and controlling the development of a(n)( )system at a minimum cost within a specified time frame.For any systems development project,effective project management is necessary to ensure that the project meets the( ),is developed within an acceptable budget,and fulfills customer expectations and specifications,Project management is a process that starts at the beginning of a project,extends through a project,and doesn't culminate until the project is completed.The prerequisite for good project management is a well-defined system development process.Process management is an ongoing activity that documents,manages the use of,and improves an organization s chosen methodology(the“process”)for system development,Process management is concerned with the activities,deliverables,and quality standards to be applied to( )project(s).A.task B.work C.sequence D.activity

考题 Earned value management(EVM)integrates the scope baseline with the()baseline,along with schedule baseline,to form the performance,which helps the project management team assess and measure project performance and progress.A.qulity B.risk C.change D.cost

考题 The cost performance index(CPI) is the ratio of earned value to ( ) and can be used to estimate the projected cost of completing the project. A. cost variance B.planneD.cost C.PlanneD.value D.actual cost

考题 ( )is a process of monitoring the status of the project to update the project costs and manage changes to the cost baselineA.Plan Cost Management B.Estimate Costs C.Determine Budget D.Control Costs

考题 Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating. 空白(3)处填()A、project scope statementB、statement of workC、project management planD、projectpolicy

考题 单选题You are working on the cost budget for one project. Which of the following is true()A This process assigns cost estimates to project activities including risks and contingency plans.B The cost baseline will be used to measure variances and future project performance.C This process assigns cost estimates for expected future period operating costs.D The cost baseline is the expected cost for the project.