Estimating activity durations uses information on activity scope of(),required resource types, estimated resource quantities, and resource calendars.
A

milestone

B

baseline

C

quality

D

work


参考答案

参考解析
解析: 该题的关键词为"required resource types、estimated resource quantities、 resource calendars",其语句结构为"Estimating activity durations(主语)uses(谓语)information on activity scope of_____(宾语)",含义为"估算活动工期应用什么活动范围的信息",结合前面的关键词,此处应该识别出估算活动工期对应的输入项,因而选择工作范围,选择选项D。
更多 “单选题Estimating activity durations uses information on activity scope of(),required resource types, estimated resource quantities, and resource calendars.A milestoneB baselineC qualityD work” 相关考题
考题 Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order. A.activity duration estimating, schedule developing, activity resource estimatingB.activity resource estimating, activity duration estimating, schedule developmentC.schedule developing, activity resource estimating, activity duration estimatingD.activity resource estimating, schedule developing, activity duration estimating

考题 The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.A.estimatingB.definingC.planningD.sequencing

考题 The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.A.estimatingB.definingC.planningD.sequencing

考题 ● (73) is one of the techniques used for estimating activity durations.(73)A.Analogous EstimatingB.Precedence Diagramming Method (PDM)C.Dependency DeterminationD.Schedule network Templates

考题 ● On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and (70) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.A.time estimatingB.cost estimatingC.project planningD.schedule development

考题 Estimating activity durations uses information on activity scope of(74) , required resource types, estimated resource quantities, and resource calendars.A.milestoneB.baselineC.qualityD.work

考题 ● Estimating activity durations uses information on activity scope of (74),required resource types, estimated resource quantities, and resource calendars.(74)A. milestoneB. baselineC. qualityD. work

考题 Estimate activity durations is the processof estimating the number of work periods to complete indivities with estimatedresources . the tools and technques is not including().A.expert judgmentB.analogous estimatingC.requiremen tstraceability matrixD.three-point estimating

考题 ● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.(71)A.activity duration estimating, schedule developing, activity resource estimatingB . activity resource estimating, activity duration estimating, schedule developmentC.schedule developing, activity resource estimating, activity duration estimatingD.activity resource estimating, schedule developing, activity duration estimating

考题 ______is one of the techniques used for estimating activity durations.A.Analogous EstimatingB.Precedence Diagramming Method(PDM)C.Dependency DeterminationD.Schedule network Templates

考题 Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other.______is following the process-Estimate Activity Durations.A.Develop ScheduleB.Estimate Activity ResourcesC.Define ActivitiesD.Sequence Activities

考题 The process of(72)schedule activity durations uses information on schedule activity scope of work,required resource types,estimated resource quantities,and resource calendars with resource availabilities.A.estimatingB.definingC.planningD.sequencing

考题 Estimating schedule activity costs involves developing an (74) of the cost of the resources needed to complete each schedule activity.A.accuracyB.approximationC.specificationD.summary

考题 Estimating schedule activity costs involves developing an(4)of the cost of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in mostapplication areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estmates are generally expressed in units of(5)to facilitate comparisions both within and across projects. The(6)describes important information about project requirement that is considered during cost estimating.A.accuracyB.approxinationC.specificationD.summary

考题 On some projects,especially ones of smaller scope,activity sequencing,activity resource estimating.Activity duration estimating,and (71) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.A.project planningB.time estimatingC.cost estimatingD.schedule development

考题 ( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project.A.ParametricB.AnalogousC.Three-pointD.Expert judgment

考题 Recent federal regulatory activity has been _______ to protect the privacy of consumer’s personal information.A.implementing B.implement C.implemented D.implements

考题 ()is a technique for estimating the duration or cost of activity or a projecy using historical data orm a similar activity or project.A.Analogous estimating B.Parametric estimating C.Three-Point estmating D.Bottom-Up estimating

考题 PDM is a method of constructing a project schedule network diagram that uses boxesor rectangles, referred to as nodes, to represent activities and connects them with arrows thatshow the dependencies.This method includes following types of dependencies or precedence relationships:F-S, the initiation of the successor activity, depends upon the completion of thepredecessor activity.() , the initiation of the successor activity, depends upon the initiation of thepredecessor activity. A.F-S B.F-F C.S-F D.S-S

考题 Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( ) , and schedule control by order. A.activity duration estimating, schedule developing, activity resource estimating B.activity resource estimating, activity duration estimating, schedule development C.schedule developing, activity resource estimating, activity duration estimating D.activity resource estimating, schedule developing, activity duration estimating

考题 ( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project. A.Parametric B.Analogous C.Three-point D.Expert judgment

考题 Estimating activity durations uses information on activity scope of ( ) , required resource types, estimated resource quantities, and resource calendars. A.milestone B. baseline C.quality D. work

考题 Estimating activity durations uses information on activity scope of(),required resource types, estimated resource quantities, and resource calendars.A、milestoneB、baselineC、qualityD、work

考题 (1) is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies or precedence relationships: (2) the initiation of the successor activity, depends upon the completion ofthe predecessor activity.(3) the initiation ofthe successor activity, depends upon the initiation ofthe predecessor activity. 空白(3)处填()A、F-SB、F-FC、S-FD、S-S

考题 Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.A、activity duration estimating, schedule developing, activity resource estimatingB、activity resource estimating, activity duration estimating, schedule developmentC、schedule developing, activity resource estimating, activity duration estimatingD、activity resource estimating, schedule developing, activity duration estimating

考题 单选题On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and()are so tightly linkedthat they are viewed as a single process that can be performed by a person over a relatively short period of time.A time estimatingB cost estimatingC project planningD schedule development

考题 单选题Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.A activity duration estimating, schedule developing, activity resource estimatingB activity resource estimating, activity duration estimating, schedule developmentC schedule developing, activity resource estimating, activity duration estimatingD activity resource estimating, schedule developing, activity duration estimating

考题 单选题Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating. 空白(2)处填()A activityB workC currencyD time