网友您好, 请在下方输入框内输入要搜索的题目:

题目内容 (请给出正确答案)
单选题
You are working on the cost budget for one project. Which of the following is true()
A

This process assigns cost estimates to project activities including risks and contingency plans.

B

The cost baseline will be used to measure variances and future project performance.

C

This process assigns cost estimates for expected future period operating costs.

D

The cost baseline is the expected cost for the project.


参考答案

参考解析
解析: 暂无解析
更多 “单选题You are working on the cost budget for one project. Which of the following is true()A This process assigns cost estimates to project activities including risks and contingency plans.B The cost baseline will be used to measure variances and future project performance.C This process assigns cost estimates for expected future period operating costs.D The cost baseline is the expected cost for the project.” 相关考题
考题 The Cost Performance Index is computed as:A . budget cost of work performed divided by actual cost of work performedB . budget cost of work performed minus actual cost of work performedC . budget cost of work performed minus budget cost of work scheduledD . budget cost of work scheduled divided by budget cost of work performedE . actual cost of work scheduled divided by budget cost of work performed

考题 Which of the following is referred to as sunk cost:A . management reserveB . contingency fundC . cost budgeted for construction under waterD . expended funds over which there is no further controlE . forecasted budget over-runs

考题 65 Which of the following is referred to as sunk cost:A. management reserveB. contingency fundC. cost budgeted for construction under waterD. expended funds over which there is no further controlE. forecasted budget over-runs

考题 114 The Cost Performance Index is computed as:A. budget cost of work performed divided by actual cost of work performedB. budget cost of work performed minus actual cost of work performedC. budget cost of work performed minus budget cost of work scheduledD. budget cost of work scheduled divided by budget cost of work performedE. actual cost of work scheduled divided by budget cost of work performed

考题 You are working on the cost budget for one project. Which of the following is true() A.This process assigns cost estimates to project activities including risks and contingency plans.B.The cost baseline will be used to measure variances and future project performance.C.This process assigns cost estimates for expected future period operating costs.D.The cost baseline is the expected cost for the project.

考题 ● You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week period. As of today, you've spent ¥260,000 of your budget to complete work that you originally expected to cost ¥280,000. According to your schedule, you should have spent ¥300,000 by this point. Based on these circumstances, your project could be BEST described as (74) .(74)A.Ahead of scheduleB.Behind scheduleC.On scheduleD.Having not enough information provided

考题 You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week perio.As of today, youve spent ¥260,000 of your budget to complete work that you originally expected to cost ¥280,000. According to your schedule, you should have spent ¥300,000 by this point. Based on these circumstances, your project could be BEST described as (74) .A.Ahead of scheduleB.Behind scheduleC.On scheduleD.Having not enough information provided

考题 Why are you working in a field other than the one in which you have a degree?

考题 ( )is the approved version of the time-phased project budget,excluding any management reserves,which can only be changed through formal change control precedures and is used as a basis for comparison to actual results.A.The control accountsB.Funding requirementC.The cost estimatesD.The cost baseline

考题 You are working on the cost budget for one project. Which of the following is true()A、This process assigns cost estimates to project activities including risks and contingency plans.B、The cost baseline will be used to measure variances and future project performance.C、This process assigns cost estimates for expected future period operating costs.D、The cost baseline is the expected cost for the project.

考题 You are working on Oracle Database 10g, which is in ARCHIVELOG mode. All the archived log files are intact.  In which scenario would performing a recovery require the opening of the database with the RESETLOGS option?()A、loss of a tempfileB、loss of a system data fileC、loss of one of the control filesD、loss of one of the tablespacesE、loss of a member from each redo log groupF、loss of the only member of an unarchived redo log group

考题 In which two cases would you perform only consistent backup?()A、You are working on a database where downtime is not tolerated.B、You are working on a database where downtime can be tolerated.C、You are working on a database that operates in ARCHIVELOG mode.D、You are working on a database that operates in NOARCHIVELOG mode.E、You are working on a database where all the tablespaces are locally managed.F、You are working on a database where control files and redo log files are multiplexed.G、You are working on a database where control files and redo log files are not multiplexed.

考题 You work in a company which uses SQL Server 2008. You are the administrator of the company database. Now you are in charge of a SQL Server 2008 instance. There are queries that have an estimated execution cost less than 3. You intend to configure the instance, make it use a single thread for these queries. In the options below, which sp_configure configuration option should you set?()A、You should set query governor cost limitB、You should set cost threshold for parallelismC、You should set priority boost D、You should set precompute rank

考题 单选题You are working on the cost budget for one project. Which of the following is true()A This process assigns cost estimates to project activities including risks and contingency plans.B The cost baseline will be used to measure variances and future project performance.C This process assigns cost estimates for expected future period operating costs.D The cost baseline is the expected cost for the project.

考题 单选题Which one of the following repair will cost the least cost?()A Routine docking repairB Voyage repairC Damage repairD Conversion

考题 单选题Wise buying is a positive way in which you can make your money go further. The ()you go about purchasing an article or a service can actually ()you money or can add ()the cost. Take the ()example of a hairdryer. If you are buying a hairdryer, you might ()that you are making the ()buy if you choose one ()look you like and which is also the cheapest ()price. But when you get it home you may find that it ()twice as long as a more expensive ()to dry your hair. The cost of the electricity plus the cost of your time could well ()your hairdryer the most expensive one of all. So what principles should you ()when you go out shopping? If you ()your home, your car or any valuable ()in excellent condition, you’ll be saving money in the long () Before you buy a new (),talk to someone who owns one. If you can, use it or borrow it to check it suits your particular () Before you buy an expensive (),or a service, do check the price and ()is on offer. If possible, choose ()three items or three estimates. 请在第()处填上正确答案。A functionB purposeC goalD task

考题 单选题You are working on Oracle Database 10g, which is in ARCHIVELOG mode. All the archived log files are intact. In which scenario would performing a recovery require the opening of the database with the RESETLOGS option?()A  loss of one of the tablespacesB  loss of a system data fileC  loss of one of the control filesD  loss of a tempfileE  loss of the only member of an unarchived redo log groupF  loss of a member from each redo log group

考题 单选题You are working on Oracle Database 10g, which is in ARCHIVELOG mode. All the archived log files are intact.  In which scenario would performing a recovery require the opening of the database with the RESETLOGS option?()A loss of a tempfileB loss of a system data fileC loss of one of the control filesD loss of one of the tablespacesE loss of a member from each redo log groupF loss of the only member of an unarchived redo log group